AVRO 2020
TABLE OF CONTENTS
1. General information 3
Project Description 3
Purpose of the Document 3
Definitions 3
Abbreviations 3
Referenced Documents 4
2. MANGEMENT & RESPONSIBILITY 4
Management and Responsibility 4
HSE Requirement 5
3. General Working Approach 6
General Discretion 6
Avro Resources 6
Working Approach 7
4. TECHNICAL INFORMATION 12
Technical Drawings 12
Bill of Quantities 14
5. SAFETY 16
6. QUALITY CONTROL 16
AVRO 2020
1. General information
Project Description
The Canadian army in EIA has a request for supply, install, and commission Electrical Distribution
the scope of works to installing the mentioned electrical equipment such as SDPs, Power Cables,
Definitions
In the document the following definitions were used. table below explained their meaning.
Definition Explanation
Abbreviations
In the document the following abbreviations were used. Their meaning is explained in the
table below.
Abbreviation Explanation
AC Alternating current
HV High Voltage
MV Medium Voltage
Page 3 of 17
Abbreviation Explanation
LV Low Voltage
CB Circuit-Breaker
Referenced Documents
managing the risks of installing the equipment. The technicians and workers should have
adequate experience and trained well in order to perform the work safely.
AVRO Company HSE manager will coordinate with the site manager to reduce the risk and
hazards that takes place on the site. Proper planning and procedure are essential points to
Page 4 of 17
HSE Requirement
AVRO Company HSE Manager with the assistant of SITE HSE Manager will commit to
ensure that HSE is at the priority of all installation activities taken place during the project.
It is compulsory that all installation activities should be explained during the toolbox talk
(TBT) meeting.
The safety inductions, training, safety audits, incentive programs and other safety items
should be done to all site personnel. Moreover, the following points have to be considered
Permit to work shall be obtained for the type of work and location.
Lifting equipment and tools shall be of suitable capacity, certified for the load and in
good working condition.
A tool box talk (TBT) shall be carried out daily prior to commence activity as per
this Method Statement and job safety analysis.
Page 5 of 17
3. General Working Approach
General Discretion
Avro has divided the work in to a workable breakdown structure in order to estimate and
distribute it’s resources based on that breakdown. However, the work is consisted of the
following main items,
2. Civil Works
2.1 - Site Survey and Occupation
2.2 - From Gen Pad to the Existing Pull Pit 01 (Near To SDP01)
2.3 - From Existing Pull Pit 01 (Near to SDP 01) to Existing Pull Pit 02 (Near to SDP
02&03)
2.4 - From Existing Pull Pit 02 (Near to SDP 02&03) to New Pull Pit 03 (Near to SDP
06)
2.5 - From Existing Pull Pit 02 (Near to SDP 02&03) to New Pull Pit 04 (Near to SDP
04)
2.6 - From New Pull Pit 04 (Near to SDP 04) to Pull New Pit 05 (Near to SDP 05)
2.7 - From New Pull Pit 03 (Near to SDP 06) to SDP 07&08
2.8 - Final Cleaning
Avro Resources
Working with the Civil Works, Avro will be using the following resources in order to
Machinery number
Concrete Cutting Machine 1 to 2
Jack Hammer 2
Backhoe 1
Page 6 of 17
Loading Truck 2 to 4
Excavator 1 to 2
Hand Compactor 2
Concrete Pump 1
Concrete Mixer 1
Loader 1
Flat Crane 1
As Initially Planned, Avro will be utilizing the above mentioned resources, and will be
monitoring the production, in case any activity has been delayed then Avro’s Project
Manager will start to increase the number of the resources needed for the activity.
Working Approach
Avro has developed a working schedule which is enclosed herein, as reference to indicate
Page 7 of 17
Page 8 of 17
Page 9 of 17
As a general narrative related to the working schedule of the project,
- The main constrains in this projects are, the supplying of SDP Panels which takes
- Though, the Civil works have been accommodated at the begging of the project, in
order to prepare the infrastructure of the project to be ready once the materials are
on site.
concrete.
- The excavation of each line will be carried out each in one day respectively.
Page 10 of 17
- Once the excavation of the line is completed, sand should have been provide don
site to level the bed and be prepared to install the PVC pipes on the correct level.
- The PVC pipe shall be fixed by steel rebar, and will be connected using tanged
- Once the pipes are installed and inspected by the QC and Client representative,
filling team will start it’s work to fill the line with another 15cm on top of the PVC
pipe. And the rest of the trench will be backfilled utilizing the existing excavated
material.
- Hand Compacter will be utilized, to compact the soil on layer not exceeding 15cm.
- Manholes should have been ready on site, as Avro is intending to be using pre-
casted concrete manholes and transported on site once it’s placed is ready.
- Manholes shop drawings will be prepared by Avro, and will be submitted to the
- This will be the approach of the contract to undertake each line separately.
- For the lines that need to be hanged out to parameter wall, the plumbing team will
be connecting the line to the manhole and hang them up to the parameter wall
- For each activity a detailed method of statement will be provided for the approval of
Page 11 of 17
4. TECHNICAL INFORMATION
Technical Drawings
Page 12 of 17
Typical Trench Drawing
Page 13 of 17
Bill of Quantities
Technical
Item Description Reference Unit Q.ty
Number
2. Civil Works
2.1 - Site Survey and Occupation
2.1.1 Survey Site L.s. 1.00
2.2 - From Gen Pad to the Exsting Pull Pit 01 (Near To SDP01)
Provision and Installation of Cable Tray
2.2.1 m.l. 5.00
40cmx05cm
Cutting Concrete Slab By Concrete Cutting
2.2.2 L.s. 1.00
Machine
2.2.3 Demolition of the slab L.s. 1.00
2.2.4 Excavation Under the Slab C.m. 19.35
2.2.5 Sand Bedding (15cm Thick) C.m. 6.00
Provision and Installation of
2.2.6 m.l. 120.00
PVC Conduits of 4x110mm(4'')
Provision and Sand Bedding
2.2.7 C.m. 6.00
above the Conduits (15cm Thick)
Provision and Installation
2.2.8 m.l. 30.00
of Electrical Warning Tape
Backfilling with Existing
2.2.9 C.m. 19.35
Soil and Compaction
2.2.1 BRC Steel Provision Sq.
20.00
0 and Installation m.
2.2.1
Shattering Works L.s. 1.00
1
2.2.1
Concreting C.m. 5.00
2
2.2.1
3
2.2.1
Concrete Curring L.s. 1.00
4
2.3 - From Exsting Pull Pit 01 (Near to SDP 01) to Exsting Pull Pit 02 (Near to SDP
02&03)
2.3.1 Demolition of Exsting Barriars L.s. 1.00
2.3.2 Excavation C.m. 32.25
2.3.3 Sand Bedding (15cm Thick) C.m. 10.00
Provision and Installation of
2.3.4 m.l. 200.00
PVC Conduits of 4x110mm(4'')
Provision and Sand Bedding
2.3.5 C.m. 10.00
above the Conduits (15cm Thick)
Provision and Installation
2.3.6 m.l. 50.00
of Electrical Warning Tape
Page 14 of 17
Backfilling with Existing
2.3.7 C.m. 16.00
Soil and Compaction
2.4 - From Exsting Pull Pit 02 (Near to SDP 02&03) to New Pull Pit 03
(Near to SDP 06)
Excavation of Trench and New Pull Pit
2.4.1 C.m. 24.49
Location
Lean Concrete of 10cm for new Pull Pit
2.4.2 C.m. 0.25
Location
Provision of Pre-Casted Concrete
2.4.3 Pcs 1.00
Manhole 60cmx60cm With the Concrete Cover
2.4.4 Sand Bedding (15cm Thick) C.m. 5.74
Provision and Installation of PVC
2.4.5 m.l. 70.00
Conduits of 2x110mm(4'')
Provision and Sand Bedding above
2.4.6 C.m. 5.74
the Conduits (15cm Thick)
Provision and Installation of
2.4.7 m.l. 35.00
Electrical Warning Tape
Backfilling with Existing
2.4.8 C.m. 12.33
Soil and Compaction
Installation of Pre-Casted Concrete
2.4.9 Pcs 1.00
Cover for the New Pull Pit
2.5 - From Exsting Pull Pit 02 (Near to SDP 02&03) to New Pull Pit 04
(Near to SDP 04)
Excavation of Trench and New Pull Pit
2.5.1 C.m. 19.97
Location
Lean Concrete of 10cm for new Pull Pit
2.5.2 C.m. 0.25
Location
Provision of Pre-Casted Concrete Manhole
2.5.3 Pcs 1.00
60cmx60cm
2.5.4 Sand Bedding (15cm Thick) C.m. 4.59
Provision and Installation of PVC Conduits of
2.5.5 m.l. 28.00
1x110mm(4'')
Provision and Sand Bedding above the
2.5.6 C.m. 4.59
Conduits (15cm Thick)
Provision and Installation of Electrical Warning
2.5.7 m.l. 28.00
Tape
2.5.8 Backfilling with Existing Soil and Compaction C.m. 10.09
Provision and Installation of Pre-Casted
2.5.9 Pcs 1.00
Concrete Cover for the New Pull Pit
2.6 - From New Pull Pit 04 (Near to SDP 04) to Pull New Pit 05 (Near
to SDP 05)
Excavation of Trench and New Pull Pit
2.6.1 C.m. 25.67
Location
Lean Concrete of 10cm for new Pull Pit
2.6.2 C.m. 0.25
Location
Provision of Pre-Casted Concrete
2.6.3 Pcs 1.00
Manhole 40cmx40cm
Page 15 of 17
2.6.4 Sand Bedding (15cm Thick) C.m. 5.45
Provision and Installation of PVC Conduits
2.6.5 m.l. 38.00
and Connection to new Pull Pit
Provision and Sand Bedding above
2.6.6 C.m. 5.45
the Conduits (15cm Thick)
Provision and Installation of
2.6.7 m.l. 38.00
Electrical Warning Tape
Backfilling with Existing Soil
2.6.8 C.m. 13.04
and Compaction
Provision and Installation of Pre-Casted
2.6.9 Pcs 1.00
Concrete Cover for the New Pull Pit
2.7 - From New Pull Pit 03 (Near to SDP 06) to SDP
07&08
Provision and Installation of PVC Conduits
2.7.1 L.s. 1.00
and Connection to new Pull Pit
Provision and Installation of PVC Conduits
2.7.2 Hanged on the Parameter Wall up to SDP m.l. 37.00
07&08
2.8 - Final Cleaning
2.8.1 Final Cleaning and Removal of Additional Soil L.s. 1.00
5. SAFETY
The main activities of safety will be carried out in compliance with Health, Safety, Security
Contractor has to comply all the laws application of safety, permits to work systems, safe
operation standards of the OWNER, and safety precautions related to the contract
performance so that to protect the work, the personnel, and project team. Simultaneously,
subcontractor (if applicable) has to full fill all the safety laws that are ordered from the
Owner.
6. QUALITY CONTROL
Avro has to ensure that the employed staff has sufficient experience in order so that to
enhance the quality of the work. As well as Avro is responsible of the quality of material
Page 16 of 17
that is used as form work, scaffold, Concrete, Steel, Pre-cast concrete, PVC Pipes, Cable
Trays and other materials. Moreover, all the inspection form shall be filled properly and
Detailed QA/QC Plan shall be developed and submitted for the approval of the client’s
engineer in order to follow up the execution work and to make sure that the quality
Page 17 of 17