You are on page 1of 9

Main Contractor Effective Date : 24-10-2012

Owner: Client: Consultant: Document No. : N7680


HYUNDAI Revision No. : 0
Page No. : Page 1 of 10
Approved By : NM
Client : TRANSCO

Project : NEW 400/220kV GRID STATION AT RUWAIS


Title : METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS
Contract No. N-7680 Rev. 0

METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS


                         

METHOD STATEMENT FOR


INSTALLATION OF EXTRACT/PRESSURIZATION FANS

AMENDMENTS

APPROVED BY
REV NO. PAGE NUMBER DESCRIPTION OF AMENDMENT EFFECTIVE DATE
(SIGNATURE)

DESCRIPTION TITLE SIGNATURE DATE

Prepared by JCJ 04-11-2012


Reviewed By CAJ 04-11-2012
Approved By NM 04-11-2012

HYUNDAI
Main Contractor Effective Date : 24-10-2012
Owner: Client: Consultant: Document No. : N7680
HYUNDAI Revision No. : 0
Page No. : Page 2 of 10
Approved By : NM
Client : TRANSCO

Project : NEW 400/220kV GRID STATION AT RUWAIS


Title : METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS
Contract No. N-7680 Rev. 0

METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS


CONTENTS
 

1.0 Activity
2.0 Introduction
3.0 Significant Hazards identified
4.0 Responsibilities
5.0 Sequence of Activity with Responsibilities
6.0 Requirements
6.1 Plan/Records and job instruction
6.2 Training
6.3 Equipment / Tool
6.4 Materials
Material Handling & Storage
6.5 Installation Of Extract fans
Preconditions
Installation Package Units
Checks
7.0 Emergency Procedures

8.0 PPE

9.0 Reference

10.0 Attachments

HYUNDAI
Main Contractor Effective Date : 24-10-2012
Owner: Client: Consultant: Document No. : N7680
HYUNDAI Revision No. : 0
Page No. : Page 3 of 10
Approved By : NM
Client : TRANSCO

Project : NEW 400/220kV GRID STATION AT RUWAIS


Title : METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS
Contract No. N-7680 Rev. 0

METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS


1.0 Activity:
Installation of
Extract/pressurization Fans
The purpose of this method statement is
to outline the sequences and methods of
works intended to be used for
Installation of Extract/Pressurization
Fans

2.0 Introduction:

This procedure is application to AC system installation for the project titled, “ NEW
400/220kV GRID STATION AT RUWAIS”, UAE, contract N-7680

3.0 Significant Hazards identified

 Attached Annexure-A

4.0 Responsibilities

Main contractor : Hyundai Engineering and Construction


Sub Contractor : Al Inayah EMW LLC
Supervisor:
Supervisor must supervise the site both from work and HSE perspectives. Supervisor must
not proceed if he is in doubt about safe work progress of work. Tool box talk shall be
conducted before start of the activity in which he communicates to his work party the
hazards, precautions and adopted control measure. He must also check their PPE and
communicate the emergency procedures. Supervisor must follow the approved method
statement.

HYUNDAI
Main Contractor Effective Date : 24-10-2012
Owner: Client: Consultant: Document No. : N7680
HYUNDAI Revision No. : 0
Page No. : Page 4 of 10
Approved By : NM
Client : TRANSCO

Project : NEW 400/220kV GRID STATION AT RUWAIS


Title : METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS
Contract No. N-7680 Rev. 0

METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS


SAFETY OFFICER:
Safety officer must ensure that the HSE plan is implemented. He should inspect the site and
inform the HSE Manager/Project Manager any deviations from the standard practices. He
may conduct a safety briefing in coordination with supervisor over a specific HSE issue.

HSE MANAGER :
HSE-Q manager shall conduct periodic audit of safety and review the procedure at
site
periodically.

PROJECT MANAGER:
Project manager must ensure that appropriate resources are provided for safe delivery of the
work.

5.0 Sequence of Activity with Responsibilities

5..1 RFI shall be raised to Consultant one day prior to start of Extract Fan
installation by Supervisor.

5..2 Supervisor/Foreman and safety officer of Sub contractor and Toshiba


shall be present at site all time during progress of work.

5..3 Site engineer to ensure that the progressing of works is carried out
according to the planned program and as per the approved method
statement.

5..4 To co-operate and ensure implementation of any comments raised by


Consultant.

5..5 To ensure that all equipment and materials required to execute the
works are available according to the planned construction program.

5..6 To co-ordinate with the Site Manager, QC Inspector, Safety Officer and
Foreman for a safe and proper execution of the works.

5..7 To control and maintain all safety measures in coordination with the
Safety Officer.

HYUNDAI
Main Contractor Effective Date : 24-10-2012
Owner: Client: Consultant: Document No. : N7680
HYUNDAI Revision No. : 0
Page No. : Page 5 of 10
Approved By : NM
Client : TRANSCO

Project : NEW 400/220kV GRID STATION AT RUWAIS


Title : METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS
Contract No. N-7680 Rev. 0

METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS

6.0 Requirements

6.1 Plans/records & job instruction (documents)

Before starting work you must ensure that you have

1. Location of work area


2. Job instruction
3. First AID box
4. Method statement

6.2 Training

Tool Box Talk to be conducted prior to work

6.3 Equipment / Tool


The equipment and tools that will be engaged for the installation of
Extract Fans will be as follows:

 Mobile Crane/Fork lift

 Drilling Machine

 Hammer

 Tool Box for Mechanical

6.4 Materials

Material Handling & Storage

Handling
Loading and unloading of Extract Fans will be carried by mobile
crane/Fork Lift.

HYUNDAI
Main Contractor Effective Date : 24-10-2012
Owner: Client: Consultant: Document No. : N7680
HYUNDAI Revision No. : 0
Page No. : Page 6 of 10
Approved By : NM
Client : TRANSCO

Project : NEW 400/220kV GRID STATION AT RUWAIS


Title : METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS
Contract No. N-7680 Rev. 0

METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS

Storage
All Extract Fans will be stored in covered storage area the contract
specification and manufacturer’s recommendation shall be the master
Reference for the material handling, storage and transport.

6.5 Preconditions

 Fans shall be installed, as per the specification, manufacturer recommendations


and site conditions.
 Related drawings on the site with approved status.
 Material, accessories and tools shall be on the site.
 Installation provisions, like power supply, auxiliary lighting, etc. shall be in
function.
 All HSE conditions are achieved.
 RFI shall be raised one day prior to start any activity at Grid station by Engineer.

Installation of Extract/Pressurization Fans)

1 Shift the fans to the place of installation in safe manner using hand trolley, fork
lift/crane as applicable. Sufficient manpower will be engaged as required for safe
shifting and installation.

2 Ensure that the correct fan is shifted to the place of installation.

3 Ensure air inlet and outlet connections orientation are as per approved drawings.

4 Fix the flexible duct connector to fan inlet and outlet as per approved
drawings/manufacturer’s instructions.

HYUNDAI
Main Contractor Effective Date : 24-10-2012
Owner: Client: Consultant: Document No. : N7680
HYUNDAI Revision No. : 0
Page No. : Page 7 of 10
Approved By : NM
Client : TRANSCO

Project : NEW 400/220kV GRID STATION AT RUWAIS


Title : METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS
Contract No. N-7680 Rev. 0

METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS

5 The fan is placed correctly on foundation. (if applicable) at the right location.

6 The fans will be properly leveled and parallel to room walls/other installations.

7 Fans shall be inspected again for any damage during hoisting/shifting and
installation.

8 Clean the interior of the fans.

9 Follow the manufacturer’s instructions while installing the fans.

Checks

The following field-checks will be carried out:

Visual checks

7 Emergency Procedures
 Evacuate The Area.
 Inform to Safety Office.
 Inform Local Authority
 Assemble in Assembly Area.
 Follow Safety Officer’s Instructions.

8 PPE

HYUNDAI
Main Contractor Effective Date : 24-10-2012
Owner: Client: Consultant: Document No. : N7680
HYUNDAI Revision No. : 0
Page No. : Page 8 of 10
Approved By : NM
Client : TRANSCO

Project : NEW 400/220kV GRID STATION AT RUWAIS


Title : METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS
Contract No. N-7680 Rev. 0

METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS

9 Reference

 Drawing no. N7680 RH 5380 S 7611, N7680 RH 5380 S 7616


 N7680 RH 5380 S 7620

10 Attachments

A. Risk Assessment

HYUNDAI
Main Contractor Effective Date : 24-10-2012
Owner: Client: Consultant: Document No. : N7680
HYUNDAI Revision No. : 0
Page No. : Page 9 of 10
Approved By : NM
Client : TRANSCO

Project : NEW 400/220kV GRID STATION AT RUWAIS


Title : METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS
Contract No. N-7680 Rev. 0

METHOD STATEMENT FOR INSTALLATION OF EXTRACT/PRESSURIZATION FANS

Attachments

A. Risk Assessment.

HYUNDAI

You might also like