Professional Documents
Culture Documents
METHOD STATEMENT
MS-001
for
PVC Conduiting/Accessories Installation
works
__________________________________________________________________________
Revision 00 Page 1 of 6
JOB:- INTERIOR WORKS OF THE FALCON LOUNGE – BIA
TABLE OF CONTENTS
1. INTRODUCTION..........................................................................................................3
2. SCOPE OF WORK…………………………………………………………………………………………………...3
3. LOCATION………………………………………………………………………………………………………………3
4. REFERENCE…………………………………………………………………………………………………………….3
5 RESOURCES…………………………………………………………………………………………………………….3
5.1. Manpower……………………….………………………………………………………………………………3-4
6. SEQUENCE/STAGES OF WORK…………………………………………………………………………………….. 4
__________________________________________________________________________
Revision 00 Page 2 of 6
JOB:- INTERIOR WORKS OF THE FALCON LOUNGE – BIA
1. INTRODUCTION
This Work Method Statement for PVC Conduiting works should be done under the
control of the specification and according to approved shop drawing of the work for
Interior works of the Falcon Lounge- BIA.
The purpose of this statement is to define the procedure and method as well as all
Parameters to perform proper way for fixing the conduits as per the scope of works and
approved shop drawings.
3. LOCATION
4. REFERENCE DOCUMENTS
5. RESOURCES
5.1 Manpower
Electrical Engineer
__________________________________________________________________________
Revision 00 Page 3 of 6
JOB:- INTERIOR WORKS OF THE FALCON LOUNGE – BIA
Electrical Supervisor
Electricians
Helper
Bending spring.
Steel wire cutter.
Hacksaw blade.
Ladder.
Measuring tapes and marker
Masking tape.
__________________________________________________________________________
Revision 00 Page 4 of 6
JOB:- INTERIOR WORKS OF THE FALCON LOUNGE – BIA
1. Ensure that the civil people have completed the Block wall/Column works and
clearance is given to proceed with the Electrical works.
2. Check the required Reference markings are available for FFL (Finish Floor Level).
3. Ensure that the FFL (Finish Floor Level) is approved by the civil consultant before
proceeding the electrical works on wall.
4. Mark the Location of Switch / Socket /PVC circular box and 20 mm PVC conduit shall
be routed on proper height based on the approved shop drawing in reference to
the marked and approved FFL by others.
5. Ensure the PVC box size and cut the wall /Column to suit the fixing in marked place
of the block wall/column with sufficient depth.
6. Start cutting the marked place for fixing the box and conduit run with the help of
grinder and chip with hammer after cutting.
7. Fix the PVC box of appropriate size (3 x3 / 3 x6 / Junction Boxes) and level with the
help of spirit level. The bottom/ center portion of the box shall match the
consultant approved marked level for switch / socket.
8. Apply cement filler to fix the box properly and leave for setting and insert the
required lengths of conduits on their paths.
9. After setting of Box, connect the dropped conduits for switch / socket to the box
with appropriate PVC adaptors.
10. PVC couplers shall be provided at all joint ends and shall be coupled and tightened
by means of PVC Glue.
11. Make sure that the conduits are not visible from outside their route which could
lead improper plastering.
12. Ensure to raise the inspection request to consultant before the plastering works in
order to obtain the approval.
6.3 Installation of PVC Conduits/Accessories in Slab.
__________________________________________________________________________
Revision 00 Page 5 of 6
JOB:- INTERIOR WORKS OF THE FALCON LOUNGE – BIA
10. Raise the inspection for slab conduiting works and once the inspection is
approved then MEP clearance shall be issued to the civil contractor to proceed
with the concrete pouring.
HSE Officer is to ensure that all the work requirements are fulfilled .e.g. if required a
job hazard analysis is conducted prior to the start of the activities that
environmental requirements are implemented and all personnel wear the required
PPE.
All operatives will be informed (via a site induction / toolbox talk) of and
expected to comply with the contractor’s site rules.
All materials used for electrical ring beam piping works shall be stored in approved
and designated storage areas at site.
ATTACHMENT:-
Risk Assessment.
__________________________________________________________________________
Revision 00 Page 6 of 6