You are on page 1of 7

Project Title: Marriot Grand Ballroom

Contract Package No. Sanitary/Plumbing Works

Document Title:

Method Statement of Pipe Sleeves for Sanitary/Plumbing Works

Revision History
CIVIL /
MARK DATE DESCRIPTION MEPF
ARCHITECTURAL
A1 9/04/12 1st Submission
A2 10/04/12 2nd Submission

GENERAL CONTRACTOR
Prepared By: NGCB CQC
QA/QC Head
Checked By: NGCB
DATE
PROJECT MANAGEMENT
Mechanical Engineer
Electrical Engineer
Reviewed by: EELHI
Civil Engineer
Architect

Project Manager
Approved By: EELHI Sr. Project Manager

CONTRACTOR’S DOCUMENT No.: MGB-MS-014-PW-002 REVISION A2

MGB-MS-014-PW-002 Page 1
TABLE OF CONTENT

1. PURPOSE
2. SCOPE AND APPLICATON OF WORKS
3. REFERENCES
4. DEFINITIONS AND ABBREVIATIONS
5. SPECIFICATION CLAUSE
6. RESOURCES AND MOBILIZATION
7. CONSTRUCTION EQUIPMENT
8. PERSONNEL
9. MATERIALS
10. CONSTRUCTION PROCEDURE AND METHODOLOGY
11. RESPONSIBILITY
12. DESIGN DRAWINGS
13. QUALITY ASSURANCE
14. HEALTH AND SAFETY
15. ORGANIZATIONAL CHART
16. INSPECTION
17. ATTACHEMENTS

1. Purpose

This document serve as guideline for proper installation of Pipe Sleeves, materials to be use, and
their respective testing procedure prior to ensure that the work conducted on the project are in
accordance with the (1)Approved For Construction Drawing and (2)Technical Specification issued by
the EELHI or (3)Approved shop drawing prepared by the corresponding contractor.

This Method Statement is simply composed of, Inspection of Materials, Preparation before
Installation, Procedure of Installation of under Pipe Sleeves and Testing/Inspection.

It is necessary to understand the step by step procedure to avoid errors or unexpected outcome of the
work and compromised the quality of workmanship and safety procedure implemented by the
authority or safety personnel.

2. Scope and Application of Work

This work shall consist of furnishing and installing a pipe sleeves as shown on the approved plans and
drawings and as specified on the Technical Specification issued by the EELHI, and directed
supervision of the Nominated Sub Contractor Engineer.

Work application is specifies as follows:


1. Preparation of Work
2. Delivery of Materials
3. Inspection of Delivered material
4. Fabrication of Pipe Sleeves
5. Setting-out/Layout/Markings
6. Installation of Pipe Sleeves
7. Provide trimmer bar

MGB-MS-014-PW-002 Page 2
3. References

This Method Statement has been referred to the following documents:

1. Approved For Construction Drawing issued by EELHI


2. Plumbing Works Technical Specification issued by EELHI
3. Submitted Shop Drawings Prepared by the Contractor and approved by the designer
4. Submitted approved materials
5. Approved work schedule associated with the master schedule prepared by NGCB
6. Approved safety plan and associated safety procedures

4. Definition and Abbreviations

● ELEV - Elevation

● MM - Millimeter

● ITP - Drain Pipe

● MS - Method Statement

● CQC - Contractor’s Quality Control

● EELHI - Empire East Land Holdings, Inc.

● NGCBDC - New Golden City Builders & Development Corporation

● NSC - Nominated Subcontractor

● FPW - Fire Protection Works

5. Specification Clause

Requirements for Pipe Sleeves are specified with Plumbing Technical Specification and/or For
Construction Drawing stated as follows:

1. Technical Specification for Plumbing Works : Section 15400 PW200 ITEMS 3.3
2. For Construction Drawing : Sheet P2-01, P6-01/Detail No. 11
3. Submittal Review Form No. MGB-SRF-030a-CP02-028a-P-004a
4. Materials
● Pipe sleeves in walls and partition shall be of cast iron, wrought iron or steel pipe
● Pipe sleeves in concrete beam or concrete slabs shall be wrought iron or steel pipe
● Pipe sleeves on footings shall be cast iron or steel pipe
● Pipe sleeves over 100mm  shall be below slab/beam soffit

All materials to be used shall be approved by the designer and comply as required on the
above stated.

6. Resources and Mobilization

According to the work program, the presence of availability of area, appropriate staff, manpower,
equipment’s and materials is required to mobilize and install the pipe sleeves in accordance with the
approved For Construction Drawing issued by EELHI and approved by the Plumbing Works
Consultant.

MGB-MS-014-PW-002 Page 3
The actual mobilization of staff, manpower and the materials delivery schedule will be dependent on
site accessibility. Actual site access will need to be notified by the NGCB at least 1 week before the
actual execution of the works

NGCB will be responsible for the provision of staff and workers temporary stair access on site, lay-out
references including appropriate type of crane for the transportation of material and equipment if
necessary as well as temporary construction water, power supply and lighting system.

7. Construction Equipment

No major equipment will be required by Ultimate Plumbing Contractor for the activities involve in the
supply and installation of the pipe sleeves. The common construction equipment requirements may
use for the completion of the work is listed below.

● Personal Protective Equipment for all Staff and Workers

● Measuring tape and setting out markers

● Electric hand grinder/cutter

● Level bar and leveling instrument

● Water level marker

● Hacksaw

● Any other tools or equipment that may useful for the installation

Note: Electrical Power tool must be suitable with a 220VAC power supply.

8. Personnel

Installation of the pipe sleeves will be organized from central location by Project Construction Team,
both NGCB. It is envisaged that the installation of pipe sleeves will be conducted by the following
personnel:

● Site Engineer

● Survey Team

● Quality Control Engineer

● Foreman

● Skilled Workers

● Helper

The above mentioned personnel shall be fully competent and trained to carry out all works associated
with the installation of pipe sleeves. They shall attend the required contractor’s safety induction and
will abide by the Health and Safety Plan, policy and procedures as well as environmental plan.

MGB-MS-014-PW-002 Page 4
9. Materials

All materials delivered to the site will be inspected by EELHI Engineers In-charge, to check that it is in
accordance with the site requirement and conform to the approved design and material qualification.

The Pipe Sleeves will be fabricated at the site and in accordance with the approved For Construction
Drawings and/or approved shop drawings. The Pipe sleeves shall be inspected before the installation
or laid out in the site.

Manual hauling or carrying the pipe sleeves at site shall be allowed if the tower crane provided by the
NGCB is not available.

The inward inspection of materials will be carried out in accordance with the relevant a QA/QC
procedures and or Quality Plan approved by EELHI.

Noted: No materials shall be permitted to enter and/or installed the jobsite without inspection
and approval from CQC & EELHI Engineers upon arrival at jobsite.

10. Construction Procedure and Methodology

The construction procedures and method described herein are based upon the scope and application
of the method statement summarized in section 2 of this documents and the work method are
organized accordingly.

a. Preparation of the Works

Before the commencement of installation, the following are required to be carried out:

 Check the design of the piping system if approved, and that the drawings for the pipe
installation are issued For Construction Drawing, and in accordance with document control
procedure.
 Check that the site access to the work area is available, that the work area is clean and
safe and that the temporary services provision are available.
 Check the pipe sleeves ancillary materials have been ordered and inspected at NGCB
Warehouse and available/ready to install at site.

b. Delivery & Inspection of Pipes, Fittings and Ancillary Materials at Site

 All delivered material shall be inspected on the arrival in the site. The inspection shall be
advised in advance (1 day before the actual inspection) as required by EELHI.
 The delivered materials shall be in accordance with the appropriate Quality Plans and
Procedures.
 The delivered materials shall be in accordance with the approved design technical
specification, approved for construction drawings and approved material submittal.
 Material approvals in form of approved SRF and all applicable documents and certification
shall be available during incoming material inspection.
 The material shall be free from any defects or damage.
 Any materials delivered in the site that are not complying with the approved material
submittals and plumbing technical specification or rejected by EELHI Engineer shall either
be return to the supplier or stored in the site at a suitable quarantine store and NCR shall
be issued to contractor.

MGB-MS-014-PW-002 Page 5
c. Installation Procedure : Setting out Works

 Setting out of the installation shall be conducted to determine the location and elevation of
pipe sleeves.
 The Nominated Sub-Contractor (Ultimate Plumbing Corporation) Site Engineer supervises
the lay-out for pipe sleeves location and elevation with refers to the For Construction
Drawing and/or Approved Shop Drawing and lay-out references provided by the General
Contractor (NGCB).

C.1 Installation Procedures

 Check location of pipe sleeves as per approved Shop drawings.


 Specify the locations and elevations of pipe sleeves.
 Minimum clearance between the pipe and sleeves shall not be less than 25mm or 1 inch
for pipes, 25mm to 89mm or 3-1/2 inches and 50mm or 2 inches clearance between pipes
100mm or 4 inches and larger. The clearance between the pipes and sleeves shall be
filled with non-combustible materials such as asbestos rope and furnished with semi-
hardening mastic flush.
 Floor sleeves shall extend at least 76mm or 3 inches above the top of the wearing surface.
 Drains, Fire department connections, test manifolds and other Auxiliary piping connected
to risers shall not be connected into walls or floors.
 Upon installation of pipe sleeves, diagonal support shall install based on the approved
shop drawings
 Pipe sleeves checking shall be conducted by NGCB CQC Engineers and inspection
request are then requested from EELHI by NGCB CQC for final installation inspection.

11. Testing Procedures

No testing required for pipe sleeves installation.

12. Responsibility

The QA/QC Head (NGCB) is the overall responsible body for the implementation and execution of the
works. At the same time, maintaining construction’s quality assurance and quality control program and
construction standards.

The General Contractor (NGCB) will be responsible for all construction activities in the site and will
directly supervise through Construction Supervisor, Foreman and Skilled workers at site. The QA/QC
Inspector will be the responsible for arranging and controlling the inspection and testing activities.

Notwithstanding the above, it is the responsibility of each individual employed in the project to take
due care to ensure their own personal safety and that of their work colleagues.

13. Design and Drawings

For approval pipe works installation shop drawings and pipe work fabrication shop drawing will be
prepared by NGCB and UPC based on approved For Construction Drawing issued by EELHI before
commencement of the works.

14. Quality Assurance

The execution of work will strictly follow the Project Quality Plan.

MGB-MS-014-PW-002 Page 6
15. Health and Safety plan

The Execution of work will follow the Project Safety Rules and Manual.

16. Organizational Chart

As per Organizational Chart of the Project

17. Inspection Test Plan

As per attached ITP

18. Attachments

● Checklist for inspection of incoming materials for pipe sleeves.

● Checklist for installation inspection of pipe sleeves.

MGB-MS-014-PW-002 Page 7

You might also like