Professional Documents
Culture Documents
Table of contents
1. Scope/Objectives
2. Reference
5. Definitions
6. Responsibilities/Supervision
7. Sequence/Method to be employed
8. Man-power requirement
9.Equipment/Materials requirement
11.Supporting documentation
12.Distribution
13.Other Information
14.Attachments
1
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
2
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
6.4. QA / QC Engineer:
To check the work is carried out as per the approved method statement.
7 Sequence/Method to be Employed
The sequence/method/procedure for the erection of the tower crane will be followed as
per the attached Method statement for Erection by M/S. Modern Emirates.
8. Man Power Requirement
Site Engineer
P&M Engineer
Foreman
Charge hand
Mason
Skilled and unskilled labour
9 Equipment/Materials required
Mobile crane or Tower crane
10. QC APPROVAL AND OTHER DOCUMENTRY REQUIREMENTS
Follow approved Method Statement, ITP, QCP, HSE Plan, and Material Approval.
11. SUPPORTING DOCUMENTATION
This MS to be read in conjunction with the below referenced documents
Contract Drawings and specifications
Project Quality Plan
Project HSE Plan
3
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences