Professional Documents
Culture Documents
METHOD STATEMENT EXCAVATION & ENABLING WORKS FOR TC5 & TC10 TOWER CRANE
FOUNDATION AT NW3 & SW3.
Table of contents
1. Scope/Objectives
2. Reference
5. Definitions
6. Responsibilities/Supervision
7. Sequence/Method to be employed
8. Man-power requirement
9.Equipment requirement
10.Materials requirement
12.Supporting documentation
13.Distribution
14.Other Information
15.Attachments
1
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
METHOD STATEMENT EXCAVATION & ENABLING WORKS FOR TC5 & TC10 TOWER CRANE
FOUNDATION AT NW3 & SW3.
1. Scope/Objectives
This method statement is to detail & to establish sequence of activities to carryout excavation
& enabling works for TC5 & TC10 tower crane foundation at NW3 & SW3.
2. Reference
2.1 Contract Drawings
5120544/GEN/S/0101, 105-REV00
5120544/SPO/S/2001-REV: 00,
5120544/SPO/S/2002-REV: 01,
5120544/NPO/S/2002-REV: 01
5120544/NPO/S/2002-REV: 01
5120544/SPO/S/2002-REV: 01
2.2 specifications 5120544-D-2001-D-20
2.3 Project Quality Plan TS-ABM-CIV-PQP-0012 R.1
2.4 HSE Plan TS-ABM-CIV-HSE-0014 -R.1
3. Access/Egress and Location
Access to the work place will be through designated and exit pathway.
4. Health & Safety
4.1.Contractor will comply with all safety measures as applicable to project safety
requirement.
4.2.PPE will be worn at all times as required.
4.3.Proper and safe access and enough barricades to the work areas shall be installed &
maintained throughout the working period.
4.4.Proper communication should be ensured.
5. Definitions
ATK-ATK Engineering & Consultant
ABM-Al Basti & Muktha LLC
MS-Method Statements
QCP-Quality Control Procedures
6. Responsibilities/Supervision
2
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
METHOD STATEMENT EXCAVATION & ENABLING WORKS FOR TC5 & TC10 TOWER CRANE
FOUNDATION AT NW3 & SW3.
3
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
METHOD STATEMENT EXCAVATION & ENABLING WORKS FOR TC5 & TC10 TOWER CRANE
FOUNDATION AT NW3 & SW3.
4
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
METHOD STATEMENT EXCAVATION & ENABLING WORKS FOR TC5 & TC10 TOWER CRANE
FOUNDATION AT NW3 & SW3.
Construction Manager
Site Engineer
QA/QC Engineer
HSE Engineer
14. OTHER INFORMATION
Ensure that all the activities have been carried out to suit the site conditions and involved with
Site in Charge.
15. ATTACHMENTS
Risk Assessment
Section Drawings