PROJECT NAME
DEWA DUBAI ELECTRICITY & WATER AUTHORITY / DUBAI
CLIENT MUNICIPALITY
CIVIL DESIGN
M/S. DERBY DESIGNS
CONSULTANT
MAIN
M/S. DANWAY ELECTRICAL & MECHANICAL ENGINEERING
CONTRACTOR
SUB
M/S. SANDS CONTRACTING CO. L.L.C.
CONTRCATOR
Mr. Anish Kumar Mr. Arun Kandi Mr. Fiorald Liko Mr. Sirajudeen
APPROVAL STATUS:
Code 2 Revise and resubmit; Work may proceed subject to incorporation of comments indicated.
CONTENTS
SHEET NO.
2. SCOPE OF WORKS 3
3. RESPONSIBILITY 3
4. REFERENCES 3
7. QUALITY CONTROL 5
11. ATTACHMENTS 6
CLIENT: CONSULTANT: CONTRACTOR: CIVIL CONTRACTOR:
The purpose of this Method Statement is to outline the sequences and the methods of works
intended to be used for Pile Head Treatment Works.
Method Statement used in Pile Head Treatment works shall be such as not to cause damage to
surrounding property and also, to ensure that work will be executed safely
2. SCOPE OF WORKS
This procedure provides a Method Statement of control of Pile Head Treatment as per the
specification / approved drawings (RFC) in order to achieve the compliance.
3. RESPONSIBILITY
3.1 Project Manager : Leads all construction activities and enforces strict adherence
to all project requirements and reports to the Divisional
Manager.
3.2 Site Manager : Leads all construction activities and enforces strict adherence
to all project requirements and reports to the Project
Manager
3.3 Engineers : Ensure that all related works are carried out in accordance
with the approved drawings, specifications, schedule, quality
and safety. They will report to the Project Manager.
3.4 Supervisor or Foreman : Supervises the entire installation at the field and reports to
the Engineers.
3.6 Site Safety Officer : Shall ensure periodical tool box talks, check for PPE, to ensure
safe execution of work as per HSE
Plan
4. REFERENCES
1. Project Specifications
2. Approved Drawings
- Bobcat - 01 No
- Drill Machine - 01 No
- Shovel - as required
- Survey instruments, like auto level, total station, etc.
Apply approved primer & water proofing membrane material on the top of blinding
concrete.
The water proofing membrane will be extended up to the
portion of the pile head 25 50 mm from the outer edge of the pile head.
Formwork will be fixed around the pile for grouting 20 50 mm thickness shrinkage
compensated free flowing concrete of high strength all around outer face of the pile.
After the completion of waterproofing pile Grout minimum thickness 50mm POLYGROUT
EY 3000 PH as per approved RFC drawing.
After completion of grouting curing shall be carried out as per specification.
After finishing of surface preparation start applying two coats elastomeric cement
waterproofing NITOCOTE CM210 (Approved material) by using roller or brushes on the
top around (vertical) the piles in accordance to the approved drawings.
Mock-up sample of pile head treatment/membrane shall be prepared and inspected.
Full attention shall be implemented wile breaking the pile in order to avoid any damages.
In case of damaged pile, the pile shall be repaired by approved material up to required
cut of level.
7. QUALITY CONTROL
All works shall be executed in compliance with quality requirements as per Project
Quality Plan.
The quality control measures will be conveyed to all concerned personnel involved the
execution of work by QA/QC Engineer, prior to commencement of work.
Only trained, legal & third party certified operatives can operate the plant items The
foreman will conduct tool box talk in the presence of HSE
officer at regular intervals and will submit copy of records to
HSE department.
Project specification