ELCTRICAL WORK METHOD

STATEMENT

MICROSOFT SITE OFFICE


MEHTOD STATEMENT FOR CONDUIT INSTALLAION

Prepared BY VKBS Reviewed by API Approved by Client

Name: Name: Name:

Sign: Sign: Sign:

Date: Date: Date:

INDEX
S.No Description of index
1.0 PURPOSE OF WORK

2.0 SYSTEM DESCRIPTION


3.0 RELATED WORKS
4.0 REFERENCE DRAWINGS
5.0 SAEFTY
6.0 TOOLS AND EQUIPMENTS
7.0 UNLOADING ,SHIFTING & STORAGE PROCEDURE
8.0 INSTALLATION PROCEDURE
ELCTRICAL WORK METHOD
STATEMENT

1.0 PURPOSE OF WORK:


This method statement explains the detailed requirements and procedures for the installation of
PVC Conduits and accessories in the concrete slabs, columns, block works and concrete walls.
2.0 SYSTEM DESCRIPTION:
The purpose of this method statement is to clearly define the installation procedures and
methodology to be implemented for the PVC conduits installation activities in the Project

3.0 RELATED WORKS:

To ensure that all the Conduiting is done according to the Contract Specification and
with the approved drawings.

4.0 REFERENCE DRAWINGS :

The drawings to be referred are:


 General Arrangement Drawing of the Respective Location
 Floor Opening Drawings of the Respective Location.
 Approved Shop drawings.
 Approved SLD .
5.0 SAFETY:

S.No Procedure Responsibility Checked By Remarks

1 All personnel engaged shall attend safety Safety Officer/ Safety Officer
induction program conducted by safety officer. Site/Project by PMC / GC
Engineer

2 All personnel should have PPE gloves, High Safety Officer/ Safety Officer

visibility jacket and all other PPE. Site/Project by PMC / GC


Engineer

3 Work areas and access way are to be free from Safety Officer/ Safety Officer
all hazards.
debris, materials and Site/Project by PMC / GC
Engineer
ELCTRICAL WORK METHOD
STATEMENT

4 All hand tools and portable power tools shall be Safety Officer/ Safety Officer
of good order / condition and shall be used for Site/Project by PMC / GC
intended.
the purpose Engineer

5 All work on Energized Systems shall be done Safety Officer/ Safety Officer
to Work System.
with a Permit Site/Project by PMC / GC
Engineer

Earthing / cordoning off to be done prior


6 Proper Safety Officer/ Safety Officer
to Commencement of work, if working in
Site/Project by PMC / GC
energized environment.
Engineer

7 Ensure proper illumination is provided in the Safety Officer/ Safety Officer


area. Site/Project by PMC / GC
Engineer

proper care shall be taken for the exposed


8 Safety Officer/ Safety Officer
cables/wires/switches with necessary sign age
Site/Project by PMC / GC
boards.
Engineer

9 No materials shall be stacked very near to work Safety Officer/ Safety Officer

place. Site/Project by PMC / GC


Engineer

10 Safety belts are compulsory above 1.8 Meter’s Safety Officer/ Safety Officer

height from floor level. Site/Project by PMC / GC


Engineer

11 Regular House Keeping should be done. Excess Safety Officer/ Safety Officer
materials should immediately be returned to Site/Project by PMC / GC
store/ yard Engineer

6.0 TOOLS AND EQUIPMENTS :


ELCTRICAL WORK METHOD
STATEMENT

6.1 Installation Tools:

 Step ladders

 Measurement tape
 Continuity tester
 Spanners & Multimeter
 Spirit level, torque wrench
 Screw Driver
 500V D.C. Megger
 Earth tester.
 Cutting pliers.
 Movable ladders.
 Insulation tape.

6.2 Safety Tools :


 Nose Mask
 Safety Goggles
 Full body safety harness with double lain yard.
 Hand gloves
 Mobile Scaffolding of Appropriate Height

7.0 UNLOADING , SHIFTING & STORAGE PROCEDURE :

S.No Procedure Responsibility Checked Remarks


By

Necessary precautions shall be taken for unloading, shifting & storage as follows:
1 Pvc Conduits shall be carefully off-loaded by using QA/QC
necessary / adequate tools and manpower and to be kept Engineer
in dry place and barricaded to avoid damages. Site / Project / PMC
Engineer

2 Conduits and fitting material shall be inspected by GC & Site /Project QA/QC
PMC before using the material and stored properly in a Engineer Engineer
specified place / dry place at all the time. / PMC

3 Conduits and fitting material received at site shall be Site /Project QA/QC
inspected and ensured that the materials are as per Engineer
ELCTRICAL WORK METHOD
STATEMENT

approved TDS. Engineer / PMC

4 Discrepancy or damage in the material shall be notified to Site /Project QA/QC


the supplier and reported for further action. Material Engineer Engineer
found not suitable for site shall be removed from site upon / PMC
client / GC approval.

8.0 INSTALLATIONS PROCEDURE :

S.No Procedure Responsibility Checked Remarks


By
1 Refer the latest approved drawing of Circuit from Site /Project QA/QC
DB to points. Engineer Engineer
/ PMC

2 Make Proper cutting chipping in wall/areas where the Site /Project QA/QC
conduits are to be embedded. Engineer Engineer
/ PMC

3 Carry out physical verification for any possible damage. Site /Project QA/QC
Engineer Engineer
/ PMC

4 Fix the conduits properly using Saddles/nails. Site /Project QA/QC


Engineer Engineer
/ PMC

5 Check the route and location cclearance. Provide proper Site /Project QA/QC
marking of routes. Engineer Engineer
/ PMC

6 Check the location of points to which conduits are to be Site /Project QA/QC
laid. Engineer Engineer
/ PMC

Proper fixing of saddle (Provide finishing & Site /Project QA/QC


7
distance between saddle) Engineer Engineer
/ PMC

8 Check for damage to galvanization of conduit during Site /Project QA/QC


installation and Continuity of conduit system and Earthing Engineer Engineer
of lighting panels and space heater panels. / PMC
ELCTRICAL WORK METHOD
STATEMENT

9 Provide galvanized paint on exposed threads.Provide red Site /Project QA/QC


band on conduit of emergency light. Engineer Engineer
/ PMC

10 Observe the conduits terminated properly and Site /Project QA/QC


neatly at the panel/switch board/junction Engineer Engineer
boxes/lighting. / PMC