DOC NO :
Project Name:
Location : Riyadh - KSA Rev : 00
LTOM PACKAGE #5 MANFOUHA
Date : Page 1 of 4
BY:
SUBJECT:
QA/QC ENGINEER
EXCAVATION, EARTHWORK AND FILLING APPROVED BY:
ACTION VERIFY
1. SCOPE
This procedure provides a standardised framework for the control of Project Manager Method Statement
excavation, earthwork and filling to ensure compliance with conditions of
contract and contract specifications.
2. PROCEDURE
B- Method Statement
i) Site plan showing the location of spoil heaps for temporary storage and
if appropriate permanent storage area.
3 Existing Utilities
Liaise with all public utility companies e.g. water, electricity, telephone Project Manager Drawing/
sewerage and surface water etc. to ensure that all the available information
on the location of utilities and underground services through and adjacent Project Engineer Markings
to the site of the excavation is obtained.
ii) Ensure that utilities and underground services are located on site using Project Engineer
markings, which are clearly visible. Ensure those plant operators and Survey
operatives involved with the activity are fully aware of the location of the Site Engr./
various utilities and underground services and their respective depths.
Surveyor
iii) Where deemed necessary, excavate trial holes to establish the precise
location and depth of services. Project Manager
iv) Plant operators must be aware of overhead cables. Use height control
indicators where necessary.
Prior to any surplus excavated material being removed from the site,
documentary evidence of “approval to tip” must be obtained beforehand
from the relevant government/municipal departments and the owner of the
land where the material is to be tipped.
6- Adjoining Structures and Property
7- Excavation Work