Professional Documents
Culture Documents
C/L OF BEARING
150MT CRANE LOAD CHART GENERAL NOTES:
5500 5500 5500 5500 5500 5500 5500 5500
C/L OF BEARING
2400
CC CRIBS CONNECTIONS & CRANE CAPACITY (IN MT) SPECIFICATIONS
CLAMPING ARRANGEMENT AS 44000 STAGE-6 BOOM LENGTH (M)
1. ALL DIMENSIONS ARE IN MM.
PER RDSO/B/1484/4R1 BEARING C/C WORKING MEMBER/DETAILS SPECIFICATION
RADIUS (M)
2. ALL LEVELS ARE IN METER.
CC CRIBS WITH ISA 75X75X8 2 4 6 8 10 12 14 16 18 21.1 25.4 29.5 35.1 LAUNCHING GIRDERS
600 SQ EACH BLOCK
STAGE-4 1. AVAIL TRAFFIC AND POWER BLOCK OF 4 HOURS. 3. ALL STRUCTURAL STEEL FOR ERECTION CONFORM TO IS-2062-2011 -GRADE-B0, E-250 FULLY
5500 5500 5500 5500 5500 5500 5500 5500 3.5M 90.0 - - - ALL GUSSET PLATES IS:2062-2011 GR-B0 QUALITY,
600 600 2. LAUNCHING GIRDERS (SPLICED LOCATION) AND RAILS SHALL BE REMOVED ONLY BETWEEN
VERTICAL ISA-50X50X6 KILLED AND NORMALIZED.
AT 1500 C/C
ALL STIFFENERS PLATES GRADE E-250
44000 LG. -1000mm 4.0M 90.0 75.0 60.0 - 4. ALL BOLTS & NUTS SHALL CONFIRM TO IS:4000-1992 AND IRS B1-2001
25 DIA HOLDING
CRIB CAPS WITH ISA-75X75X8 STAGE-2 BEARING C/C 1. BSG GIRDER SHALL BE LIFTED USING HYDRAULIC JACK OF 250MT CAPACITY (GRID-B & D) TO
JACK-250MT JACK-250MT GRIDS-17 & 1 AS SHOWN IN ELEVATION. ALL BRACING MEMBERS
5. ALL WELDS SHALL CONFIRM TO IS:816 & SHOULD BE 8MM MIN. U.N.O.
UNDER EACH CRIB RDSO/B-10414/R 3. THE BSG SHALL BE FURTHER LIFTED ABOVE THE ROLLING BEAMS ABOUT 100 TO 150mm USING
800 PLATFORM SHS 50X50X4.0 4.5M 90.0 75.0 60.0 -
DOWN BOLTS
ERECT BUILT UP BEAMS WITH B3-4-ISMB600 (LAUNCHING GIRDER) USING 1X150 T CRANE OVER MS CHQD. PL. @ 200 C/C WELDED 4MM CRIBS CONNECTIONS, CLAMPS etc.. RDSO/B1-1484/4R1
LINKS 8TOR 250 C/C RAIL FORMATION LVL. JACKS AT JACKING POINTS AND WOODEN BLOCKS AT BEARING POINTS FOR REMOVING OF
6MM THK THK
5.0M 90.0 72.5 60.0 38.0 6. NO DIMENSIONS SHOULD BE SCALED/MEASURED FROM THE DRAWING. ONLY WRITTEN
C/L OF BEARING
1. THE PROPOSED BSG SHALL BE ASSEMBLED OVER THE CRIB LOCATIONS ABOUT 1200mm CC CRIBS. IS: 3757-1992, IS: 4000-1992,
C/L OF BEARING
BOTH WAYS
12 tor 125 C/C LAUNCHING GIRDERS, CC CRIBS, RAIL CLUSTER BEAMS AND SLEEPERS ETC (RAILWAY SPAN 6MM WELD 6.0M 87.8 66.8 60.0 38.0
ALL BOLTS & NUTS DIMENSIONS SHOULD BE FOLLOWED.
2. JACK SHALL BE REMOVED AND BSG SHALL BE PLACED OVER ROLLING CAGE & BSG SHALL BE CC CRIB CONNECTIONS, CLAMPS etc.. IRS-B1-2001
B/W TOP & BOTTOM ABOVE GROUND LEVEL. ALL ROUND
7. CONSTANT WATCH AND PRECAUTIONARY ARRANGEMENT (SUCH AS SAFETY
450
8 6
RDSO/B1-1484/4R1
SIDE SLEWED USING JACKS OF 30T CAPACITY. FORCE SHALL BE APPLIED AT BOTTOM BEAM OF BRACING GRID-10 TO 17). 7.0M 79.6 61.2 59.1 38.0 WELDING PROCEDURE & QUALITY IS: 9595, IS: 814, IS: 816
FND BOTTOM LVL: 2. BOTH ARCHES AND CROSS BEAMS WITH ISMB 600 ALONG WITH TOP CONNECTING BEAMS 3600X1800
ISA 75X75X8 ON ALL
3600X1800 =12500=
HORIZONTAL
ISMC150 AT 1000C/C NET/HARNESS/HELMET) SHALL BE MADE AVAILABLE DURING ERECTION OF THE TEMPORARY
99.807 M20-150 THK PCC
BSG AT BEARING LOCATION SIMULTANEOUSLY AT BOTH ENDS OF BSG. ALSO, WEDGE FACES WITHIN CRIBS 4. JACKING FORCE SHALL BE APPLIED TO SUPPORT THE BSG. WOODEN PLANKS ABOUT 100 to (LENGTH-1000mm)
8.0M WOODEN PLANKS, BLOCKS IS: 883-1994
AS PER RDSO DRAWING RDSO/B/10414 SHALL BE MADE. 6 ISMA-50X50X6 69.60 56.1 52.7 38.0
STRUCTURES & LAUNCHING OF BOW STRING GIRDER.
8150*
8150*
150mm SHALL BE REMOVED AT CENTER LINE OF BEARING. AT 1000C/C
300
3. METALLISING AND PAINTING SHALL BE DONE ALONG WITH TESTS TO VERIFY THE QUALITY OF ARRESTORS (FIXED TO RAILS USING RAIL CLAMPS) SHALL BE USED TO AVOID OVER ROLLING OF LAUNCHING GIRDER 9.0M 61.20 52.1 49.3 38.0 52Kg RAILS IS: 3443-1980
1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 1800 5. NOW JACK SHALL BE LOWERED UP TO THE LEVEL OF WOODEN PLANKS. AGAIN SUPPORT THE
DETAIL -X2 8. THE ERECTION WORK NEAR RAILWAY TRACK SHALL BE EXECUTED UNDER SUPERVISION OF
HYDRAULIC HYDRAULIC BSG DURING PUSHING. SLEWING SHALL BE DONE AT RATE OF 173.2MM/SEC. PULLING WIRE ROPE-32 DIA IS: 14268-1995
WELDING WORK AND LIFTING OPERATION SHALL START. NOTE: ALL MATERIAL SHALL CONFORM TO IS:2062-2011
1200
4000
300 TH COMPACTED 3600 SQ. SQ. SQ. SQ. SQ. SQ. SQ. 3600 SQ. SQ. SQ. SQ. SQ. SQ. SQ. =13140= GRADE-A, E-250 10.0M 54.1 48.1 45.9 38.0 RAILWAY SUPERVISOR.
JACK-250MT JACK-250MT BSG ON JACK TO REMOVE WOODEN PLANKS ABOUT 100 to 150mm.
450
LAYER OF MOORUM
150 4. HYDRAULIC JACK OF 250T IS ARRANGED TO LIFT THE BSG & TO ERECT THE CRIBS STAGE BY 3. SLEWING SHALL BE STOPPED ONCE THE BSG REACHES OVER CC CRIBS ALONG GRID- E/1, G/1, M25 CONCRETE-RCC
450
450
FOUNDATION DETAILS FOR -F1 1200 1200 1200 1200 1200 1200 1200 9. FLAG MAN ON EITHER SIDE SHALL BE POSTED DURING THE BLOCK PERIOD BY RAILWAY.
300
150 1200 1200 1200 1200 1200 1200 1200 12.0M 43.2 41.3 39.6 34.2
F3 F2 F2 F2 F2 F2 F2 F2 F3 F3 F2 F2 F2 F2 F2 F2 F2 F3 6. THE LOWERING OPERATION CONTINUED TO PLACE THE "BSG" TO ITS FINAL POSITION OVER THE IS: 456-2000
SECTIONAL VIEW STAGE AT ALL THE FOUR JACKING LOCATIONS OF BSG (600MM FROM C/L OF BEARINGS). E/9 & G/9 ROLLING CAGE SHALL BE ARRESTED USING WEDGES. M20 CONCRETE- PCC
150 150
600
3000 3000 3000 3000 3000 3000 3000
600
6000 3000 3000 3000 3000 3000 3000 3000 6000 BEARINGS. 14.0M 34.3 35.1 34.5 30.6 10. BANNER FLAG ON EITHER SIDE WILL BE ERECTED AS PER IRPWM ON EITHER SIDE OF TRACK.
4000 6000 300 300 300 300 300 300 300 6000 4. BSG GIRDER SHALL BE LIFTED USING HYDRAULIC JACK OF 250MT CAPACITY (GRID-E & G) TO 300 300 300 300 300 300 300 Fe500 HYSD REINFORCEMENT BARS IS: 1786-2008
7. AT ALL THE FOUR BEARING LOCATIONS LOWERING OPERATION SHALL BE DONE CRANE CAPACITY 150 MT 11. BEFORE EXECUTION OF WORK SITE-IN-CHARGE SHOULD INSURE THAT THE DIMENSIONS GIVEN IN
ATTACH THE ROLLERS UNDER EACH VERTICAL HANGERS FOR LONGITUDINAL PULLING AS "DET-X1" X2 WINCH MECHANISM TYPE POWER DRIVEN ONLY
THIS DRAWING ARE VERIFIED AT SITE.
150
SIMULTANEOUSLY NOT MORE THAN 100 to 150mm AT A TIME . NO. OF CRANES USED 1 NOS
FRL :99.257
FRL :99.257
6500 4 @ 600 = 2400 STAGE-2 SHOWN IN ELEVATION. STAGE-4 BOW STRING GIRDER RDSO/B-10414 SERIES
12. ALL THE WORK SHALL BE DONE PREFERABLY IN DAY LIGHT, IF BY ANY REASON, IT HAS TO BE
M20-150 THK PCC STAND-BY CRANE 1 NOS
ELEVATION ALONG GRID- B & D ELEVATION ALONG GRID B & D ISMC 300 B/B AT EACH CRIB GAD DRG NO- SWR/CN/BNC/BR/183/ALT-1-2020
CONTINUED ALL BEYOND SUNSET. THE AREA SHALL BE LIGHTED BY FLOOD LIGHT.
28 28 28
17 17 1 LOCATIONS OPERATING RADIUS (REQ) 14 M SWR/CN/BNC/ST/14-2022
7 SUB STRUCTURE DRG-
150
WOODEN BLOCK
6500 3000
1200
300 13. AT THE TIME OF EXECUTION OF WORK AT SITE, RESPECTIVE RAILWAY AUTHORITIES SHALL BE
BOOM LENGTH (REQ) 35.1 M
6500
Ø20
M25-450 THK RCC F2 F2 F2 F2 F2 F2 PLATFORM WITH CONSULTED
46 46 46 SHEETING PLATE 75 % CRANE LIFTING CAPACITY 0.75 X 30.6 X 1 = 22.9 MT
3000
3000
1800
00 A 28 A A 28 A A 28 14. TRACK SHALL BE PROTECTED IN ACCORDANCE WITH CLAUSE 807 AND 808 OF INDIAN
SQ.
3000
AL2 3000 3000 3000 REQUIRED LIFTING LOAD 8.0MT
AL1 BRAC RAILWAYS P.WAY MANUAL.
6500
2750
2750
300 1800 14050 1800
1200 ING
F2
Ø20 ISMC ING BRACING
F3 600 F2 F2 F2 F2 F2 F2 F2 F3 600 F3 600 F2 F2 F2 F2 F2 F2 F2 F3 600 F3 F2 F2 F2 F2 F2 F2 F2 F3 BRAC 100
554
3000
3000
3000
4 @ 600 = 2400
2800 3300 00 300 100 ISA 75X75X8 ON ALL "IT IS CERTIFIED THAT WEIGHT OF GIRDERS ARE 8T. HENCE BY USING 15. CRS SANCTION SHOULD BE OBTAINED FOR LAUNCHING OF GIRDER OVER RAILWAY TRACK.
ISMC
730
44000 DR2
3000
3000
1800
B B B
4000
B B 1X150MT CAPACITY CRANE WITH DULY ADOPTING 14.0M RADIUS &
SQ.
FACES WITHIN CRIBS
1710
BEARING C/C
ACTIVITY TABLE 16. TRAFFIC AND POWER BLOCKS TO BE ARRANGED FOR ERECTION OF STEEL GIRDERS OVER
8400*
BOOM LENGTH 35.1M WHICH IS ADEQUATE TO LIFT THE GIRDERS
1511 @ 3=4533
F2
2300
B3-4 ISMB600
B3-4 ISMB600
B3-4 ISMB600
B3-4 ISMB600
DR1
BOTH FACE
300
6500 17. TEMPORARY TOWER STAGING ADJOINING THE RAILWAY TRACK SHALL BE ERECTED UNDER
ISMC 100
CC CRIBS
C 100 CE
ALL THE CRIBS MODULES SHALL BE ERECTED ALONG
ISM TH FA
6570
6570
CONNECTIONS &
BRACINGS WITH BRACING. ERECTION OF BUILT-UP GIRDER SPEED RESTRICTION NON-STOP AND 20KMPH & INFRINGING TRACK TO BE BLOCKED.
BO
CLAMPING
2500
7000
F1 F1 F1 F1 F1 F1 GRIDS ON BOTH FACE DESCRIPTION CAPACITY QTY(NOS) 4 HOURS
PER STAND BY TOTAL BLOCK-1 SHOWN AND FIXING FIRMLY BY WELDING.
ENARC
RDSO SCHEDULE OF DIMENSIONS.
1 TO 9
1 TO 9
2750
TM052
RDSO/B/1484/4R1 22 04 26 PULLING THE BSG OVER RAILWAY SPAN USING PULLING
6500 ROLLER SET 100MT
2500
19. ALL NECESSARY SAFETY PRECAUTIONS SHALL BE TAKEN WHILE WORKING NEAR RAILWAY
4000
4000
C C C C C
11000
6000
6500
AL1 AL2 AL1 AL2 AL1 AL2 ING WINCHES TILL IT REACHES THE OTHER END OF THE PIER
9800
13140
13140
14600
15600
BRAC TRACK FOR PROTECTION OF TRESPASSERS WORKMEN AND RAIL TRAFFIC.
C/L OF CARRIAGEWAY BRAC 100 HYDRAULIC LIFTING JACK 250MT 04 02 06
LH16 LH16 LH16
ISMC ISMC ING BEARINGS.
F1
K
K
3000 LH17 LH17 LH17 100 RAIL FORMATION 20. SCHEME OF ACTIVITIES OUTSIDE RAILWAY TRACK AREA MAY BE MODIFIED / ALTERED TO SUIT
7000
2750
AC
AC
AC
K
K
K
BOTH FACE
02 02 04
K
HYDRAULIC PUSHING JACK 30MT
AC
AC
AC
2500
3000
AC
AC
AC
6000
''M''
ISMC 100
450
C 100 CE
LVL
150
TR
TR
TR
300
LOWER THE GIRDER OVER BEARINGS WITH JACKS AND
6500
300
4 HOURS SITE CONDITIONS AT THE TIME OF EXECUTION, WITHOUT COMPROMISING ON THE STRUCTURAL
ISM TH FA
TR
TR
TR
6570
6570
TR
TR
TR
K
Ø20
6500
RE
RE
RE
PULLING WINCH 50MT 02 02 04
AC
K
K
BLOCK-2 FIXING OF AC SHEET AND POLYPROPYLENE NET BELOW
RE
RE
RE
AC
3000
XG
XG
XG
3000
AC
Ø20
BO
TU
TU
TU
00
& SAFETY ASPECTS.
TR
TU
TU
TU
F FU
F FU
F FU
FE
FE
FE
TR
00 PLAN VIEW
TR
RESTRAINING WINCH 50MT 02 02 04 THE BOWSTRING GIRDER.
F FU
F FU
F FU
6000 6000 6000
RE
''N''
2750
O
RE
2500
XG
JACK FORCE
300
21. SAFETY NET SHALL BE PROVIDED UNDER THE GIRDERS WHILE FIXING THE BRACING AND
O
TU
B3-4 ISMB600
15 1200 15 15
/L
/L
/L
TU
O
F3 600 JACK-250MT F2 F2 F2 F2 F2 F2 JACK-250MT
F3 600 F3 600 F2 F2 F2 F2 F2 F2 F3 600 F3 F2 F2 F2 F2 F2 F2 F3 TYPICAL CROSS SECTION ALONG ALL CRIB GRIDS
F FU
11 11
FE
/L
11
/L
/L
WIRE ROPE 100MT 04 02 06
C
F FU
/L
/L
/L
1800
C
5 5 5 SHUTTERING WORK. ALTERNATIVELY 4MM THK. MS PLATE SHOULD BE PERMANENTLY WELDED
BLOCK-3 REMOVAL OF REMAINING CC CRIBS, BRACINGS OVER
3000
3000
3000
O
2 HOURS
C
LH16
3000
3000
1800
D D D D D
/L
O
SQ.
RAILWAY SPANS AND CLEARING THE SITE.
/L
C LH17 PULLING WINCH PULLING WINCH PULLING WINCH NOTE- OVER RUNNING TRACKS HAVING 25KV OVERHEAD TRACTION.
/L
2266
CC CRIBS CONNECTIONS &
C
2300
3300 35
C
3000
3000
730
74
300
JACK-250MT JACK-250MT
F2
300
F1 F1 1. ALL EQUIPMENTS TO BE TESTED WITH 125% OF ESTIMATED LOADS 22. ALL ROLLING ARRANGEMENT/ROLLERS SHALL BE PROVIDED BELOW VERTICAL HANGERS ONLY.
700
PER RDSO/B/1484/4R1 600
F3 F2 F2 F2 F2 F2 F2 F2 F3 300 F3 600 F2 F2 F2 F2 F2 F2 F2 F3 600 F2 F2 F2 F2 600 F3 F2 F2 F2 F2 F2 F2 F2 F3
2. THE CAPACITY CHECK CERTIFICATE OF EQUIPMENT SHALL BE SUBMITTED TO THIS 23. MAXIMUM BASE PRESSURE ON SOIL IS = 9.78T/M2 WITH ALLOWABLE BEARING CAPACITY
730
748
=2800=
3000
3000
1800
1800
TO HASSAN TO MYSURU CC CRIBS WITH ISA 75X75X8 E E E E E
SQ.
SQ.
2233
2300
7500 58 58 58 OFFICE DULY SIGNED & STAMPED BY SUPPLIER & LAUNCHING AGENCY.
6500
610 1000
58
1000 824 =2800= 600 SQ EACH BLOCK 00 B1-3 ISMB600 00 B1-3 ISMB600 B1-3 ISMB600 00 B2-4 ISMB600 B1-3 ISMB600 B1-3 ISMB600 ASSUMED =12T/M2 FOR NORMAL CASE AND 10.64T/M2 WITH ALLOWABLE BEARING
875
720 00 740 736 TO MYSURU JACK-250MT JACK-250MT TO MYSURU JACK-250MT JACK-250MT TO MYSURU
F2
F2
6500 TO HASSAN TO HASSAN TO HASSAN 35 200 FOR SAFETY PURPOSE CAPACITY= 15T/M2 FOR WIND LOAD CASE. ENGINEER AT SITE SHALL CONFIRM THE MAXIMUM
625
200 420
2750
7
BOTH FACE
BOTH FACE
CRIB CAPS WITH ISA-75X75X8 RESTRAINING WINCH RESTRAINING WINCH 4 RESTRAINING WINCH 150X150X25 THK
ISMC 100
ISMC 100
150X150X25 THK
BEARING PRESSURE ON SOIL SHALL NOT EXCEED SAFE BEARING PRESSURE AND SUBMIT THE TEST
C 100 CE
C 100 CE
2500
2750
2750
25 DIA HOLDING UNDER EACH CRIB PLATE
CAPACITY-50MT CAPACITY-50MT CAPACITY-50MT
ISM TH FA
ISM TH FA
A3 1200
6570
6570
3000 WOODEN PACKING 900 900 PLATE
DOWN BOLTS
3000 REPORT FOR OFFICIAL RECORDS. ALL THE FOUNDATION TOP LEVELS ARE KEPT AT RAIL
BO
BO
SUITE TO SITE 150X150X25 THK
6500
4000 4000 4000
7000
LINKS 8TOR 300 C/C RAIL FORMATION LVL. 2ISMC 150 150X150X25 THK
Ø20 58 450 58 450 58 PLATE PLATE 2ISMC 150 250
PER ROD
FORMATION LEVEL.
6500
00 00
10000
2750
58
250
Ø20 00 F1 F1 F1 F1 F1 F1
2500
2750
2750
4000
4000
4000
9500
6000
2ISMC 150
41O11'40'' 00 B/W TOP & BOTTOM 41O11'40'' 41O11'40'' 41O11'40'' 24. GRADE OF CONCRETE=M25, THE GRADE OF PCC=M20, THE GRADE OF STEEL FE500 AS PER IS
300
11000
PER ROD PER ROD
9800
150
13140
14600
13140
1&9
1&9
C/L OF CARRIAGEWAY
4000
4000
MIN.
FND BOTTOM LVL: F F F F F 1786-2008.
C/L OF CARRIAGEWAY C/L OF CARRIAGEWAY C/L OF CARRIAGEWAY
7000
13140
16100
2750
END CROSS BEAM
25. NO WELDING SHALL BE DONE AND TEMPORARY GIRDERS/BEAMS WILL BE SIMPLY SUPPORTED
2500
F1
F1
6000
2750
2750
300
RH16 RH16 RH16 MIN.
ON TRESTLES.
BOTH FACE
BOTH FACE
875
B3-4 ISMB600
B3-4 ISMB600
B3-4 ISMB600
B3-4 ISMB600
14 14 14 14
''M''
ISMC 100
ISMC 100
C 100 CE
C 100 CE
625
00 00 00 00
ISM TH FA
ISM TH FA
30DIA. BAR WITH THREAD 30DIA. BAR WITH THREAD
26. LIFTING JACKS SHALL BE OF 250MT CAPACITY. ACTUAL CAPACITY REQUIRED 60MT.
6570
6570
0 =2800= 300 TH COMPACTED 0 0 0
CL VERTICALS
3000 AT TOP AND BOTTOM
950
2500
BO
BO
HSFG 10.9 GRADE
L BEARING
1505 1756 1750
HSFG 10.9 GRADE
2800 150 FOUNDATION DETAILS FOR -F2 150 35
74 OF BSG OF BSG 27. FOR DETAILS OF CC CRIB CONNECTIONS, CLAMP ETC.. USED FOR TEMPORARY ARRANGEMENT
''N''
6500 300
300
F1 F1
875
6500 SECTIONAL VIEW
F3 F2 F2 F2 F2 F2 F2 F2 F3 F3 600 JACK-250MT
F2 F2 F2 F2 F2 F2 F2 JACK-250MT
F3 600 600 F2 JACK-250MT F2 F2 JACK-250MT
F2
600
F3 F2 F2 F2 F2 F2 F2 F2 F3 REFER RDSO DRG NO-RDSO/B-1484/4R.
625
30DIA. BAR WITH THREAD 30DIA. BAR WITH THREAD
2750
2300
150 150
C
3000 AT TOP AND BOTTOM AT TOP AND BOTTOM 28. DIRT WALLS SHOULD NOT BE CONSTRUCTED BEFORE ERECTION WORK AND PROVISION FOR
2750
3000
3000
1800
1800
G 13 G G 13 G G 13
SQ.
SQ.
3000 HSFG 10.9 GRADE HSFG 10.9 GRADE
150
98 98 9 2000 ANCHORING THE WINCHES ON ABUTMENTS SHOULD BE DONE.
44000 3000 B1-3 8ISMB600
2260
7 B1-3 ISMB600 7 B1-3 ISMB600 7 B2-4 ISMB600 B1-3 ISMB600 B1-3 ISMB600
ROLLERS
6500
730
TYP.
F2
F2
8150* 8
BEARING C/C Ø PLATE-25THK PLATE-25THK WOODEN PACKING AS PER IS 883-1994 PLATE-25THK WOODEN PACKING AS PER IS 883-1994 900 29. IN CASE PULLING WINCH-2X50MT IS NOT ACCOMMODATED ON ABUTMENT, SAME MAY BE
GIRDER BOTT.
PLATE-25THK
6500
M20-150 THK PCC
10000
20
GIRDER TOP.
2750
610 1000 Ø20 00 PULLING WINCH AR1 RESTRAINING WINCH PULLING WINCH AR1 RESTRAINING WINCH PULLING WINCH AR1 RESTRAINING WINCH 250 WIDE 250 WIDE END FACE PL. 250 WIDE END FACE PL. 250 WIDE
FIXED ON GROUND AT APPROPRIATE PLACE FOR EASEMENT OF PULLING.
2750
9500
END FACE PL.
606 00 35 STIFF. PL. 8 25THK-450 WIDE 8 25THK-450 WIDE END FACE PL.
3 @ 600 = 1800 CAPACITY-50MT CAPACITY-50MT CAPACITY-50MT CAPACITY-50MT CAPACITY-50MT STIFF. PL.
:108.657*
:107.407*
370 720 74 CAPACITY-50MT 20THK-200X400 25THK-450 WIDE 8 25THK-450 WIDE
12 12 12 12 20THK-200X400
50 1000 827 50 AR2 50 AR2 CRANE
50 AR2
WEDGE (IS 883-1994) FIXED TO RAILS 25Ø BOLT-10.9 Gr.
25Ø BOLT-10.9 Gr. STIFF. PL.
20THK-200X400
25Ø BOLT-10.9 Gr. STIFF. PL.
20THK-200X400
FLANGE PLATE-20THK 30. FORCE ON EACH PULLING AND RESTRAINING WINCH IS 3.57MT. CAPACITY OF 50MT IS
AR1 0
740 733 M25-300 THK RCC 0 0 250MT 0 HSFG HSFG
HSFG WEDGE (IS 883-1994) FIXED TO RAILS ADOPTED AT SITE AT EACH POINTS. ALL WINCH SHALL BE POWER DRIVEN TYPE ONLY. ENGINEER
2750
WITH REMOVABLE C-TYPE
UR2 UR2 UR2 1050
WITH REMOVABLE C-TYPE 25Ø BOLT-10.9 Gr. WEB PLATE-16THK @ 250 C/C
2750
RAIL CLAMPS 12 THK STIFFENER 12 THK STIFFENER
UR1 UR1 UR1 500 ROLLER FRAME RAIL CLAMPS 500 HSFG AT SITE SHALL ENSURE GOOD CONDITION OF WINCH AND ITS PARTS AT TIME OF LAUNCHING
875
(TYP.) (TYP.)
AR2 MIN. MIN. ROLLER FRAME
625
ROLLER 100T CAPACITY
OF BSG. THE BSG SHALL BE PUSHED AT THE RATE OF 173.2 MM/SEC.
3 @ 600 = 1800
BRACINGS RESISTANCE GUIDE ROLLER GUIDE ROLLER RESISTANCE
FORCE =5MT FORCE =5MT
300
300
ISMC100 BRACKET BRACKET
1550 1250 8MM WELD ROLLER FRAME ROLLER FRAME 31. STEEL WIRE ROPE CONFORMING TO (IS-14268-1995) SHALL BE TIED AT TOP CHORD (RIDGE OF
3000
434 ALL ROUND
UR2 100X700X16 THK PL. GUIDE ROLLER GUIDE ROLLER 100X700X16 THK PL.
A2 BOW) ON BOTH SIDES OF BSG TO ENSURE STABILITY AGAINST UNDULATIONS / UNSYMMETRICAL
PLACED IN GROOVE I/S MS C-TYPE CLAMP-300MM 8 A2 8 PLACED IN GROOVE INSIDE MS C-TYPE CLAMP-300MM
52Kg RAIL ROLLER 100T CAPACITY 52Kg RAIL ROLLER 100T CAPACITY
UR1 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9 GUSSET PL. 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9 WOODEN SLEEPER AS PER IS:2062-2011
WOODEN SLEEPER
AS PER IS:2062-2011 ACTIONS DURING MOVING / PULLING CONDITION.
STAGE BEFORE LAUNCHING : WOODEN MAT @500mm C/C WOODEN MAT @500mm C/C
PLAN BEFORE LAUNCHING AS PER GAD
375
-10THK.
(250X150) OVER ISMB 600 (250X150) OVER ISMB 600
376
1. PREPARE WELL COMPACTED LEVELED GROUND UP TO TRACK NOTE: PLAN OF 2nd STAGE GUSSET PL. BRACINGS PLAN OF 4th STAGE PLAN OF 6th STAGE 100X700X16 THK PL. AT ALL SPANS
WOODEN PACKING
100X700X16 THK PL. AT ALL SPANS
WOODEN PACKING
SPECIAL NOTES
-10THK. PLACED IN GROOVE INSIDE 8 PLACED IN GROOVE INSIDE
FORMATION LEVEL AS SHOWN FOR ASSEMBLY OF BOW STRING GIRDER FOLLOWING ARE THE SUB-STRUCTURE DETAILS AS PER SITE EXECUTION: ISMC100
CC CRIBS
WOODEN SLEEPER 25X25X50LONG
J BOLT-20Ø
WOODEN SLEEPER 25X25X50LONG
J BOLT-20Ø
BATTEN PL.16THK BATTEN PL.16THK
8MM WELD 275 500 500 500 500 500 500 500 500 500 500 500
OVER CC CRIBS. ALL ROUND
BATTEN PL.16THK
150 WIDE 27Ø HOLE FOR 25Ø BOLT 150 WIDE 27Ø HOLE FOR 25Ø BOLT 1. ALL THE CRIBS TO RDSO DRG.NO.B-1484/4 SHOULD BE USED. UNEVEN AND BLUNT EDGE CRIBS
BATTEN PL.16THK
2. SOIL BEARING PRESSURE OF AS MENTIONED SHALL BE ENSURED AT SITE. 1. LHS SPAN OF BSG WILL NOT BE CONSTRUCTED TILL BSG LAUNCHING OPERATION. 150 WIDE HARD WOOD SLEEPER
8
840
THROUGHOUT @ 1000 C/C
840
THROUGHOUT @ 1000 C/C
150 WIDE HARD WOOD SLEEPER ARE NOT PERMITTED. MONOLITHIC ACTION OF CRIBS SHOULD BE ENSURED BY PROVIDING
500 C/C 250x150x900 @ 500 C/C GIRDER O/O 3-ISMB600 BATTEN PL. -2X16THK 4-ISMB600 500 C/C 250x150x900 @ 500 C/C
NECESSARY SOIL STABILIZATION & COMPACTION SHALL BE CARRIED 2. RH16, RH17, UR1 & UR2: PIER AND PIER CAP COMPLETED AT SITE. LAUNCHING GIRDER
3 ISMB600
27Ø HOLE FOR 25Ø BOLT
-1000LG.-150WIDE @ 500C/C
DOG SPIKES GIRDER O/O
27Ø HOLE FOR 25Ø BOLT LAUNCHING GIRDER SUITABLE HORIZONTAL AND VERTICAL BRACING ON TOP AND FOUR SIDES WITHOUT
150
THROUGHOUT @ 1000 C/C 4 ISMB600
THROUGHOUT @ 1000 C/C
OUT BY ENGINEER-IN CHARGE AT SITE TO ENSURE SBC IS MORE THAN THE 3. LH16, LH17 ONLY PIERS CASTED AT SITE. INFRINGING THE RUNNING TRACKS. ENGINEER AT SITE SHOULD ENSURE THE SPECIFICATION OF
DETAIL-M DETAIL-N HW PACK
MAXIMUM PRESSURE AT FOUNDATION LEVEL OF CRIBS. 4. DR1, DR2 FOOTING & PIER NOT CASTED AT SITE. FOUNDATION DETAILS FOR -F2 RDSO/B-10414/R RDSO/B-10414/R 1800 SQ.-150MM THK. HW PACK
ON CC CRIBS
1800 SQ.-150MM THK. ON CC CRIBS
CRIBS.
BATTEN PL.16THK
5. AL1 & AL2 (BSG PIERS) NOT CASTED AT SITE. SAME NOT SHOEN IN FURTHER PLAN VIEW SEC A3-A3 150 WIDE DETAIL-X1 FOR GIRDER A5 SEC A5-A5 2. THE TEMPORARY ARRANGEMENT HAS BEEN CHECKED FOR CONSIDERING THE SELF WEIGHT OF
TO MYSURU TO MYSURU TO MYSURU A3
STAGES OF LAUNCHING. AT BEARING LOCATION OF BSG (4-ISMB 600) AT EACH VERTICAL HANGERS OF BSG THE STRUCTURE EXCLUDING DECK SLAB AND CONSTRUCTION LIVE LOAD.
9000
9000
DETAIL-X1 FOR GIRDER
L BEARING
3600
6. ALL THE GIRDERS AND SLABS WILL BE ERECTED ONLY AFTER BSG LAUNCHING. 10 THK PLATE FLANGE PLATE-20THK (3-ISMB 600) 680 3. THE SUPER IMPOSED DEAD LOAD i.e, WEARING COAT , R.C.PARAPET, FOOT PATH HAVE NOT
188
7. FURTHER STAGES ONLY SUB-STRUCTURE DETAILS WILL BE SHOWN IN PLAN AND CC CRIBS CONNECTIONS & 12
188 12 60 475
BEEN TAKEN FOR DESIGN PURPOSE.
10
20
CLAMPING ARRANGEMENT AS 12 THK PLATE
ELEVATION AS PER SITE EXECUTION TILL DATE. TO HASSAN TO HASSAN "DETAIL-S" TO HASSAN 6 6
PLATE 700x100X16 THK.
700
8
4. THE ENGINEER-IN-CHARGE SHALL ENSURE THAT THE INDIVIDUAL CRIBS ARE INTERCONNECTED
C
PER RDSO/B/1484/4R1 12 THK PLATE
R75
66 TYP.
TO HASSAN 600 600 BSG BOTTOM CHORD
8. BSG LAUNCHING WILL BE DONE ONLY FOR RHS SPAN. CC CRIBS WITH ISA 75X75X8 STIFF. ANGLE 100X100X10 60 35
8 J-BOLT 20 DIA WITH SUFFICIENT NUMBER OF CLAMPS AND PROPERLY BRACED. BEARINGS SHOULD BE
243
GIRDER TOP. GIRDER TOP. 600 GIRDER TOP. 10 THK PLATE TYP. HSFG 8.8 Gr.
600
232
600 SQ EACH BLOCK WELDED 6THK TO GUSSET PL. & WEB PLATE-16THK
250
6760 45600 PIER C/C 6760 45600 PIER C/C 6760 45600 PIER C/C PROPERLY PROTECTED WHILE LAUNCHING OF BSG.
100
104810
200
:108.557* JACK-250MT :108.557* JACK-250MT :108.557* 100
45600 PIER C/C CRIB LEG
160
TO MYSURU 12 THK PLATE 12 THK PLATE 100Ø40 THK
44000 BEARING C/C
B1- 3 ISMB600 ISMC100 6 B1- 3 ISMB600 MS SQ. BAR "DET-A" B1- 3 ISMB600 B2- 4 ISMB600 B1- 3 ISMB600 MS ROLLER STIFF. PLATE-12THK 5. CONTROLLED CONCRETE WITH WEIGH BATCHING SHALL BE USED AND THE WORK SHALL BE
2400*
2400*
CRIB CAPS WITH ISMC-100 808 6 451 PLATE-C: 39
10
44000 BEARING C/C GIRDER BOTT. 6 44000 BEARING C/C GIRDER BOTT. 44000 BEARING C/C GIRDER BOTT.
42000 CLEAR SPAN
25 DIA HOLDING UNDER EACH CRIB
BOG LEVEL : 106.52 :107.657* BOG LEVEL : 106.52 :107.657*
1000 X 25 X 25
1075X910X25 BOG LEVEL : 106.52 :107.657* 88
100 ØX40 THK
27
25.5Ø HOLE SUPERVISED BY AXEN HAVING EXPERIENCE IN BRIDGE CONSTRUCTION .
500
250
DOWN BOLTS ISMC 100 A4 A4 J-BOLT 20 DIA HARD WOOD SLEEPER
ISMC100
610 BOG LEVEL : 106.52 1800 1800 1800 ''Y'' 1800 1800 1800 1800 1800 1800 1800 ''Y'' 1800 1800 1800 1800 1800 1800 1800 BOTH FACE 1800 1800 1800 1800 ''Y'' 1800 1800 1800 1800 10 THK PLATE 188 95 6. THE GRADUAL RELEASE OF SPEED RESTRICTIONS SHALL BE AS PER PARA 637(1)(f) OF INDIAN
365
250x150x900 @ 500 C/C
477
827 LINKS 8TOR 250 C/C RAIL FORMATION LVL. 700
PIER TOP :106.033 PIER TOP :105.640 42000 CLEAR SPAN
SQ. SQ. SQ. SQ. SQ. SQ. SQ.
42000 CLEAR SPAN
SQ. SQ. SQ. SQ. SQ. SQ. SQ. SQ. SQ. SQ.
42000 CLEAR SPAN
SQ. SQ. SQ. SQ. SQ. SQ. SQ. SQ.
12
BOTH WAYS
RAILWAY PERMANENT WAY MANUAL.
20
PIER TOP :105.421 12 tor 125 C/C DETAIL OF GUIDE ROLLER
SECTION A4-A4 DETAIL OF ROLLER FRAME
2192
2000
ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100 ISMC 100
2493
200
900
PIER TOP :105.261 J-BOLT 20 DIA
1090
2100
1473 BOTH FACE BOTH FACE BOTH FACE BOTH FACE BOTH FACE 200 BOTH FACE BOTH FACE BOTH FACE BOTH FACE BOTH FACE M20 DIA BOLTS BOTH FACE BOTH FACE BOTH FACE BOTH FACE BOTH FACE BOTH FACE BOTH FACE
B/W TOP & BOTTOM 7. NEW STEEL CRIBS OF SIZE 600 X 600 X 1800 SHALL BE USED AND CRIBS ALREADY DISTORTED OR
450
7265*
6525
6525
6525
1400 GUSSET PL.-8THK C 100 CE
HSFG 8.8 Gr.
900 900
250
1000
100
VC
3600X1800 3600X1800 3600X1800 3600X1800 52 Kg RAIL WITH NUTS ISM TH FA 3600X1800 3600X1800
6525
8150*
8150*
8150*
8150*
8150*
8150*
2700 1050 99.807 M20-150 THK PCC
600
2800 0 0 0 E 0 WOODEN SLEEPER 0
10 CE
0
10 CE
3300 2800 10 CE
C 100 CE C 100 CE C 100 CE 10 CE DETAIL-X 10 C
C 100 CE C 100 CE C 100 CE 10 CE
C 100 CE C 100 CE C 100 CE C 100 CE C 100 CE 8. CC CRIBS ARE DESIGNED FOR HEIGHT OF 11M MAXIMUM.
3774
5694
19130 (SK) 7708 (SK) 7708 (SK) 9254 (SK) C FA C FA DETAIL-Y 19130 (SK) 7708 (SK) 7708 (SK) 9254 (SK) C FA
ISM TH FA ISM TH FA C FA 19130 (SK) 7708 (SK) 7708 (SK) ISM TH FA 9254 (SK) C FA
ISM TH FA ISM TH FA C FA
3141
300
ISM TH ISM TH FA ISM TH FA ISM TH FA ISM TH @ 500 C/C ISM TH
ISM TH ISM TH ISM TH
13380 (SK) 7708 (SK) 7708 (SK) 15003 (SK)
5521
1200 BO BO BO BO BO BO BO BO 52 KG RAIL TO BE ATTACHED
PULLING 14396 (SQ) 5800 (SQ) 5800 (SQ) 6964 (SQ) BO BO BO BO BO RESTRAINING PULLING 14396 (SQ) 5800 (SQ) 5800 (SQ) 6964 (SQ) BO BO RESTRAINING PULLING 14396 (SQ) 5800 (SQ) 5800 (SQ) 6964 (SQ) BO BO RESTRAINING Foot Path
9. * DIMENSIONS SHOWN ARE TO BE VERIFIED AT SITE DURING EXECUTION.
10069 (SQ) 5800 (SQ) 5800 (SQ) 11290 (SQ) 1200 2000 PL. 900X10THK WITH ISMB-600 Divide
r
WINCH -2X50MT FGL :99.510 WINCH -2X50MT WINCH -2X50MT FGL :99.510 WINCH -2X50MT WINCH -2X50MT FGL :99.510 WINCH -2X50MT Road
2000 1676 1676 RL :99.995 1676 1676 1676 RL :99.995 1676 8 1676 1676 RL :99.995 1676 SEC. A2-A2
300
300
300
300
300
300
300
300
300
300
300
300
300
300
300
300
300
300
300 TH COMPACTED
10. ENGINEER IN-CHARGE SHALL ENSURE THE GOOD CONDITION & CONFIRM THE ADEQUACY OF
300
300
300
300
300
300
300
M20 DIA BOLTS
450
450
450
450
FGL :99.920 FGL :99.920 FGL :99.920
450
450
FGL :99.510 6000 FGL :99.810 FGL :99.810 WOODEN PACKING FGL :99.810
1676 1676 RL :99.995 1676 FGL :99.920 LAYER OF MOORUM F3 F2 F2 F2 F2 F2 F2 F2 F3 F3 F2 F2 F2 F2 F2 F2 F2 F3 F2 F2 F2 F1 1F F2 F3 F2 F2 F2 F2 F2 F2 F2 F3
FGL :99.810 150 FGL :99.740 FGL :99.740 -25 THK FGL :99.740
EACH ELEMENTS (ROPE, HOOK. CRANE ETC..) USED IN REGARDS TO LAUNCHING OF BSG.
450
054
FGL :99.740
150 FOUNDATION DETAILS FOR -F3 FRL :99.257 FRL :99.257 FRL :99.257
750
750
750
650 650 PACKING PL.
750
750
750
650 650 FRL :99.257 FND LVL: 6000 3000 3000 3000 3000 3000 3000 3000 6000 FND LVL: FND LVL: 6000 3000 3000 3000 3000 3000 3000 3000 6000 FND LVL: FND LVL: 3000 3000 3000 3000 6000 3000 3000 3000 3000 3000 3000 3000 6000 FND LVL:
SECTIONAL VIEW STOPPER PL. 4000 0004
11. FOR ANY CC CRIB INFRINGEMENT WITH EXISTING PIER/PIER CAP, SAME SHALL BE SUITABLY
4000
BR
Divider
150 150 8 8 Road
4800
@ 500 c/c
18604 (SK) 16611 (SK)
6000 24353 (SK) 10861 (SK) 24353 (SK) 10861 (SK) 24353 (SK) 10861 (SK)
san
Bus
Sta
nd
SHIFTED/RELOCATE AT SITE BY ENGINEER IN-CHARGE.
14000 (SQ) 12500 (SQ) 14000 (SQ) 12500 (SQ) 14000 (SQ) 12500 (SQ)
150
Foot Path
4700
1000
Has
6000
14000 (SQ) 12500 (SQ)
5900
2500 52 Kg RAIL 8
1000
2500 3000
t
Exi
FND LVL :94.510 FND LVL :94.510 CLUSTERS FND LVL :94.510 SAFETY NOTES
nd
1200
s Sta
FND LVL :94.510
1200
6500 AR1 AR1 AR1
Bu
6 @ 600 = 3600 FND LVL :93.920 FND LVL :93.920 FND LVL :93.920 Foot
Path
FND LVL :93.920 7500 FND LVL :93.810 FND LVL :93.810 FND LVL :93.810
AR2 AR2 BATTEN PL.16THK AR2 er Path
1. ADEQUATE SAFETY MEASURE FOR RUNNING TRAIN SHALL BE ADOPTED WHILE DOING THE EARTH
Foot
CH:857
CAUTION INDICATOR
Road
EP
4-ISMB600 der Unde Court
CH:1627
SPEED INDICATOR
d Divi District
3 @ 600 = 1800
DOG SPIKES Roa
IMPOSING NECESSARY SPEED RESTRICTION BY PROVIDING TEMPORARY ENGINEERING
TERMINATION
30 m t Path
INDICATOR
10 11 12 13 15 16 17 18 1 2 3 4 5 6 7 8 9 10 11 12 13 15 16 17 18 1 2 3 4 5 6 7 8 9 10 11 12 13 15 16 17 18 1 2 3 4 5 6 7 8 9 Foo
try
CH: 2422
INDICATORS.
En
83.63
RD
RD
83.633
3000
nd
er
s Sta
Divid
d
30
Roa
Bu
HW PACK
T
HSFG BOLT
24 DIA-8.8GR. LENGTH OF STAGE-2 STAGE-4 1800 SQ.-150MM THK.
ON CC CRIBS STAGE-6 SKLR SC
mP ER
Foot
Path
WHILE EXECUTING FOUNDATION WORK CLOSE EXISTING FOUNDATION INCLUDING IMPOSING
EACH BOLT = 675 mm 30 RD
CC CRIB ELEVATION ALONG GRID- E ELEVATION ALONG GRID- E ELEVATION ALONG GRID- E HAS GI
OF SPEED RESTRICTION IF REQUIRED.
DETAIL- S SC
200
mP R
ANGLE-75X75X8
(REFER STAGE-4 FOR MARKING)
20 DE
GIR 4. THE GRADUAL RELEASE OF SPEED RESTRICTION SHALL BE AS PER PARA 637(1)(f) OF IRPWM.
Ch:1682
RAIL FORMATION LVL. lex
Foo
t Path
PS
m ER
C
ial
Co
mp 5. NECESSARY SHORING ARRANGEMENTS TO BE MADE TO PROTECT EXISTING BRIDGE STRUCTURE
300/450
30 RD erc
WHEREVER NECESSARY.
SPEED INDICATOR
225
GI mm
Co
ri
T
6. JOINT PROCEDURE ORDER ON SAFETY RELATED ISSUES PERTAINING TO WORK SITE IN
TERMINATION
wa
de ly
CH:1737
INDICATOR
am Supp
sh
CAUTION INDICATOR
30
150
CH:942
CONSTRUCTION PROJECTS (Lt. No. W339/SAFETY PRECAUTION Dt: 18-02-2011) VIDE CTE Lt. No.
un
i Ch ty
ri e
Sr ctrici
sh offic
250
r
ide
Div
SWR/W.247/SAFETY AT WORK SPOT Dt: 20-06-2017 IS TO BE STRICTLY FOLLOWED.
wa
Ele
de ly
ad
un pp
BOW STRINGER GIRDER
FIXING ARRANGEMENT OF ANCHOR BOLT
30 m
CH:2507
Ro
13140
am y Su
FOUNDATION DETAILS FOR -F3 BOW STRINGER GIRDER
13140 7. DURING EXECUTION OF WORK THE MATERIAL / EQUIPMENTS SUCH AS RELEASED MATERIALS
i Ch cit
WITH CC CRIB AND RCC SLAB
h
t Pat
Sr tri
BEARING C/C
5
PLAN VIEW BOW STRING
50.00 m
ec
Foo
715 m 800 m
Ø7
WEDGE FIXED TO RAILS BEARING C/C ETC. SHOULD NOT INFRINGE THE TRAIN. ALL SAFETY MEASURES TO BE TAKEN BY ENGINEER - IN -
El
910 =12500= 2700
RE PANEL APPROACH
GIRDER (BSG)
2 4 6 8 10 12 14 16 18 IS 883-1994 =12500= BEARING
730
ISA 130x130x10 120 @ 5 = 600 720 1000 CHARGE DURING EXECUTION.
150
LAUNCHING GIRDER
300 800 SQ. ABT
250T CAPACITY DR-
25
52 Kg RAIL BOTTOM CROSS BEAM
100
130 WEB
DR-4
1100
HSFG 8.8 Gr.
BOTTOM CROSS BEAM
SQ.
44000
MIN. (PARA 807, 808, 814, ANNX-8/3 OF IRPWM-2020)
2300
55
BEARING C/C WOODEN PACKING (WRAPPED ALL ROUND 9. SAFETY PRECAUTIONS MUST BE ENSURED AS PER ABOVE RELEVANT JPOs OF ZONAL RAILWAY
41 0K 0m
CH:1/600
WOODEN PACKING AT
62 ILS
STAGE-5
ABT
0% 8m
3
BOW STRING
LE EE S DE
250T CAPACITY (NOT TO SCALE)
DR- ABT
JACKING LOCATION WITH HARD METAL STRIP PLATE SAFETY WOODEN BLOCKS 600 AND INSTRUCTIONS OF RAILWAY BOARD.
SP DIU E
156
AR3
600
RA RV
BEARING LVL BEARING LVL GIRDER (BSG)
CU
8 ABT
JACK.
SE NG D
TH
AGAINST DISLOCATION OF BLOCKS) 1000x1000
50
LH1 UR
C/L OF BEARING
106.520 106.520 JP 10. WORKING AREA SHALL BE BARRICADED TO ENSURE SAFETY OF TRACK OPERATION ON
2400*
WOODEN BLOCKS NOTE: NECESSARY TEMPORARY ENGINEERING INDICATORS VIZ. CAUTION, SPEED AND TERMINATION
18
2 RH
C/L OF BEARING
DR-
1. CENTER LINE OF REMAINING CRIB SUPPORTS SHALL BE MARKED AS SHOWN IN RUNNING LINES.
1200
1200
C/L OF BEARING
250T CAPACITY 1000x1000
UR3
RDSO/B-10414/R INDICATOR WITH RETRO REFLECTIVE TO BE PROVIDED SUITABLY BY ENIGNEER-IN CHARGE AT THE APPROACHES 7
LH1
50
PLAN AND ELEVATION. 50 55 25 JP RCC PEDESTAL JP JP RCC PEDESTAL JP JACK. ACTUAL FORCE-60T 610 1090
B
610 11. WHILE CARRYING OUT PREPARATORY WORK AT PLATFORMS NECESSARY PRECAUTIONS
17
ARRESTING OF BSG
1 SLA
Bridge
RH
DR-
MS C-TYPE CLAMP-300MM 6
C/L OF PIER
2
LH1 UR
130
RCC PEDESTAL SHOULD BE TAKEN TO AVOID UNSAFE CONDITIONS.
t Path
130
55
1800
1800
ISMC 300 B/B AS PER IS:2062-2011
2
Bridge
Foo
6525
6525
AL- 16
STAGE-3 3. REMAINING CC CRIBS ALONG WITH BRACING SHALL BE ERECTED AS SHOWN IN 12. PROTECTIVE SCREEN OF STANDARD DIMENSION TO BE PROVIDED ALONG THE ENTIRE LENGTH
RH
R
UR1
STAGE-1
DE
2192
2000
1 2 3 4 5 6 7 8 9
25
THE PLAN AND ELEVATION.
GIR
TYPE SIZE SECTION J1-J1 LAUNCHING GIRDER OF PROPOSED FOB / ROB OVER THE TRACK WITHOUT ANY GAP.
TRACK
OF
CL
0M
G
RIN
0.0 2
4. LAUNCHING GIRDER- B1 & B2 FOR THE REMAINING CC CRIBS SHALL BE ERECTED 1090 1000
AR-
WOODEN BLOCK
44
5500 5500 5500 5500 5500 5500 5500 5500 13. ERECTION / LAUNCHING WORK OVER RUNNING LINE SHALL BE CARRIED OUT UNDER TRAFFIC
ST
ILS 0m
TA 0.0 ph
TRACK
W
OF
1. CC CRIB COLUMNS WITH FOOTING-F3 ALONG GRID- B & D LOCATIONS
CL
DE 11 Km 0m
MS PLATE - R 700
BO
J2 MS 1200 LG. PLAN VIEW OF DETAIL-A E 45 4.3
R
USING CRANE OF 1X150MT CAPACITY AS SHOWN IN PLAN AND ELEVATION BOTTOM MAIN BEAM
DE
BLOCK UNDER THE SUPERVISION OF CONCERNED DyCE.
RV
LC.NO : 3 AT
Km:1/600-700
1'40"
10 %
d
CU DIUSD
1. CENTER LINE OF CRIB SUPPORTS SHALL BE MARKED AS SHOWN IN DRG.
Roa
2.5
700x300x25 250
GIR
41°1
44000 130 C- CLAMP
F1 4000X4000X450 SHALL BE BUILT SIMULTANEOUSLY STAGE BY STAGE WHILE LIFTING OF BSG. ISA 130x130x10 OF BOWSTRING GIRDER 6000 6000 RA EE TH
250
alt
LAUNCHING GIRDER
G
SP NG
Asph
M20 BOLTS
WITH POWER AND LINE BLOCK OF 2 HOURS. 125
RIN
00
2. RCC SLAB SHALL BE CAST FOR SUPPORTING THE CC CRIBS. ALL TOP BEARING C/C J1 50 55 25 J1 MS BAR
LE
SE
CH:1/7
14. IN ELECTRIFIED TERRITORY EARTHING TO BE DONE AND CERTIFIED BY TRD OFFICIALS BEFORE
ST
2. CC CRIB COLUMN WITH FOOTING-F3 ARE TO SUPPORT BSG WHILE HSFG 8.8 Gr. MS PL.-Q: 20THK 2700
W
42000
Ø75
5. THE BSG SHALL BE PULLED USING WINCH OF CAPACITY 2X50T CAPACITY TILL IT 600 x 25 x 25 PLATE - S
BO
ER-3 TE
POWER BLOCK IS CANCELED.
ROB IN LIEU OF
GIRD POSI
LC.NO : 3 AT Ch:1682
0M
FOUNDATIONS SHALL BE MAINTAINED AT FORMATION LEVEL. -225X250
RE PANEL APPROACH
COM
Chain
Pully
BUILDING UP OF CRIB. CC CRIB COLUMNS ALONG GRID- A ARE REQUIRED WELDED 525 x 375 x 25 RAIL LVL: 99.995 RAIL LVL: 99.995 EFF. SPAN IMP. NOTE:
lt Road
5
C/L OF BEARING
40 40
d
REACHES PIER BEARINGS CENTERS OF AR1 & AR2 AS SHOWN IN PLAN AND 120 @ 6 = 600
Roa
P1
15. GIRDER MUST BE ADEQUATELY SECURED IMMEDIATELY AFTER LAUNCHING.
C/L OF BEARING
TE
3. CC CRIBS SHALL BE ERECTED FOR THE FOOTINGS FOR ABOUT 1200MM AS
300
WEDGE FIXED TO RAILS
GIRD POSI
8
8M
80
alt
Aspha
WHILE PUSHING THE BSG.
ER-1
HYDRULIC JACK 1200
COM
RDSO/B1-1484/4R1
Asph
ENGINEER IN CHARGE AT SITE SHALL CONFIRM
ER
SC
GIRD
Wall
16. WORK HAS TO BE EXECUTED UNDER SUPERVISION OF AN EXPERIENCED AND COMPETENT
375
Compound
SHOWN ALONG GRID A TO D ONLY AT THE LOCATION OF VERTICALS BRACING 30 t CAPACITY
WEB
3
3. ALL THE CRIBS SHALL BE ERECTED UPTO LAUNCHING GIRDER LEVELS AND ISA 75X75X8 ON ALL M20 BOLTS 100 THAT THE "BSG" IS LIFTED/LOWERED P1
P1
Under Construction
HANGERS FOR ASSEMBLING OF "BSG". MIN.
ER C
4 RAILWAY ENGINEER.
School Campus
School Building
FACES WITHIN CRIBS
DETAIL-A (STAGE-6)
GIRD mPS
St. Philomeina
28 DIA HOLE
Buildings
SHALL BE BRACED AS SHOWN WITH ENSURING NECESSARY WELDING. 3600X1800 3600X1800 ISA 130x130x10 HSFG 8.8 Gr.
17.6
25 55 50
2
ER
F3 6000X3000X450
Don Boscho
P1
SC
& Commercial
GIRD
4. CC CRIBS ALONG GRID E TO G SHALL BE ERECTED ALONG WITH J2 ARRANGEMENT AT BEARING AVOID ANY UNSYMMETRICAL JACKING ACTION
8150*
8150*
ER
Institute
PSC
Station
GIRD
7000 7000
Residential
17.6m
Man Hole
1
MH
P1
MH
To RailWay
BRACING, LAUNCHING GIRDER (3 ISMB600) WITH RAIL CLUSTER & ISMC 300 B/B
FOR LIFTING / LOWERING OF BSG AT SUPPORTS.