You are on page 1of 13

Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.

027) DUBAI

PROJECT: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I &


II (A.026 & A.027) DUBAI, UAE- MAIN WORKS

METHOD STATEMENT
Installation & Testing of above ground Drainage System

Project Name: ISLAND PARK I & II (A.026 & A.027)


Client: EMAAR
Supervision Consultant: Mirage Leisure and Development
Main Contractor: Fibrex Contracting LLC.
MEP Contractor: Spectrum Cube Technical Services LLC.

Doc. No. : DCHIP1&2-SPC-MEC-MST-0003

REVISION STATUS

Issue Rev Description Prepared by Reviewed By Approved By


Date Construction HSE Dept. QA/QC Dept. Project PM/PD
Manager
20.06.2023 00 MSRA For Abdul Rafik Jayakrishnan Britto Cleetus Ravi Srinivasan
Installation &
Testing of above
ground Drainage
System

DCHIP1&2-SPC-MEC-MST-0003 1 of 13 MSRA for Above ground drainage system Rev.0


Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

TABLE OF CONTENTS

1. PURPOSE

2. SCOPE

3. REFERENCE

4. DEFINITIONS

5. HUMAN RESOURCES (PROJECT TEAM AND RESPONSIBILITIES)

6. RESOURCES

6.1 MATERIAL AND THEIR APPROVAL


6.2 SHOP DRAWING APPROVAL
6.3 SUB CONTRACTOR APPROVAL
6.4 TOOLS & EQUIPMENT

7. HEALTH, SAFETY AND ENVIRONMENT

8. PROCEDURE (CONSTRUCTION SEQUENCE / METHODOLOGY)

8.1 Pre-installation checks


8.2 Installation of above ground drainage pipes & fittings
8.3 Test for drainage pipes (Gravity test / Pressure test)

9. CONSTRUCTION PROGRAMME:

10. APPENDICES

10.1 RISK ASSESSMENT (RA)


10.2 INSPECTION & TESTING PLAN (ITP)
10.3 METHOD STATEMENT BRIEFING SHEET
10.4 CHECK LIST SHEET
10.5 TEST REPORT

DCHIP1&2-SPC-MEC-MST-0003 2 of 13 MSRA for Above ground drainage system Rev.0


Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

1. PURPOSE

This document defines the methodology, sequence, control measures, safety and quality control
requirements, including tools and equipment intended to be used in performing the works as
established in the project specifications and relevant referenced documents to Installation & Testing
of above ground drainage system

2. SCOPE

This Method Statement is for Installation and testing of above ground Drainage System as set out in
the specifications, approved drawings, codes and DM standards referenced within DCHIP Project
Control Documents.

3. REFERENCE: All works shall comply with the relevant requirement standards listed below:

3.1 Project Specifications:


3.2 Approved Project Quality Plan
3.3 Approved HSE Plan
3.4 Approved Construction Drawings/ IFC
3.5 DM Requirements, specified in the Contract/ Project Specifications

4. DEFINITIONS

4.1 Client EMAAR


4.2 ENGINEER Mirage Leisure and Development
4.3 MAIN CONTRACTOR Fibrex Contracting LLC (FC)
4.4 MEP CONTRACTOR Spectrum Cube technical Services LLC (SPC)
4.5 QA/QC Quality Assurance/Quality Control
4.6 HSE Health, Safety and Environment
4.7 ITP Inspection and Test Plan

5. HUMAN RESOURCES (PROJECT TEAM AND RESPONSIBILITIES)

Project Manager shall review and approve the methodology for the execution of the works, and
ensure that the works are implemented in an efficient manner. The Project Manager is generally
responsible for the overall project execution, quality and safety.

DCHIP1&2-SPC-MEC-MST-0003 3 of 13 MSRA for Above ground drainage system Rev.0


Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

Construction Manager is responsible for the implementation of method statement and ensures
that all involved site construction personnel are aware of this method statement and shop drawings
are followed. He shall ensure that the execution of works shall be carried out in safe manner. He will
also be responsible for the monitoring of the work progress on daily basis to ensure activities are
accomplished as per the construction program

Site Engineer Shall ensure that the works are carried out according to the design, approved shop
drawings and procedures. He will be responsible on behalf of the Contractor to coordinate, check and
follow up the work with relevant parties and ensure that proper sequence of activities is followed in
order to achieve target completion. He will ensure that safe work practices are followed for all works
under his care.

MEP Coordinator/ Engineer will coordinate with the Construction Manager/ or Site Engineer in
advance of all MEP services interfacing with the work schedules and progress. He will coordinate with
the MEP subcontractor and ensure that all MEP services/ sleeves/ openings are identified and
completed. Inspection Request will be raised to the Employer for MEP services/sleeves/openings
installations were shown in the approved shop drawings. A copy will be forwarded to the QA/QC
Engineer for all submitted Inspection Request with copies of approvals.

QA/QC Engineer shall ensure that works are carried out in accordance with the Quality Plan. He shall
ensure that all ITP requirements are met. The QA/QC Engineer shall ensure that the inspection
request for inspections and testing are raised and submitted to the Employer on time. He shall ensure
that materials being used are in accordance with project specifications and approved by the Employer.

INSPECTION & TESTING

1. The QA/QC Engineers shall ensure that the inspections are completed in accordance with the ITP
requirements. They will conduct random inspections as per the ITP requirements to verify compliance
with the specification and design drawings.
2. They shall ensure that the Site Construction Team will use the latest revisions of approved
drawings/ documents on site.
3. Any discrepancies found during an inspection will be immediately communicated to the
Construction Manager/ Project Engineer/ Site Engineer for rectification and compliance with specified
requirements. Discrepancies should be rectified prior to the Engineer’s inspection.

Surveyor shall be responsible for setting out the location, line and levels, plus other dimensional
requirements in accordance with the design drawings and approved shop drawings.

Safety Engineer / Safety Officer will monitor and implement all HSE related issues. He shall ensure
that all necessary requirements regarding health, safety and environment concerns, risk assessment
are met and adhered to. The Safety Engineer shall ensure that all permits and authorization are on
hand (as per Project HSE Plan) prior to starting any site operation (if required).

DCHIP1&2-SPC-MEC-MST-0003 4 of 13 MSRA for Above ground drainage system Rev.0


Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

Foreman / Supervisor will be responsible to carry out the work in safe manner and to supervise
the work force together with the proper execution and monitoring of works, and all appropriate
checks will be carried out during each stage of the works.

Subcontractor: Spectrum Cube Technical Service LLC. shall be responsible for the execution of the
work in accordance to the project specifications and to the satisfaction of the main contractor and
approval of the Employer.

6. RESOURCES:

6.1 Materials and their approval

Reference Project specification: Volume-05, Part-E, Section 05- Soil, Waste, Vent & Storm
u-PVC Pipe and fittings to BS EN 1329-1 (BS 4514) for pipe sizes 80mm diameter and above.
u-PVC Pipe and fitting to BS EN 1455 & BS EN 1566-1 for pipe sizes 50mm diameter and smaller.
HDPE Pipes and fittings to DIN 19560 / DIN EN 1451 for commercial Kitchen waste pipe.
u-PVC Pipes, Class E & D to BS EN 1452-2 and u-PVC Fittings to BSEN 1452-3 for underground
condensate drain & Sump pump discharge application

6.2 Shop Drawing approval

• Ensure that latest approved shop drawing for this installation is present and all personnel are
working from the same drawing.
• All the comments on drawing are understood.

6.3 Sub Contractor approval

Reference # DCHIP1&2-FC-MEP-PQN-001

6.4 Tools and Equipment

 Personal Protective Equipment (PPE): Safety helmet, safety gloves, safety shoes, eye protection
or goggles, approved respirator and safety jacket.
 Below listed tools and Equipment’s are used
• u-PVC / HDPE Pipe and Fittings
• Butt welding machine
• Portable plumbing Hand Tools
• Measuring Tape/ Spirit Level/ Plum Bob
• Ladders / Hydraulic pallet trolly
DCHIP1&2-SPC-MEC-MST-0003 5 of 13 MSRA for Above ground drainage system Rev.0
Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

• Lifting tools and tackles / Flat-bed truck


• Boom truck, fork lift, slings, etc.
• Chamfering tools / MEWP
• Hacksaw frame and blade
• 110/230V Drilling machine

• PPE – Overall, Helmet, Boots, Glasses, Gloves.

7. HEALTH, SAFETY AND ENVIRONMENT

 General PPE is mandatory for all personnel will consist of safety boots or shoes, safety helmet,
safety gloves, HI-VI2 vest or shirt and overalls (for workers). Other PPE requirements will be
determined by Risk Assessment as the work proceeds and other hazards are anticipated i.e.
working at height/ or at the leading edge of a structure.
 Prior to commencement of any activity, HSE Personnel, the Site Engineer, will give all operatives in
a general site safety induction/ Supervisors will also conduct Tool Box talks and method statement
briefings to the personnel involved in operation.
 The emergency response procedure should be conveyed to the work men through the toolbox talk
prior to the carrying out of the activity.
 In case of emergency, the workers should follow the emergency response procedure and must
gather in the designated assembly point.
 In case of fire / emergency, evacuate the work area to the designated assembly points.
 In the event of an accident or incident immediately, notify the Project Manager and HSE Manager.
 Refer to the attached Risk Assessment and Control Measures

8. PROCEDURE (CONSTRUCTION SEQUENCE / METHODOLOGY)

8.1 Pre-installation checks

A pre-start meeting prior to the commencement of the works will take place with the Site
Engineer, H&S office, Supervisor /Foreman in charge to address the following:
 Ensure that the area has been surveyed as per approved drawings
 Ensure the installation area is safe, clean from debris & foreign matter.
 Ensure that adequate number of tradesmen and proper tools are present and all people have
knowledge of the method statement.
 Comply with project specifications, technical report and manufacturer recommendations.
 All related drawings will be submitted to consultant for approval, approval endorsed and
checked prior to the works commencement.
 Follow Local Authority / DM regulation & standards.
DCHIP1&2-SPC-MEC-MST-0003 6 of 13 MSRA for Above ground drainage system Rev.0
Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

8.2 Installation of above ground drainage pipes & fittings

Marking of Supports

Pipe route, supports, hangers & spacing of marking shall be done as per approved shop drawing and
project specification.

Installation of Supports

Make drill hole on the sofit and fix anchor.

Threaded rods and slotted channels shall be prepared in the workshop.

Fix the threaded rods and slotted channels securely into the slots.

General Installation Comments

Wall penetration area G.I Sleeve shall be provided and sealant to be applied.

Pipe supports and anchors to be installed as per Project specification.

Pipe size and pipe route to be verified prior to start the installation of work.

Drainage pipe invert level shall be maintained as per shop drawing.

All Installed clean-outs shall be accessible location.

Pipe identification label shall be provided for all pipes.

Installation of u-PVC pipes

 Before Installation, all pipes and fittings shall be checked for defects.
 Check the working area is clean, safe with all the necessary marking signs, secured against
unauthorized access.
 Check size of the pipes on delivered to site as per the approved MAR, Shop drawings and
project specifications.
 All pipes shall be inspected for cleanliness and damage prior to installation and further
DCHIP1&2-SPC-MEC-MST-0003 7 of 13 MSRA for Above ground drainage system Rev.0
Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

cleaning shall be carried out after the works has been completed if necessary.
 Drainage pipe route shall be marked as per approved shop drawing.
 Approved materials such as pipes, fittings, anchors, hangers and support clamps shall be used.
 Prior to fix the pipe, cut it exact to a length as per drawing, de-burr the edges and clean the
ends.
 All pipes, supports and anchors shall be installed as per project requirements.
 Pipes to be pushed to full socket depth, withdrawal pipe 5mm/As per manufacturer’s
recommendation on the waste system and 10mm on soil system to allow for expansion.
Repeat the same procedure for the entire length of the pipe run.
 Push fit fittings shall be used during connection lubricant to be applied.
 Drainage pipe support to be fixed as per Project Specification.
 Drainage pipe slope to be maintained as per shop drawing.
 SP, WP double stack pipes connected with vent pipes for each level.
 No short radius bends to be used in vertical pipe.
 To provide the space between two pipes and sleeves, if wherever required.
 Horizontal run SP, WP shall be vent pipe connection on top end.
 All Balcony drain pipes are connected with waste pipe. Ensure that U-trap provided for balcony
drain pipe.
 Vent pipe shall be terminated at top roof with vent cowl and height 2.0 meter from the FFL.
 Vent pipe shall be installed 5.0 meter away from any air intake louver.
 Sanitary fixtures are installed and pipes are connected with drainage system.
 Drainage pipe to be tested by gravity test or pressure test.
 Rain water pipes shall be installed as per shop drawing and approved materials to be used.
 All Rain water pipe network connected with Inspection chamber.
 Submersible pump discharged pipes shall be installed as per shop drawing and approved
materials to be used.

 Installation of CDP pipes


 Installation of CDP pipes shall be installed as per shop drawing and approved materials to be
used.
 Condensate drain pipe shall be provided for FCU, FAHU & Pump room.
 U-trap shall be provided near the Unit or Equipment.
 PVC Solvent cement jointing glue shall be used for pipe connections.
 Rubber insulation to be provided for CD pipe.

 Installation of Clean-outs
 Clean-out shall be provided at change of direction and long run more than 15.0 meters.
DCHIP1&2-SPC-MEC-MST-0003 8 of 13 MSRA for Above ground drainage system Rev.0
Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

 Clean-out shall be installed in accessible location.


 Clean-out back support shall be provided for each Clean-out.

 Installation of HDPE pipes (for Commercial Kitchen waste pipe)


 The HDPE pipe route shall be marked as per shop drawing and approved materials to be used.
 Wipe the pipe surface to remove the dust particles and other contaminants.
 Ensure that the prepare pipe surfaces are completely dry before proceeding the welding work.
 The pipe, fitting & jig must be aligned and free from any bending stress.
 Ensure that the pipe and fittings supported properly to prevent it sagging during welding
process.
 Butt fusion joint welding machine shall be used.
 2 fixed & 2 movable clamping blocks to hold the pipes or fittings.

 Pipes or fittings fully inserted between two clamping blocks prior to welding process.

 Press the start button on the control box and check the required temperature setting to be
adjusted. The Temperature range from 150 degree to 300 degree Celsius.

 During welding process, the pipes shall be pressed together and welding to be formed.

 Weld fit setting and jointing time shall be 20minutes takes place for each joint.

 Butt joint welding done successfully and clamps to be opened after the welding work.

 The welding machine to be removed carefully from the joint.

 Upon completion of welding work and rise inspection for Engineer’s approval.

Below sequence to be followed for pipe jointing for Gravity Drain Pipes.

Type of joints to be as per approved Material Submittal.

DCHIP1&2-SPC-MEC-MST-0003 9 of 13 MSRA for Above ground drainage system Rev.0


Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

Below sequence to be followed for pipe jointing for Pressurized drain pipes.

DCHIP1&2-SPC-MEC-MST-0003 10 of 13 MSRA for Above ground drainage system Rev.0


Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

DCHIP1&2-SPC-MEC-MST-0003 11 of 13 MSRA for Above ground drainage system Rev.0


Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

 On completion of each pipe section, check and adjust if necessary to ensure the proper level
and alignment of pipe.
 After completion of a section of pipework install temporary caps to any open ends before
leaving the worksite.
 Attach and fix the identification labels, safety, and warning signs at the locations as mentioned
in the approved material submittal and as required by the standards and specifications.
 After the complete installation of waste, soil and rainwater above ground piping system, a
preliminary inspection of the whole system will be conducted.
 A final inspection for installation will be done in coordination with the Consultant prior to
starting the gravity test.

8.3. Gravity test for drainage pipes:

 Above ground drainage pipes shall be tested by plugging the end of the pipe and filling the
water to a minimum of 3.0meter column head to keep.
 The segment or portion of pipe work to be tested shall be slowly filled from the possible
lowest point with clean domestic water and air is released at all high points in the system until
the system is completely full.
 During each phase of installation, carry our interim leakage tests using water head, to ensure
and prove the firmness and leak free of joints.
 All openings of pipes should be closed with expansion test plug.
 High level end of the pipe is connected to a 90-degree elbow and is connected to a piece of
pipe, in order to get a minimum column head of 3.0 meter of water from the low-level point.
The vertical pipe should be supported then start filling the water into the pipe through water
hose.
 Fill water carefully to minimize the air bubbles trapped in the line then open, small opening in
the expansion test plugs such that all air trapped in the line should washed out. Again, fill
water up to the required level of 3.0-meter column head and keep this pressure head for 4
hours.
 All joints should be visually inspected for any leakage during the test and any leakage if found,
shall be rectified and test repeated until there is no loss of water in the stand pipe.
 After 4 hours, if there is no decrease in level is observed, then the system will be considered
tested successfully. In case of any decrease in level, find out the leak in joints and re-do the
test.

Pressure test for drainage pipes (Sump Pump Discharge Application)

 All Pipe network shall be completed prior to pressure testing.

DCHIP1&2-SPC-MEC-MST-0003 12 of 13 MSRA for Above ground drainage system Rev.0


Project Name: DUBAI CREEK HARBOUR DEVELOPMENT – ISLAND PARK I & II (A.026 & A.027) DUBAI

 Systems may be tested as a whole or in sections to facilitate the progress of the work.
 The piping system to be tested shall be closed by plugging and blanking all openings in the
system in an approved manner and filled slowly with water and air bubbles to be released.
 Plugs shall be released temporarily to ensure that water has reached all parts of the system.
 Pressure shall be applied to the system by means of a hand pump with a water container. The
pump discharge shall be connected to the system through Isolation Valve and recently
calibrated pressure gauge to be used during pressure testing.
 After the test pressure is reached, the pump shall be blocked off by closing the Isolation Valve
and the variations of pressure in the system monitored on the pressure gauge.
 The test pressure shall be maintained on the system for a min of 4 hours during which time the
system shall have no noticeable drop in pressure.
 While the system is under pressure, a careful inspection shall be made of all pipes and joints
and if any leaks in joints or evidence of defective pipe or fitting is disclosed the defective work
shall be corrected immediately by replacing defective parts with new joints and materials. No
makeshift repairs or application of any repair compound will be permitted.
 After the correction is made the pressure test shall be repeated until a completely tight system
is ensured.
 The test pressure shall be released slowly so as not to produce shocks and sudden contractions
that might damage the piping.
 System test pressure to be monitored for 4 hours.
 All pipe network shall be tested to at least 1.5 times the system working pressure.
 No part of any piping system shall be tested to pressure less than the specified test pressure
measured at the highest point of the system.

9. CONSTRUCTION PROGRAMME:

Working program submitted to Employer.


10. APPENDICES
10.1 Risk assessment (RA)
10.2 Inspection and Testing Plan (ITP)
10.3 Method Statement Briefing Sheet
10.4 Check list Sheet
10.5 Test Report

DCHIP1&2-SPC-MEC-MST-0003 13 of 13 MSRA for Above ground drainage system Rev.0

You might also like