Professional Documents
Culture Documents
DOC NO :
Project Name:
Location : Riyadh - KSA Rev : 00
LTOM PACKAGE #5 MANFOUHA
Date : Page 1 to 6
1. Purpose
2. Scope of Work
3. References
4. Man Power
5. Tools and Equipment
6. Procedures
7. Quality Control
8. Safety
9. Attachment
1- Purpose
The purpose of this procedure is to provide the methodology and testing of bolt tightening (bolt
torquing) of structural steel work in all supply mechanical equipment to the commercial
buildings, plants and refinery project and its equipment structures
2- Scope of Work
The scope of work includes bolt tightening requirements of all mechanical equipment structural
joints and sections showing the bolt size to be used, field inspection, and implementing safety
precautions during work execution to prevent accidents.
3- References
Work shall be performed according to project applicable standards and project specifications:
High Strength Bolt Tightening Inspection and Testing (ASTM A325/A490 Bolts)
Pre-Installation Procedure Verification Testing Turn-of-Nut Method (ASTM A325/ASTM A490 bolts)
Pre-Installation Procedure Verification Testing of Calibration Wrench (ASTM A325/ASTM A490 bolts)
Structural alignment inspection during erection
Correcting structural alignment errors
Pipe Racks, Steel Supports, and Miscellaneous Steel Structures
4- Manpower
Structural Steel Foreman/Mechanical Foreman
Structural/Mechanical Skilled Workers
Manlift Operator
Page 1of 6
Flagman
QC Inspector
6.1.2 All primary structural frames and some secondary framing require high strength A-325 or A490
Bolts.
6.1.4 Steel members to be jointed must be free from oil, grease or any loose adherent materials.
6.1.5 Any circumstances discovered by the DEC that affect progression, performance, or completion of
work activities such as discrepancies between drawings and delivered steel members to be jointed,
incorrect fabricated steel members, incomplete or unacceptable material shall be reported in writing.
6.1.6 Before bolt tightening DEC shall check the connection points to confirm their location, orientation,
elevation and condition.
6.1.7 Contractor shall place a scaffolding access, ladder, wood boards or floor plates for the people who
will conduct the activity to prevent injury while commencing the work.
6.2.2 The structure shall be plumbed, levelled and braced before final bolting connections are made.
Page 2of 6
6.3.1 Where structural joints are made using high-strength bolt assemblies, the materials, method of
installations, tension control, types of wrenches to be used and inspection methods shall conform to
AISC Specification for Structural Joints using ASTM A325 or A490 Bolts.
6.3.2 When used, direct tension indicator washer shall be installed according to the manufacturer’s
given specifications.
6.3.3 All bolts shall be as noted on the shop drawing, erection drawings or other contract documents.
6.4.2 “SNUG-TIGHT” as defined is the effort of a person using SPUD WRENCH or tightness attained by a
few impacts of an IMPACT WRENCH.
In this case, full efforts of a man using an ordinary spud wrench would bring the bolt to a snug tight
position. No wrench extension or long wrenches should be used to avoid tensioning; the normal spud
wrench is usually 12 inches (300mm) long.
Few impacts of an impact wrench should be sufficient to bring the bolts into snug tight position. If the
impact wrench is strong enough, this operation should not take more than 30 seconds of application to
bolt which already tightened to full contact with the steel connection plates.
6.4.3 Once the SNUG tight position is achieved a straight line shall be marked by metal marker or pentel
pen on the bolt head continue to nut location. This will indicate the initial position of nut prior to its
final tightened position.
6.4.4 In critical-slip connection where the joint is subject to vibratory or fatigue loading, chance of bolt
to be loosened is very high. In this case, after bolts has fully tensioned an additional jamb-nut maybe
provided. Alternately, the threads can be spiked or marred or the nut can be tack-weld to the base metal
to prevent it from turning
6.5 Operations
6.6 All bolts in the joints must be further tightened using either the turn-off-nut or calibrated wrench
method after the initial tightening operation
6.6.1 Turn-Of-Nut-Method
Once the bolt is snugly tight, the amount of rotation required should be applied to further tighten it.
Refer to the table below for reference.
KIPS KN KIPS KN
1/2 12 53 15 67
5/8 19 85 24 107
1 51 227 64 285
Compressed air is the most common source of power. A sufficient amount of pressure must be applied
to the tool, with a minimum of 100 psi for bolts with a diameter of 7/8″ or less. Pressure must be
increased for larger bolts. Hose lines should be large enough to accommodate the number and size of
wrenches that will be utilized.
Under Bolt Head Black Finish Bolts 0.025 in. 0.015 in.
Under Nut with Hardened Flat Washer Black Finish 0.015 in. 0.010 in.
With the gaps shown above, required minimum bolt tensions will be
induced as given in Table 2
7. Quality Control
7.1 Check the physical appearance and the material specifications to be used for bolting prior to the
work execution.
7.2 Ensure to follow IFC drawings for bolt specification requirements including sizes and
manufacturer’s recommendation. Observe as always SATIP activity, SAIC and SATR standard
requirements for compliance.
7.3 Check, verify and continuously monitor bolting works activities at site and lay down yard where
assembly and bolt tightening is on progress.
8. Safety
8.1 Ensure that all personnel involved in the work are wearing standard personnel protective
equipment (PPE).
8.1.1 Maintain warning devices such as warning tapes, signboards and barriers around the work area to
prevent injury to all personnel affected by the operations.
8.1.2 Tools (Hand Tools and Machined Operated tools) and Safety Harnesses shall be monitored and
coded as per safety monthly monitoring guidelines for acceptance and compliance of these equipment
to daily site activities.
Page 5of 6
9. Attachment
9.1 JOB SAFETY ANALYSIS
9.2 Inspection Request Form
Page 6of 6