Document Number: RWTP-EX-PL1-211111-MST-001-R01
METHOD STATEMENT FOR TRENCHING
AND CHAMBER FOUNDATION WORKS
Date: 21-11-2021 Document: RWTP-EX-PL1-211111-MST-001 Revision: 03 Page 2 of 24
Table of Contents
1.0 PURPOSE ..................................................................................................................................................... 3
2.0 SCOPE ........................................................................................................................................................... 3
3.0 REFERENCE DOCUMENTS ...................................................................................................................... 3
4.0 ABBREVIATIONS / DEFINITIONS............................................................................................................ 3
5.0 HSE CONTROLS ......................................................................................................................................... 4
6.0 MANPOWER ................................................................................................................................................. 4
7.0 EQUIPMENTS & TOOLS ............................................................................................................................ 4
8.0 PERSONNEL PROTECTIVE EQUIPMENT - PPE.................................................................................. 4
9.0 PROCEDURE ............................................................................................................................................... 5
9.1 SURVEY & LEVELING ....................................................................................................................................... 5
9.2 EXCAVATION ................................................................................................................................................... 5
9.2.1 EXCAVATION FOR FOUNDATIONS ............................................................................................................. 5
9.2.2 EXCAVATION FOR TRENCHES ..................................................................................................................... 5
9.2.3 DISPOSAL OF EXCAVATED MATERIAL ........................................................................................................ 6
9.3 BACKFILLING & COMPACTION ........................................................................................................................ 6
9.3.1 FOUNDATIONS & PITS ................................................................................................................................ 6
9.3.2 PIPE LINE EXCAVATION .............................................................................................................................. 6
10.0 HEALTH, SAFETY, SECURITY & ENVIRONMENT .............................................................................. 7
11.0 RESPONSIBILITIES .................................................................................................................................... 7
11.1 PROJECT ENGINEER (PE) ....................................................................................................................... 7
11.2 CONSTRUCTION ENGINEER ................................................................................................................... 7
11.3 HSE ADVISOR .............................................................................................................................................. 8
11.4 SITE SUPERVISOR ..................................................................................................................................... 8
11.5 QC Engineer/Inspector ................................................................................................................................ 9
11.6 PERMIT HOLDER ........................................................................................................................................ 9
12.0 QUALITY CONTROL & SUPPORTING DOCUMENTATIONS ............................................................ 9
13.0 EMERGENCY ARRANGEMENTS ............................................................................................................ 9
14.0 EMERGENCY CONTACT NUMBERS.................................................................................................... 10
15.0 INSPECTION AND TESTING................................................................................................................... 10
16.0 RISK ASSESSMENT ATTACHED .......................................................................................................... 10
METHOD STATEMENT FOR TRENCHING
AND CHAMBER FOUNDATION WORKS
Date: 21-11-2021 Document: RWTP-EX-PL1-211111-MST-001 Revision: 03 Page 3 of 24
1.0 PURPOSE
The purpose of this method statement is to describe the procedure for doing the earth works like
excavation, backfilling, compaction, padding grading etc... To be carried out in accordance with
the project specification and standards required for the project scope.
2.0 SCOPE Mention BOQ & Ensure the compliance with RWTP-AS-QA4000R01-211016-Guideline
The procedure shall be applicable to all the earth work activities for pipeline trench excavation of
valve chamber/pit foundations etc... Which are required for the completion of the project.
HV - Heavy Vehicle
ERT - Emergency Response Team
MS - Method Statement
9.0 PROCEDURE
9.1 SURVEY & SETTING OUT
o Prior to commencement of any civil works safety precautions and necessary permits for
the job shall be taken from client (RWTP). Mention Client Name
o Prior to commencement of activities the control documents should be reviewed.
Specify the documents Available to start execution
o The coordinate and the datum use for the surveying and constructions shall be referred
from fixed controlled Bench Mark (BM) available in the existing facility
Change the instrument to (GPS) Change as (IFC & Existing RWTP facility.)
o All Survey instrument such as Dumpy level/Theodolite /Total station shall be calibrated
and calibration certificate made available for verification. If required.
o Sufficient Pegs shall be set and maintained during progress of civil works as required.
o Every 20 m pegs interval
o Three parties to inspect as inspection for settlement X,Y,Z in JSR.(Susteco, RWTP,
Orbital)
o To be approved by RWTP & Closed by Susteco site representative civil engineer.
o Once JSR & RFI closed them, Subcontractor is permitted to commence excavation.
9.2 EXCAVATION
9.2.1 EXCAVATION FOR FOUNDATIONS
o Prior to start excavation ensure that valid permit is in place.
o Before commencing breaking and excavation, make sure that there is no underground
services passing through the proposed excavation area.
o Excavation shall be executed for the required length, width and depth as per approved
drawing. IFC Number?
o Edge of the excavation shall be kept clear always. The excavated material shall be
deposited at least one meter away from the edge of the excavation to avoid overloading
the sides, avoiding collapse and preventing loose material from falling back.
o Adequate shoring of excavation shall be under taken as required to protect the excavation
faces from the collapsing.
o The bottom of the excavation shall be level and free of loose material.
o Barricade to be placed around the trench
o Excavation route shall be identified and marked before proceeding the works.
o The trenches shall be sufficient width to allow satisfactory jointing of the pipes and tamping
of backfilling under and around the pipe.
o Proper barrier should be placed on both side of the excavation with sign boards.
o Edge of the excavation shall be kept clear always. The excavated material shall be
deposited at least one meter away from the edge of the excavation to avoid overloading
the sides, avoiding collapse and preventing loose material from falling back.
9.3.2 PIPE LINE EXCAVATION (PL1) (See 9.3.1) and Do the same
o Ensure the clients approval RFI for Survey & Setting out, Excavation the previous is obtained
activity is closed as per the approved ITP (With code)
before starting backfilling.
o Backfilling of foundation and pits shall be placed evenly and compacted not exceeding
150 mm compacted thickness.
o Backfilling shall not contained stones with diameter greater than 100 mm
o Make sure that all sleeves and traps are in place before starting of backfilling
o Make sure the being installation as per the manufacturer requirement
o Confirm the required level of formation after backfilling & compaction as per approved
drawing.
o Work place shall be reinstated to its original up on completion of backfilling & compaction.
METHOD STATEMENT FOR TRENCHING
AND CHAMBER FOUNDATION WORKS
Date: 21-11-2021 Document: RWTP-EX-PL1-211111-MST-001 Revision: 03 Page 7 of 24
11.0 RESPONSIBILITIES
o Specific attention to all safety measures and quality control in line with the HSSE and
Quality Plan.
o Provide all necessary information and distribute the responsibilities to his construction
team.
o Ensure and monitor that the work progress is in accordance with the required program
and report the same to the Project Engineer.
o Coordinate with the Safety Advisor to ensure that the works are carried out in a safe
working practice.
o Monitor the execution of the works to confirm the compliance with the specification,
approved drawings (IFC Drawings), method statement, ITP.
o Maintain the records of Quality control check sheets / formats required for the activity.
SR.
NAME OF PERSON DESIGNATION CONTACT NO.
NO
CONSTRUCTION
1 PRINEESH PRAKASH 97240394
MANAGER
2 BINU MATHEW PROJECT ENGINEER 94768303
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Improper loading
Defective equipment Injury to persons due to 4 D H Follow proper lifting / loading procedures
Overloading fall from the vehicle Use proper restraining devices and procedure
Injury to persons due to Proper supervision Low Provision of first-aid
Defective chain binder and first aider Take the
Lack of proper restraining
fall of load from the Use of certified restraining accessories
vehicle Use of trained and experienced personnel injured to the nearest
devices
Material damage Ensure competence of the personnel involved clinic. Activate
Use of extra leverage for
tightening Movement of load Capacity of the vehicle should be related to the ORBITAL / RWTP/PDO
during transportation, load to be carried emergency response
Over tightness / slackness
Dimensions of the load
due to improper Loaded vehicle should not be more than:- manual
restraining. a) 4.8 mtrs height
Unsecured Loads
Accidents, personal b) 3.5 mtrs width
Use of lifting equipment
injury / death, property c) 1.5 mtr extension beyond rear
Uncertified tools and damage due to load
Emergency No
tackles d) 1.0 mtr form front
collapse. Use of point check list or lifting activity RWTP/PDO –
Comply with SP-2001 24385555, 24675555 &
Trained banksman with vest 5555
Length of vehicle on government roads should
not exceed 17 mtrs. ROP - 9999
Driver shall ensure that loads in the vehicle shall
be secured with ropes, straps, chains binders,
nets or suitable covers.
METHOD STATEMENT FOR TRENCHING
AND CHAMBER FOUNDATION WORKS
Date: 21-11-2021 Document: RWTP-EX-PL1-211111-MST-001 Revision: 03 Page 12 of 24
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Movement and positioning helmet and helmet shall be securely fastened by Emergency No
of articulated vehicles in chinstrap.
congested area. Driver shall park vehicle with brakes applied and RWTP/PDO –
Inadequate access to the reverse gear in position. 24385555, 24675555 &
back of vehicle for securing Driver of vehicle and plant shall ensure that ramp 5555
the equipment/ plant. of vehicle is secured in position to prevent
ROP - 9999
Loading of wheeled or movement or slippage while equipment is being
tracked plant on vehicle loaded.
Over head line Operator shall ensure that equipment wheels
Improper route or track are positioned in alignment with
Transporting without escort vehicle ramp.
vehicle Movement of equipment on ramp is very
(JCB/ Excavator/ Rock slow and controlled, movement to be on low
Breaker/ Side Boom). gear, no jerk. Steady control on steering.
Concerned supervisor / Site in charge to engage
only drivers experienced in this type of operation.
Once the plant is loaded driver of the trailer shall
ensure that lashing is done to prevent forward,
reverse and lateral movement during
transportation.
Proper route survey shall be conducted prior to
transporting Beam pumps
Escort vehicles shall be provided while
transporting beam pumps.
Use of chocks for all loading & unloading
vehicles
METHOD STATEMENT FOR TRENCHING
AND CHAMBER FOUNDATION WORKS
Date: 21-11-2021 Document: RWTP-EX-PL1-211111-MST-001 Revision: 03 Page 14 of 24
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
METHOD STATEMENT FOR TRENCHING
AND CHAMBER FOUNDATION WORKS
Date: 21-11-2021 Document: RWTP-EX-PL1-211111-MST-001 Revision: 03 Page 16 of 24
Incorrect use and defective Tripping over injury 3 D M Use of competent operator Low Provision of first-aid
lifting equipment Mechanical failure Operator shall check soil condition and see that and first aider take the
Inadequate crane working Dropped load outriggers are in position before starting lifting injured to the nearest
platform (due to Tripping over dropped operations clinic. Activate
soft/unstable soil, outrigger load injury Crane to be operated within SWL ORBITAL / RWTP/PDO
not fully deployed etc) Injury / Accident Certification and color coding of equipment/tools emergency response
Over loading of Loss of property and tackles manual
Crane/forklift Fall of material / injury All rigging, singing and lifting to be done by
Defective lifting equipment Tripping of person competent person
Incorrect rigging, singing Fire Prior to use, all equipments to be visually
and lifting practices Emergency No
Back injury inspected
Damage to lifting Hard injury All persons to be made aware of danger through RWTP/PDO –
equipment since inspection tool box talk
24385555, 24675555 &
Personnel having body Ensure sufficient room for operation
5555
part trapped by load Tag line to be attached to load to prevent
Moving crane/load hitting swinging ROP - 9999
people / assets The material not to be stacked too high
Material stacked too high Material to be stacked on adequate base
Inadequate base for Materials to be secured/covered are kept under
storing materials shelter
Material not protected from Good housekeeping to be maintained
bad weather Material to be adequately segregated
Lack of segmentation of Proper ventilation
material (eg. Oil, Gases, Declare no smoking area
Chemicals etc) Clean up spillage immediately
Incompetent operators Persons to be trained for correct manual lifting
Spillage of Oil, Chemical techniques
Use of fire ignition source
METHOD STATEMENT FOR TRENCHING
AND CHAMBER FOUNDATION WORKS
Date: 21-11-2021 Document: RWTP-EX-PL1-211111-MST-001 Revision: 03 Page 17 of 24
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
E.25) Shuttering & De- Personnel Injury Use of proper lifting procedures
shuttering Damage to material Proper supervision
Collapse of shuttering Use of trained and experienced personnel
structure etc. 2 D M Good housekeeping Low Provision of first-aid
Tripping and falling Use of necessary PPE
Sharp edges and first aider Take the
Fall of shuttering plates
down Remove nail from the area after use injured to the nearest
due to improper lifting / Use quality and standard tools clinic. Activate
positioning Proper working platform ORBITAL / RWTP/PDO
Improper storage of Certified scaffolding emergency response
shuttering plates. manual
Protruding nail
Flying objects
Homemade tools
Emergency No
Working at height
RWTP/PDO –
24385555, 24675555 &
5555
ROP - 9999
E.26) Working with Skin allergy Use of trained and experienced personnel
Concrete Personnel injury Use of suitable PPE like, gloves, apron etc.
Provision of guards to rotating parts
METHOD STATEMENT FOR TRENCHING
AND CHAMBER FOUNDATION WORKS
Date: 21-11-2021 Document: RWTP-EX-PL1-211111-MST-001 Revision: 03 Page 22 of 24
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Splashing of concrete Damage to property / 2 C L Use wheel stopper Low SHOC Card of cement
Fall of mortar pan equipment etc. Proper supervision to be made available at
Untrained operator Eye Injury Proper working platform and fall arrestor site.
Collapse concrete work Fall Injury Trained personnel
Prolonged exposure to Respiratory problems RWTP/PDO approved equipment and Provision of first-aid
dust, noise and cement Back injury competent operator and first aider Take the
Poor housekeeping Obtain PTW injured to the nearest
Sharp edge of mortar pan Regular maintenance inspection of plant clinic. Activate
Rotating parts of concrete Barricade the area/perimeter barricade ORBITAL / RWTP/PDO
mixer Warning signs to be placed emergency response
Improper use of tools or Restriction of personnel around rotating manual
defective tools equipment
Incorrect use of or Tool box talk to be conducted before start works
defective plant, equipment, Use RWTP/PDO Approval equipment Emergency No
Mixer, JCB, Dumper Authorized/ competent operator
Incorrect material handling Competent signalman RWTP/PDO –
technique Use PPE: Helmet, shoes, goggle, mask, gloves 24385555, 24675555 &
Incompetent operator Tool box talk 5555
Inadequate maintenance of Preventive/routine maintenance
plants Use ear plugs ROP - 9999
Incorrect form work Barricade area
Noise Warning signs
Fall/trip Tool box talk
Unauthorized movement of Only authorized personnel
persons Adequately designed and checked form work
METHOD STATEMENT FOR TRENCHING
AND CHAMBER FOUNDATION WORKS
Date: 21-11-2021 Document: RWTP-EX-PL1-211111-MST-001 Revision: 03 Page 23 of 24
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
Consequence
Risk
(0,1,2,3,4,5)
(A,B,C,D,E)
Risk Rating
Probability
Contingency
(H,M,L)
Rating
Significant HSE Hazard Hazard Effect Control Measures after measures
controls
placed
RWTP/PDO –
24385555, 24675555 &
5555
ROP - 9999