Professional Documents
Culture Documents
A VR O C OM P A NY Page 1 of 10
AVRO 2020
TABLE OF CONTENTS
1 General information 3
1.3 Definitions 3
1.4 Abbreviations 3
3. INSTALLATION PLAN 5
4. TECHNICAL INFORMATION 7
5. SAFETY 9
6. QUALITY CONTROL 10
AV R O C O M P AN Y Page 2 of 10
AVRO 2020
1 GENERAL INFORMATION
The Canadian army in EIA has a request for supply, install, and commission Electrical Distribution
The purpose of this document is to explain the Method Statement of installing the mentioned
electrical equipment such as SDPs, Power Cables, and Buried Conduits with Manholes.
1.3 Definitions
In the document the following definitions were used. table below explained their meaning.
Definition Explanation
1.4 Abbreviations
In the document the following abbreviations were used. Their meaning is explained in the
table below.
Abbreviation Explanation
AC Alternating current
HV High Voltage
Page 3 of 10
Abbreviation Explanation
MV Medium Voltage
LV Low Voltage
CB Circuit-Breaker
managing the risks of installing the equipment. The technicians and workers should have
adequate experience and trained well in order to perform the work safely.
AVRO Company HSE manager will coordinate with the site manager to reduce the risk and
hazards that takes place on the site. Proper planning and procedure are essential points to
ensure that HSE is at the priority of all installation activities taken place during the project.
Page 4 of 10
It is compulsory that all installation activities should be explained during the toolbox talk
(TBT) meeting.
The safety inductions, training, safety audits, incentive programs and other safety items
should be done to all site personnel. Moreover, the following points have to be considered
Permit to work shall be obtained for the type of work and location.
Lifting equipment and tools shall be of suitable capacity, certified for the load and in
good working condition.
A tool box talk (TBT) shall be carried out daily prior to commence activity as per this
Method Statement and job safety analysis.
3. INSTALLATION PLAN
- The SDPs will be assembled locally with Circuit Breakers brand Schneider or ABB.
- After receiving the SDPs on site and finishing form civil work such as Manholes and
Buried Conduits, put the SDPs on their locations by using proper material until reached its
suitable place.
- Fix the SDPs on the concrete base by suing the proper material such as bolts and nuts.
- All installation process for all Equipment will be Completed per approved SLD, approved
- Prepare required safety documents for the activity before commence with it.
- Before commencing with Equipment installing activities unpacking & visual checking of
Page 5 of 10
3.2 POWER CABLES
- Check required documents & Drawings before commencing. AVRO Company site
engineer should take End-User supervisory comments and recommendations in mind and
- Make sure that all required types of cable are available at site.
- Check the Cable drums visually & primarily insulation tests by a proper test equipment
before commencing with cable pulling under relative engineer supervision and get his
approval.
- Make sure that all devices and tools which will be used for cable pulling activities are in
good condition and had been inspected such as (Cable stand, cable roller, trolley, Cable
- Specified sufficient team to commence with cable pulling and explaining work plan with
them about SAFETY requirement and prepare required safety document before
- Review over all the design and Make sure that cable routes have no any sharp edges or
improper condition.
Page 6 of 10
4. TECHNICAL INFORMATION
4.1 Technical Drawings
Figure no.1 SLD for Main Distribution Panels with Cable length of SDPs
Page 7 of 10
Figure no.3 Single Line Diagram for SDP5-100A.
Page 8 of 10
4.2 Cables Schedule Table
The required size of cable according to the SOW is 5X95mm2 because this
type of cable is unavailable on the local market the cable size
4x95mm2+1x95mm2 will be used instead of 5X95mm2.
LIST OF CABLES
Note: - Because the cable length is known for outgoing CBs, the price for
meter length will be provided in commercial offer. So outgoing cables will not
be considered in the above table.
5. SAFETY
The main activities of safety will be carried out in compliance with Health, Safety, Security
Page 9 of 10
Contractor has to comply all the laws application of safety, permits to work systems, safe
operation standards of the OWNER, and safety precautions related to the contract
performance so that to protect the work, the personnel, and project team. Simultaneously,
subcontractor (if applicable) has to full fill all the safety laws that are ordered from the
Owner.
6. QUALITY CONTROL
Contractor has to ensure that the employed staff has sufficient experience in order so that
to enhance the quality of the work. The subcontractor is responsible of the quality of
material that is used at the roof such as form work, scaffold, and other materials.
Moreover, all the inspection form shall be filled properly and submit to the consultant
engineer.
Page 10 of 10