METHOD STATEMENT

FOR PCC WORK


METHOD STATEMENT FOR PCC
WORK

REV NO : 00 DOC No : Antenna-DC-01-PCC- DATE : 15/11/2023


MS-001

DOCUMENT CONTROL

Prepared By

Draft Author Company Date Signature

Reviewed By

Version Reviewer Company Date Signature

Approved By

Version Approver Company Date Signature

Record of Revisions

Date Revision No Details of Revision Page Affected


METHOD STATEMENT FOR PCC
WORK

REV NO : 00 DOC No : Antenna-DC-01-PCC- DATE : 15/11/2023


MS-001

CONTENTS

1. OBJECTIVE Page 04

2. SCOPE Page 04

3. REFERENCE Page 04

4. EQUIPMENT TOOLS AND TACKELS Page 04

5. MATERIAL USED Page 05

6. PROCEDURE Page 05

A. PRECAUTIONS BEFORE START OF CONCRETE WORKS Page 05

B. SAMPLING AND TESTING OF FRESH CONCRETE Page 05

C. TRANSPORTATION Page 05

D. CURING Page 05

7. METHODOLOGY OF QUALITY INSPECTION Page 07

A. PERSONNEL Page 07

B. BEFORE CONCRETING Page 07

C. DURING CONCRETING Page 07

D. AFTER CONCRETING Page 07

8. RESPONSIBILITIES Page 07

9. CHECKLIST FOR PCC WORK Page 09


METHOD STATEMENT FOR PCC
WORK

REV NO : 00 DOC No : Antenna-DC-01-PCC- DATE : 15/11/2023


MS-001

1. 0BJECTIVE:
The objective of this method statement is to execute PCC works meeting the construction

requirements and technical specifications. Being strong in compression, concrete play a vital role

in enhancing the strength of a structure.

2. SCOPE:
The scope of PCC is to provide a uniform level, impermeable layer to water, a strong base to

foundation and to prevent termite attacks to the structure.

3. REFERENCE :
 IS 456-2000 (Reaff Feb 2016) Code of practice for plain and reinforced concrete

 " IS 2571-1970 (Reaff Jan 2017) Code of practice for laying in-situ cement concrete

4. EQUIPMENT TOOLS AND TACKLES :

Concrete batching plant

 Concrete transit mixtures


 Tower Crane/mobile Crane
 Vibrator & needle
 Aluminium straight edge
 Mason trowel
 String Line / Plumb bob
 Measurement tape
 Concrete buckets
 Total Station
 Nylon thread
 Pumps to place concrete
 Wire brush mesh
 Thermometer
METHOD STATEMENT FOR
PCC WORK

REV NO : 00 DOC No : Antenna-DC-01-PCC- DATE : 15/11/2023


MS-001

5. MATERIAL USED:

 Concrete of Approved design mix


 Hessian cloth for curing
 Water
 Approved Bonding agent
 Foam sheet
 Cement and crusher sand for making bunds for curing

6. PROCEDURE:

A. PRECAUTIONS BEFORE START OF CONCRETE WORKS

Prior to start concrete works; following shall be ensured:

 Ensure all required work permits are obtained.


 Ensure all predecessor activities are approved.
 Ensure relevant mix design is approved.
 Checklist for both PCC shall be signed before the pour by all respective in-charges
 Ensure all tools and equipment are gathered
 Batching time, grade of concrete, vehicle reached time, slump test shall be verified. Only
passed/approved vehicle shall be allowed to pour concrete.
B. TRANSPORTATION:

The concrete once prepared can be shifted in the following ways:


 Chutes
 Wheel barrows
 Concrete buckets and tower cranes
 Line Pump
METHOD STATEMENT FOR
PCC WORK

REV NO : 00 DOC No : Antenna-DC-01-PCC- DATE : 15/11/2023


MS-001

C. PLAIN CEMENT CONCRETE (PCC):


 Ensure concrete mix is approved prior to start work
 In case of water stagnation in excavated areas, the same should be dewatered using
suitable motor
 After de-watering, the slush has to be removed.
 Ensure proper compaction and surface preparation (removing dust / debris).
 Ensure the compaction test is carried out in over excavated area after backfilling.
 If necessary, soling has to be done prior to concreting so as to provide impermeable bed to
the PCC.
 Soling is the process of hand packing rubble stones one adjacent to another, to provide a
stable base to the PCC and footing, before concreting work.
 Ensure the measurement length, breadth and depth.
 Ensure thickness of concrete as per requirement.
 Provide edge formwork as required.
 Bull mark or level pegs should be fixed on edges and center with required top level
 Approved concrete grade should be used.
 Concrete should be well compacted after placing using straight edge.
 Concrete by vision should be homogeneous and proper level.
 Curing of PCC shall be done minimum one day and avoid the shrinkage cracks.

D. CURING:

Continuous curing for a minimum period of 3 days is must for any concrete constructed

using Ordinary Portland cement.


METHOD STATEMENT FOR
PCC WORK

REV NO : 00 DOC No : Antenna-DC-01-PCC- DATE : 15/11/2023


MS-001

7. METHODOLOGY OF OUALITY INSPECTION:

Personnel:
 Ensure all personnel are wearing gumboots, helmets and rubber gloves
 Ensure all personnel are wearing safety belts during concreting at heights or on the
periphery of structures

Before concreting:
 All the shuttering gaps must be cleaned and sealed with cement grease paste so that there is
no leakage of slurry (If applicable).
 Ensure if all cover blocks are kept in place and are intact

During concreting:
 Ensure proper grade of concrete as recommended by the structural consultant is employed

o Evenness of the top surface of fresh concrete should be checked


o Appropriately sized concrete vibrator needle shall be used to ensure sufficient
compaction

After concreting:
Curing should be carried out as per the given guidelines
 Ensure that initial curing is done and proper curing is done regularly

8. RESPONSIBILITIES:
Construction Manager: He shall be responsible for overall management of construction activates.
Site Engineer: He shall be responsible for Executing in safe work method as per drawing and guide
the supervisors and workmen.

Site Supervisor: He shall be responsible managing all plant and machineries and labor and safety
of the workers.
METHOD STATEMENT FOR
PPC WORK

REV NO : 00 DOC No : Antenna-DC-01-PCC- DATE : 15/11/2023


MS-001

QA/QC site in charge: He shall be responsible for ensuring the quality of work as per the
specification and standards.

HSE Manager/Engineer: He shall be responsible for assisting to engineer/supervisor to ensure the


Safety of workers during the progress of work. Safety inductions of each staff and workers shall be

done and daily PPE check to be done and tool box talk shall be carried out before the start of work.

General safety awareness as well as particular safety precautions and guideline for activity to be

carried out in that particular day shall be discussed.

Stores officer: He shall be responsible for receiving and storing of all incoming materials. Also
responsible for maintaining the record of incoming and outgoing and up to date stock details of
materials.
METHOD STATEMENT
FORPPC
WORK

REV NO : 00 DOC No : Antenna-DC-01- DATE : 15/11/2023


PCC-MS-001

CHECK LIST FOR PLAIN CEMENT CONCRETE WORK :

CHECK LIST FOR ON SITE INSPECTION

ACTIVITY : PLAIN CEMENT CONCRETTE P.C.C


Name of project : Checklist No:
Vendor/Contractor : Drawing no :
Contract no : Date of inspection :
NOTE : Please [√] appropriate box or enter readings as per drawings
SL.NO. To be checked YES NO NA REMARKS
1 Are the latest "Good for Construction" drawings available? [] [] []
2 Have the required barricading and safety measures been taken? [] [] []
3 Are the required number of cement bags available on site? (or [] [] []
adequate quant1ty of RMC been ordered )
4 Are the required tools available at site to ensure correct work [] [] []
5 Have the vibrators been checked before start of the concrete? [] [] []
6 Is the platform and scaffolding material secure [] [] []
7 Is the necessary shuttering complete and in place? [] [] []

PRE POUR 8 Has the shuttering material been properly aligned using [] [] []
appropriate equipment?
CHECKS
9 Are spare hessain cloth or tarpaulin sheet available as protection [] [] []
from the elements?
10 Have the dimensions and orientation of the excavated pit been [] [] []
checked?
11 Has the pit been cleaned by removing all the loose materials? [] [] []
12 Has the excavated pit watered and rammed for better compacted [] [] []
strata?
13 Is the surface level of the pit even? [] [] []
14 |Is the necessary dewatering arrangements done incase af water [] [] []
logging at the pi1?
15 Does the shuttering box fit in position? [] [] []
16 Has the pit been button marked? [] [] []
17 Has the anti-termite treatment been done? [] [] []
18 Has the strata been checked and approved by the concerned [] [] []
authority?
CHECKS 19 Are all the labors wearing gum boots while concreting? [] [] []
DURING Is the right grade of concrete being used2
20 [] [] []
EXCUTION
21 |Has the level of PCC maintained? [] [] []
22 Has the leveling and finishing of PCC done? [] [] []
POST 23 Has it been ensured that hessain cloth is provided and curing done? [] [] []
POUR Has it been ensured that no loose earth has fallen on the P CC bed
24 [] [] []
CHECKS
METHOD STATEMENT
FORPPC
WORK

REV NO : 00 DOC No : Antenna-DC-01- DATE : 15/11/2023


PCC-MS-001

COMMENTS :

CHECKED BY AVS CHECKED BY AVS : APPROVED BY : CTRLS

ENGINEER :

Engineer :
Sign QA/QC :

SIGN (QA/QC) :

Project Manager :