Professional Documents
Culture Documents
DOCUMENT CONTROL
Prepared By
Reviewed By
Approved By
Record of Revisions
CONTENTS
1. OBJECTIVE Page 04
2. SCOPE Page 04
3. REFERENCE Page 04
6. PROCEDURE Page 05
C. TRANSPORTATION Page 05
D. CURING Page 05
A. PERSONNEL Page 07
8. RESPONSIBILITIES Page 07
1. 0BJECTIVE:
The objective of this method statement is to execute PCC works meeting the construction
requirements and technical specifications. Being strong in compression, concrete play a vital role
2. SCOPE:
The scope of PCC is to provide a uniform level, impermeable layer to water, a strong base to
3. REFERENCE :
IS 456-2000 (Reaff Feb 2016) Code of practice for plain and reinforced concrete
" IS 2571-1970 (Reaff Jan 2017) Code of practice for laying in-situ cement concrete
5. MATERIAL USED:
6. PROCEDURE:
D. CURING:
Continuous curing for a minimum period of 3 days is must for any concrete constructed
Personnel:
Ensure all personnel are wearing gumboots, helmets and rubber gloves
Ensure all personnel are wearing safety belts during concreting at heights or on the
periphery of structures
Before concreting:
All the shuttering gaps must be cleaned and sealed with cement grease paste so that there is
no leakage of slurry (If applicable).
Ensure if all cover blocks are kept in place and are intact
During concreting:
Ensure proper grade of concrete as recommended by the structural consultant is employed
After concreting:
Curing should be carried out as per the given guidelines
Ensure that initial curing is done and proper curing is done regularly
8. RESPONSIBILITIES:
Construction Manager: He shall be responsible for overall management of construction activates.
Site Engineer: He shall be responsible for Executing in safe work method as per drawing and guide
the supervisors and workmen.
Site Supervisor: He shall be responsible managing all plant and machineries and labor and safety
of the workers.
METHOD STATEMENT FOR
PPC WORK
QA/QC site in charge: He shall be responsible for ensuring the quality of work as per the
specification and standards.
done and daily PPE check to be done and tool box talk shall be carried out before the start of work.
General safety awareness as well as particular safety precautions and guideline for activity to be
Stores officer: He shall be responsible for receiving and storing of all incoming materials. Also
responsible for maintaining the record of incoming and outgoing and up to date stock details of
materials.
METHOD STATEMENT
FORPPC
WORK
PRE POUR 8 Has the shuttering material been properly aligned using [] [] []
appropriate equipment?
CHECKS
9 Are spare hessain cloth or tarpaulin sheet available as protection [] [] []
from the elements?
10 Have the dimensions and orientation of the excavated pit been [] [] []
checked?
11 Has the pit been cleaned by removing all the loose materials? [] [] []
12 Has the excavated pit watered and rammed for better compacted [] [] []
strata?
13 Is the surface level of the pit even? [] [] []
14 |Is the necessary dewatering arrangements done incase af water [] [] []
logging at the pi1?
15 Does the shuttering box fit in position? [] [] []
16 Has the pit been button marked? [] [] []
17 Has the anti-termite treatment been done? [] [] []
18 Has the strata been checked and approved by the concerned [] [] []
authority?
CHECKS 19 Are all the labors wearing gum boots while concreting? [] [] []
DURING Is the right grade of concrete being used2
20 [] [] []
EXCUTION
21 |Has the level of PCC maintained? [] [] []
22 Has the leveling and finishing of PCC done? [] [] []
POST 23 Has it been ensured that hessain cloth is provided and curing done? [] [] []
POUR Has it been ensured that no loose earth has fallen on the P CC bed
24 [] [] []
CHECKS
METHOD STATEMENT
FORPPC
WORK
COMMENTS :
ENGINEER :
Engineer :
Sign QA/QC :
SIGN (QA/QC) :
Project Manager :