Professional Documents
Culture Documents
2x10 MW
DAFTAR ISI
1. INTRODUCTION.................................................................................................................................... 4
1.1. Project Description......................................................................................................................... 4
1.2. Objectives ..................................................................................................................................... 4
1.3. Definition ....................................................................................................................................... 4
2. ORDER OF PRECEDENCE ................................................................................................................... 4
3. CODES AND STANDARDS ................................................................................................................... 4
4. MATERIAL............................................................................................................................................. 5
5. TRANSPORTATION & HANDLING (LOADING & UNLOADING) ............................................................. 5
6. STORING .............................................................................................................................................. 5
7. SETTING OUT ....................................................................................................................................... 6
8. PC PILE 6
8.1. Preparation of PC Pile Driving ........................................................................................................ 6
8.2. PC Pile Splicing ............................................................................................................................. 8
8.3. PC Pile Driving ............................................................................................................................ 10
8.4. Tolerance .................................................................................................................................... 11
8.5. Reporting .................................................................................................................................... 11
8.6. PC Pile Driving Criteria ................................................................................................................ 12
9. SPUN PILE DATA ................................................................................................................................ 13
10. TEST PILE........................................................................................................................................... 13
10.1 General ....................................................................................................................................... 13
10.2 Static Load Test .......................................................................................................................... 13
10.3 PDA Test..................................................................................................................................... 24
11. LAMPIRAN .......................................................................................................................................... 29
PALU MINING POWER PLANT
2x10 MW
1. INTRODUCTION
1.1. Project Description
PT. Adiprotek Envirodunia which engaged in provision of energy sector including oil and gas to built Palu
Mining Power Plant 2x10MW, have been collaborated with PT. Enviromate Technology International located
on Citra Palu Mineral Gold Mine area in Central Sulawesi.
1.2. Objectives
This document covers the specification for pile works which will be required for detail engineering execution.
All detail civil engineering calculations will refer to this document.
1.3. Definition
Definitions used in this document will not violate other definitions used in other documents which is:
COMPANY PT. Adiprotek Envirodunia.
2. ORDER OF PRECEDENCE
Where conflict arises, the order of precedence will be:
INDONESIA Laws and Regulations
Owner Specification (if any)
International Codes and Standards
This Specification
4. MATERIAL
a) Driven Pile (PC Pile)
PC Pile used is precast concrete to meet the standards of ACI 543R or JIS A 5335 or equivalent with f’c=500
kg/cm2 concrete strength and using Portland Cement type I with Silica Fume or equivalence. Minimum
content of Silica Fume is 20.6% as reference in ASTM C150. Testing shall be done according to ACI 543R
or manufacturer’s standard.
6. STORING
The storing location of PC Pile to be used shall be placed as close as possible to the work location and shall
be arranged according to its sequence of work execution. The storing shall be done with closed storage and
PALU MINING POWER PLANT
2x10 MW
good drainage to avoid corrosion and/or deterioration on PC Pile and firm ground, grade the land evenly,
dry ground and lay props in short intervals. For each bundle of pipes, prop them in the same position and
do not heap up more than 10 piles on top of another. The position of the sleeper shall be as follows when
storing piles:
7. SETTING OUT
Before work was begun, the Contractor should perform setting out precisely using a experienced
worker, to determine the drive position for PC Pile as planned by the Engineer.
The contractor should report everything that occurred in the site that is expected to disrupt the work
continuity in writing to COMPANY, hence such interference can be handled as soon as possible.
If public facilities and other utilities are founded in the site, the Contractor shall keep all these facilities
to remain able to function during the execution took place. All costs needed to protect / maintain the
facility / utility there, including resetting damaged by Contractor’s error, should have been anticipated
in the bid.
8. PC PILE
8.1. Preparation of PC Pile Driving
8.1.1 Equipment
a. Before mobilizing the piling equipment (Crane, Hammer, Leads, Hammer Components, Pile Followers,
and/or Jets), hammer shall be inspected to examine its condition and shall attain approval from
COMPANY.
PALU MINING POWER PLANT
2x10 MW
b. Piling equipment, hammer and hammer pads shall be selected and adjusted to the requirement for
reaching the necessary penetration and required PC Pile capacity without causing any damage.
c. Any hammer found unsuitable to be used during PC Pile Drive shall be changed with the correct
hammer.
Numbering shall be made by giving mark with paint at specified interval of the entire length of pile and the
numbering shall be painted at this interval starting from the lower part of pile.
One-third of the upper part of pile shall be marked at interval of 25 cm, while the remaining two-third of the
lower part of pipe shall be marked at interval of 50 cm.
Work sequence of PC Pile Drive shall be planned carefully to prevent displacement and lifting of PC Pile
that has been piled due to the piling of other pile. This is the work sequence of piling:
a. Mobilization Piling Machine to The Site:
Firstly, clarify the location that the piling machine has to be moved to. After that, the piling
machine will be moving in to the location in site. The piling machine will be set on place.
b. Driving Initial Pile:
After bringing in the piling machine, first pile or starter pile or initial pile will be ready to drive in to
the ground by following the pile point that shown in the construction drawing. The initial pile will
be driven in to the ground until maximum or can’t be driving in anymore.
c. Driving Extension Pile:
If initial pile has been fully driving in to the ground, the second pile or extension pile will be
jointing to the initial pile and drive again. The extension pile will be driving into the ground until
maximum as the initial pile.
d. Cutting Off Pile Head:
The pile cut off elevation refers to the top of pile elevation indicated in the plans and “pile cutoff”
refers to the excess length of furnished pile above this elevation. After piles have been driven to
the minimum tip elevation, the cutoff elevation shall be marked on the piles.
e. Preparation of Pile Head of Pile Cap:
After cutting off the excessive pile, excavate the soil surrounding of the pile about 300 mm
depth for preparation of pile cap.
f. Load Test:
PALU MINING POWER PLANT
2x10 MW
There are two kinds of load test for pile, those are axial loading test (with minimum safety factor is
3) and lateral loading test. The purpose of load test is to test the strength of the pile. A certain load
will be putting on the pile for a certain period. If the PC Pile is crack, which mean the PC Pile is
failed to support the load. If the PC Pile left for certain days without any crack, which mean the PC
Pile is strong enough to carry the load of the building. Normally load test will be carried on before
driving the pile to the ground. If the load test for the PC Pile is failed, then the contractor has to
supply another batch of PC Piles.
PC Pile shall be placed at the specified location points according to the specified construction design.
The total of blow count for each marked number at 50 cm and 100 cm interval shall be noted. Penetration,
rebound and the fall height of hammer shall be noted and recorded.
The final set specified in the final piling criteria shall be reached minimum at the requirement in PC Pile
Driving Criteria.
The acceptable equipment and tools used to cut PC Pile - to prevent PC Pile from damage during the
cutting - shall attain approval from COMPANY.
The detailed welding procedure as well record on qualification test for chief welder shall be submitted by
Contractor to COMPANY to attain written approval before commencing the work.
The required welding position shall be in accordance with the provisions in 6G or 2G and 5G. The welder
assigned in this work shall meet the qualification under ANSI/AWS D1.1 or ASME Chapter I (see sub-chapter
9.1(3)). Alternatively, the welding procedures with supportive PQR (Procedure Qualification Record) as well
the record on qualification of welder certified under ASME Chapter IX can be changed with sub-chapter 9.1
(2).
Centering of piles which to be spliced has to be done before the welding are conducted.
PALU MINING POWER PLANT
2x10 MW
8.2.2 Welding
8.2.3 Inspection
All welding output shall be visually inspected based on acceptance standard and requirements in ANSI /
AWS D1.1 Section 8.15 “Quality of Weld” & Section 3.6 “Weld Profile”.
Welding shall not contain fracture, undercut of depth more than 0.8 mm, open surface porosity, and shall
not contain crust.
PALU MINING POWER PLANT
2x10 MW
Regarding PC Pile that enduring damage before cut-off elevation during piling or not being piled within the
tolerated limits as specified below, necessary actions shall immediately be taken to repair PC Pile or taking
other actions prior to COMPANY approval.
When pile driving for PC Pile group, it shall be driven from the inside part towards outside to prevent
densification and burdened piling in the inside part.
Re-driving is required if PC Pile lifted more than 25 mm to properly provide support towards PC Pile end.
If the pile driving of PC Pile will cause hazardous interruption towards the surrounding facility, structure, etc.
Contractor shall report to COMPANY to attain approval before starting the work.
Before starting the pile driving, if necessary, to make initial dig due to the following hole, CONTRACTOR
shall report to COMPANY to attain approval from starting the work:
To attain load service of particular design from PC Pile strength specified previously in statistic
calculation, therefore if clay is used, the diameter of initial hole shall not bigger than 75% of the pile size
and if sand is used, the diameter of initial hole shall not bigger than 50% of the PC Pile section.
To attain the desired design length, the dig of initial hole shall be stopped at minimum 3.0 meter
above the specified penetration level.
If necessary it is important to minimize displacement in the soft clay layer, and to handle part of PC Pile
emerging to the surface due to volume displacement, the diameter of initial hole to be drilled shall not
bigger than 75% of the outside size of pile and shall not smaller than 150 mm of the pile size.
Necessary benchmark survey needs to be undertaken after piling, if it is predicted that there would be
any part of the pile emerging to the surface.
8.4. Tolerance
Limits tolerated in the PC Pile Drive are as follows:
a. PC Pile shall be piled according to the tolerated limits as follows:
For batter pile, maximum slope is 1 cm for every 100 cm of pile length along longitude axis;
Maximum 75 mm in horizontal section of any direction of the position shown the drawing.
b. PC Pile shall be cut at specified elevation as shown in the technical drawing with tolerance of +/- 12
mm.
8.5. Reporting
In logbook on piling, Contractor shall store the complete record for each PC Pile and shall provide
information mentioned below every day to COMPANY:
a. Time and date of work commencement / termination for every piling work.
PALU MINING POWER PLANT
2x10 MW
b. Description on foundation, location, drawing number and PC Pile number (no double PC Pile number).
c. Size and type of PC Pile.
d. Pile hammer used (model, size, weight)
e. Total of blow and penetration
f. Elevation of ground surface.
g. Elevation of lower end of PC Pile if piling is completed.
h. Observation towards ground surface.
i. Cut off elevation.
j. PC Pile length existing.
k. Storing in center cut off level from its actual position.
l. Special remark if available.
This provisional driving criteria shall be have correction based on the result of PC Pile loading test and
PDA test (Pile Driving Analysis), of which the totality of PC Pile section acceptable under PDA test shall
not less than 75%.
PC Pile shall be piled according to the final piling criteria. The final piling criteria shall be specified based
on PC Pile loading test and PDA test (Pile Driving Analysis). Pile should be re-analyzed with the existing
length.
The spun pile’s characteristic should be analyzed with accordance to soil investigation result. The
bearing value (from end bearing and skin friction) will be different in certain soil condition.
Construct a weighted box or platform (Fig. 4) over the test pile, supported on cribbing or on other
piles installed after the test pile.
(i) Cribbing Support
For driven piles, drilled shafts or micropiles, locate the nearest face of the cribbing support not
less than 10 ft. (3 m) or 5 test pile diameters (whichever of the two criteria is the greater
distance) from the test pile or reference beam supports. Measure these distances between,
the test pile face and the nearest face of the cribbing supports. A greater spacing between the
cribbing supports and test pile or reference system may be required to prevent foundation
stresses caused by the cribbing from affecting the test.
(ii) Pile Support
For driven piles, locate these support piles not less than 10 ft. (3 m) or the sum of 5 support
pile diameters and 5 test pile diameters (whichever of the two criteria is the greater distance)
from the test pile or reference beam supports. For drilled shafts or micropiles, locate these
support piles not less than 10 ft. (3 m) or 5 reaction pile diameters (whichever of the two criteria
is the greater distance) from the test pile or reference beam supports. Measure these
distances between the test pile face and the nearest face of the pile supports.
Design the load beam and transfer beam to resist four times the pile design load indicated in
the contract documents, without undergoing a magnitude of deflection exceeding 75 percent
of maximum travel of the jack. Load the weighted box or platform with earth, sand, concrete,
water, pig iron, or other suitable material to obtain a total weight of at least four times the pile
design load indicated in the contract documents.
The load beam for a reaction frame may bear on the load transfer beam with no connections.
The load beam may need stiffeners at the points of bearing. The beam may need truss work,
not shown in the figure, to prevent excessive bending and resulting ram extension in excess
of the seventy-five percent (75%) of the maximum travel of the jack.
The pressure intensity exerted on the ground surface from any cribbing must not exceed the
bearing capacity of the soil or cause settlement of the test pile and/or measurement system.
Design the load beam and transfer beam to resist four times the pile design load indicated in
the contract documents, without undergoing a magnitude of deflection exceeding 75 percent
of maximum travel of the jack. Load the weighted box or platform with earth, sand, concrete,
water, pig iron, or other suitable material to obtain a total weight of at least four times the pile
design load indicated in the contract documents.
The load beam for a reaction frame may bear on the load transfer beam with no connections.
The load beam may need stiffeners at the points of bearing. The beam may need truss work,
PALU MINING POWER PLANT
2x10 MW
not shown in the figure, to prevent excessive bending and resulting ram extension in excess
of the seventy-five percent (75%) of the maximum travel of the jack.
The pressure intensity exerted on the ground surface from any cribbing must not exceed the
bearing capacity of the soil or cause settlement of the test pile and/or measurement system.
pile and the jack base. The size of the solid steel billet shall be not less than the size of the
pile butt or less than the area covered by the jack base.
Place the load application system (including hydraulic jack, spherical bearing andload cell)
between the bearing plate on the pile and the centre of the underside of the load beam.
To distribute load over the entire width of the load beam, place another solid steel billet of
sufficient thickness (1 in. (25 mm) minimum) as a bearing plate between the load beam and
the load application system.
Construct the system so that all components are centred along the pile's longitudinal axis, to
ensure application of a concentric axial load.
Immediately before starting a load test, verify that at least 1 in. (25 mm) of clear space exists
between the upper bearing plate and load beam, or the upper bearing plate and load
application system.
c. Measuring Apparatus and Site Protection
Provide apparatus for measuring deflection consisting of a primary system, at least one auxiliary
system, and a network of settlement reference points. Establish two fixed independent benchmarks at
least 50 ft. (15 m) from the test site to monitor the settlement reference points. If desired, the auxiliary
system may also be referenced to these benchmarks. Clearly identify all measuring devices, scales,
and reference points with numbers or letters to ensure accurate data recording:
1. Primary System for Measuring Devices (Figures 5 & 6)
Provide one of these primary instrument packages to monitor movement of the pile top:
Three linear variable differential transformers (LVDTs) and a readout unit. Use DC/DC-
type displacement transducers having at least 6 in. (150 mm) of travel and a linearity of
0.5 percent or less. Supply a readout unit having a minimum display of 3-1/2 digits,
capable of monitoring output from at least three DC/DC-type LVDTs.
Three dial gages having at least 2 in. (50 mm) of travel, an adequate number of suitable
gage blocks to increase the travel to at least an additional 4 in. (100 mm), and a precision
of 30 μm.
Align the measuring devices parallel to the longitudinal axis of the test pile and the axis of load
application. Attach the devices to a simply supported reference beam, completely independent of
the test pile and loading apparatus. Ensure the load application system will not interfere with any
measuring devices during any part of the test. For driven piles, embed the reference beam supports
at least 10 ft. (3 m) into the ground, at a horizontal distance of not less than 10 ft. (3 m), 5 reaction
pile diameters, or 5 test pile diameters (whichever of theses is the greater distance) from the closest
PALU MINING POWER PLANT
2x10 MW
face of the test pile and from any reaction piles or supports for the weighted box or platform. For
drilled shafts or micropiles, embed the reference beam supports at least 10 ft. (3 m) into the ground,
at a horizontal distance of not less than 10 ft. (3 m) or 5 pile diameters (whichever of the two criteria
is the greater distance) from the closest face of the test pile and from any reaction piles or supports
for the weighted box or platform.
Maintain a clear distance of 6 in. to 12 in. (150 mm to 300 mm) from the test pile to the reference
beam or any projection used to support a dial. The beam and projections should be at about the
same elevation as the attachments to the pile on which the measuring devices will bear.
Attach the dial gage supports to the reference beam so as to allow the stem of each device to rest
on an attachment to the pile sides. To mount hardware and pile attachments for LVDT devices use
materials, such as brass, aluminium, or 303 Series stainless steel, to avoid magnetic interference
with the instruments. The pile attachments are angles, about 3 in. x 4 in. (75mm x 100 mm) with
the 4 in. (100 mm) dimension projecting from the pile. For round piles, place these attachments on
the perimeter of the pile at a 120° spacing and an equal radial distance. For piles of other cross-
section, place the attachments at convenient locations as approved by the COMPANY.
Surfaces on which the gage stems bear should have a smooth finish, such as glass or sheet acrylic,
attached by an epoxy or other suitable material approved by the COMPANY.
PALU MINING POWER PLANT
2x10 MW
Maintain each load increment until the deflection rate under the applied load, or rate of rebound
from the previous load increment, is less than 50 μm in 15 minutes. The minimum period for
maintaining a load increment, however, is 30 minutes and an increment may be removed after
having been maintained for 2 hours, regardless of rate of deflection or rebound. When 200
percent of the design load has been applied during Cycle 3, provided the pile has not failed,
leave this load in place for 24 hours. When the pile has rebounded to zero load at the end of
Cycle 3, maintain zero load at least 1 hour. Maintain each load constant and note any
adjustments to the jack in the "Remarks" column on the Time-Settlement Data Sheet.
If the pile fails before application of the 200-percent load, rebound it to zero load as specified
in the table above.
PALU MINING POWER PLANT
2x10 MW
Figure 8 Typical of Cycle Load (in kN) vs Settlement (in millimetres) during Load Test
PALU MINING POWER PLANT
2x10 MW
Figure 9 Typical of Cycle Load Increment (in kN) vs Settlement (in milimeters) for static loading test
The capacity of the test piles was selected as the greater capacity defined by two failure
criteria. The first criteria establishes the allowable design capacity as "50 percent of the applied
test load which results in a net settlement of the top of the pile of up to 1.3 cm, after rebound,
for a minimum of one hour at zero load." The second criterion uses Davisson's criteria as
described below.
The Davisson offset limit load criterion was used on the project to define the ultimate capacity,
or failure, of the test piles. The ultimate load is interpreted as the point at which the
displacement of the pile head meets a limit that is offset to the elastic compression line of the
pile. For piles less than 61 cm in diameter, the limit is defined by the following linear
relationship:
S f S e 0.38 0.008D
where,
𝑠𝑓 = Movement of pile top (cm).
D = Pile diameter or width (cm).
𝑆𝑒 = Elastic compression of total pile length (cm).
PALU MINING POWER PLANT
2x10 MW
The elastic compression in this case refers to the pile deflection that would occur if 100 percent
of the applied load was transferred to the toe of the pile (i.e., zero shaft friction), and is given
by the following equation:
QL
Se
AE (2)
where,
Q = Applied load.
L = Total length of pile.
A = Cross-sectional area of the pile.
E = Modulus of elasticity of the pile.
The average load in the pile at the midpoint between two telltale locations was estimated from
the elastic shortening of the pile using the following equation:
D1 D2
Q avg AE (3)
L
where,
A = Area of pile.
E = Modulus of elasticity of the pile.
D1 = Deflection at upper telltale location.
D2 = Deflection at lower telltale location.
ΔL = Distance between the upper and lower telltale locations.
Both equations 2 and 3 require the modulus of elasticity of the pile. The specifications require
that the elastic modulus be determined via compression tests performed on representative
concrete samples (ASTM C 469-87a). However, this method is not really applicable to the
concrete-filled steel pipe piles. It was common practice on the CA/T project to use the upper
telltale and pile head deflections to calculate the modulus of the pile using equation 3. This
approach was justified by assuming that any pre-augering that was performed prior to pile
installation would reduce the shaft friction, especially near the pile head. In some cases, the
elastic modulus of the PPC piles was determined from a combination of telltale and
compression test data.
PALU MINING POWER PLANT
2x10 MW
Lift, align and rotate the pile to be tested with the PDA as directed by the PDA Consultant or the
CONTRACTOR. Place the pile in the leads and template so that the PDA instruments and their
accompanying wires will not be damaged.
The PDA Consultant or the CONTRACTOR will furnish the PDA measuring instruments and materials for
installing the instruments.
Attach the PDA instruments as directed by the PDA Consultant or the CONTRACTOR after the pile is placed
in the leads and the template.
Use only the preliminarily approved pile driving methods and equipment to drive piles with the PDA
instruments attached.
Drive the pile as directed by the PDA Operator or the CONTRACTOR in order to measure the wave speed
of the pile.
Drive the pile to the required bearing capacity and specified tip elevation, if applicable, as shown on the
plans or as directed by the PDA Consultant or the CONTRACTOR. During pile driving, the PDA will be used
to evaluate, including but not limited to, the following: hammer performance, bearing capacity, distribution
of soil resistance, pile driving stresses, energy transfer, pile integrity and various soil parameters such as
quake and damping.
The PDA Operator or the CONTRACTOR may require the COMPANY to approve modification of pile
installation procedure during driving as follows:
Reduce the hammer energy,
Drive deeper or shallower because of variations in the subsurface conditions,
Readjust the transducers
Realign the pile.
The CONTRACTOR is responsible in terms of both actual expense and time delays for any damage to the
PDA instruments and supporting equipment due to the CONTRACTOR’s fault or negligence. Replace any
damaged equipment at no additional cost.
When directed by the CONTRACTOR, reattach the PDA instruments and restrike or redrive the pile.
Obtain the required stroke and penetration (at least 6 in or 150 mm) or as directed by the PDA Operator or
the CONTRACTOR.
The PDA Operator or the CONTRACTOR will record dynamic measurements during restriking and redriving.
The CONTRACTOR may require restriking and redriving more than once on the same pile.
The CONTRACTOR will determine when PDA testing has been satisfactorily completed.
The PDA Consultant shall perform analysis of the PDA raw data with the CAPWAP (version 2006 or later).
PALU MINING POWER PLANT
2x10 MW
At a minimum, analysis is required for a hammer blow near the end of initial drive and for each restrike and
redrive.
Additional CAPWAP analysis may be required as determined by the PDA Consultant or the COMPANY’s
representative.
Submit three hard copies and an electronic copy (pdf or jpeg format on CD or DVD) of a PDA report to
CONTRACTOR within 5 calendar days and to COMPANY within 7 calendar days after field testing is
complete. The PDA report shall include but not be limited to the following:
1. Title Sheet
Project description
Pile location
Personnel
Report date
2. Introduction
3. Site and Subsurface Conditions (including water table elevation)
4. Pile Details
Pile type and length
Required bearing capacity and factor of safety
Concrete compressive strength and/or steel pile yield strength
Pile splice type and locations
Pile batter (if any)
Installation methods including use of jetting, preaugering, spudding, vibratory hammer,
template, barge, etc.
5. Driving Details
Hammer make, model and type
Hammer and pile cushion type and thickness
Pile helmet weight
Hammer efficiency and operation data including fuel settings, bounce chamber pressure,
blows per minute, equipment volume and pressure
Ground or mud line elevation and template reference elevation at the time of driving
Final pile tip elevation
Driving resistance (ram stroke, blows per foot (0.3 meter) and set for last 10 hammer
blows)
Restrike and redrive information
PALU MINING POWER PLANT
2x10 MW
11. LAMPIRAN