Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 1 of 16
Approved By
Prepared By Checked By Checked By Head Of Engineering
Rev Description Date (Shield Tech) (AL DHANA) (HMC-Eng’r)
(HMC)
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 2 of 16
TABLE OF AMENDMENTS
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 3 of 16
CONTENTS
1.0 INTRODUCTION………………………………………………………………………04
3.0 OBJECTIVES…………………………………………………………………………..04
9.0 ATTACHMENTS……………………………………………………………………….16
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 4 of 16
1.0 INTRODUCTION
This Method statement describes in details the onsite Supply, Installation and Commissioning of
Electro Mechanical Works for AWH. All the Materials Accessories will be as per the project
(Tender) specifications.
This method statement covers Supply Installation and Commission of Electro Mechanical works.
All the materials are manufactured & will be installed in accordance with approved material
submittal, Issued for construction drawings, manufacturer’s recommendation and Project
Specification
The Installation of Materials for AWH -Lithotripsy and recommendation as per approved drawing,
installation will be inspected & approved by HMC Engineering / AWH team. This guidance is
based on the requirements coordination with HMC Engineering FM team set forth in the HSE
Plan and Project Quality Plan (PQP). Also this method statement covers in brief about the
installation procedure with respect to approved shop drawing and the recommendations.
This Method Statement also covering the associated works like Electro Mechanical works, etc.
3.0 OBJECTIVES
This document provides guidance for the implementation of an effective procedure for
compliance with requirements and suggestion stipulated within for the safe and quality
installation of Civil and Electro Mechanical Works. This includes the following:
Room Construct
Proposed area 4 x 4x 3 m Construction of the Room with plywood l.
Wooden Door 2 m x 2 m Single leaf
Wooden roof slab
Protected with polythene
With proper air conditioning System
Temporary Fire Detection system
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 5 of 16
Electrical Work
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 6 of 16
Mechanical Work
GI DUCTING & FFAHU Fixation
Installation of Supply Air & GI 22g/24g duct as per design
Installation of VCD as per the duct size & design.
Aluminum Ceiling diffuser as per the propose size & design.
Fire rated dampers with access door as per the duct size & design.
Fresh air ducting as per requirement with sand trap lower filter.
Leakage Testing & third party air balancing.
Installation of FFAHU as per drawing.
Plumbing/Drainage Work
Supply & Fixation
Supply fixation of domestic water 22mm/15mm copper pipe line with brazing fittings.
Clinical Wash basin connected to the existing nearness point hot cold & return water
line & proper brazing.
Battery operated Sensort type wash basin mixer
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 7 of 16
Disposing Material - Remove all unwanted things like as demolished building waste,
electrical and other debris. Mobilize to prescribed industrial waste disposing and clean
the site.
This procedure will be used, as needed, to provide assurance that installation activity will
be conducted as required by the project specification and procedures also Shield Tech.,
will observe this installation from time to time to make sure installation in line with the
recommendation & requirements. It is not expected that completion of the entire
procedure will be accomplished during any one inspection and/or every time the
inspection procedure is used. It is a continuing activity until complete installation work is
finished. All work associated with the method statement must be checked and signed off
by the client / client representative.
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 8 of 16
Prior to starting work, necessary approvals shall be made from the Company.
Existing services, pipelines and fittings still in are shall be protected in a proper way to
prevent any damage or clogging during demolition.
In case of demolition of existing building, adequate information shall be given well in a
dvance to allow and plan any shutdown is necessary during changeover.
Adequate protection and preservations shall be given to existing foundation, pathway
s and roads.
In case of any obstructions or fall of debris on roads, the area shall be cleaned on im
mediate basis.
During demolition of concrete structures, suitable temporary supports shall be made t
o existing structure. All the demolished materials shall be separately stored and dispo
sed of at the approved dumping location.
In case of observations of any unidentified services or cables during the process, it sh
all be informed immediately to the company and work shall be proceed further only aft
er getting proper approval.
A sequence of operations shall be established which allows the clearance of debris o
n regular basis such that unnecessary overloads to the existing structures shall be av
oided and to maintain a good housekeeping.
Upon completion of demolition work, the site shall be kept tidy and the surrounding ar
ea shall be cleaned to avoid the accumulation of any dust and debris.
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 9 of 16
Material will be delivered at site in undamaged condition, with identifying labels intact
and legible.
Materials will be handled, off loaded & stored properly.
All Material shall be stored per manufacturer’s recommendation. .
All materials will be covered for protection.
Protection cover shall be in place for all materials until taken out for installation.
Delivery of materials will be checked for any shortage by store keeper and for and qu
ality, damaged, storage condition and compliance for project specification and approv
ed material submittal etc will be inspected by QC.
After inspection and acceptance by contractor QC that all delivery materials are corre
ct then MDS (Material Delivered to Site Inspection) will be raised for consultant inspec
tion.
Damaged, rejected material (non compliance with the requirement) will be identified a
nd stored separately or removed from site later.
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 10 of 16
Cables placement will take place mainly above ground in perforated, ladder-type cabl
e trays.
Placement of cable rollers every 6-12 meters or as required will ensure that the cable
will not be in contact with the tray.
If a cable winch is used, it will be installed properly for cable pulling.
The drum schedule will be used to identify the cable drum that will be used for cable p
ulling.
A gripper or a cable shock will be used to fix the cable to the winch.
Cable laying will begin from one end of the route or any other suitable point if needed
Prior to cable cutting, inspection of both ends shall take place to make sure there is s
ufficient length for proper dressing and end termination.
Right after every cable is finished, all cables shall be tested for insulation resistance
Installation of cable tags.
Update the cable and drum schedules with cable pulling information.
Trefoil (three-foil formation) laying shall be used with single core cables.
Punch list and installation shall be inspected.
When cable lying is completed, insulation test will take place according to attached for
mat.
Raceways’ inspection will make sure that wires are compliant with the installation
When more than one wire is installed in the same raceway, they should be pulled in th
e raceway at the same time.
Use guide wires and similar equipment when wire pulling, to support the tension and
avoid possible damage.
Wherever the Engineer approves, use lubricant or wire pulling compound if necessary.
Ensure that the pulling compound used is chemically compatible with any insulations
or conductors it touches.
Conductor splices must be enclosed in junction boxes
Use a minimum of 300mm of slack conductors inside DB and at each outlet as neede
d.
Ensure proper wire installation in all boxes.
Following installation, the Wires Insulation Test should be conducted according to the
attached format.
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 11 of 16
The outer as well as inner surface of each duct shall be cleaned by cloth prior to
installation.
Approved duct sealant shall be applied at the joint of the ductwork.
Two or more piece of duct shall be joint together on the floor to form manageable
lengths.
Prior to installation of duct coordination with other trades / discipline will be done.
Position of duct support shall be marked on the underside of the stab/structural
member/vertical walls as the case and mechanical anchor.
Threaded rod of suitable size as per approved drawings shall be fixed to mechanical
anchor fastener / clamps using proper lock nut.
Duct pieces shall be installed and joined together as detailed of approved drawing.
Volume control dampers and fire dampers shall be installed at the location shown on
approved shop drawing.
Installation of the duct work applies approved duct sealant to all flanged joint of the
duct work installed by using sealant gun.
Duct joint, joints of branch tapping butterfly dampers, volume control dampers, etc.
shall be insulated materials as detailed above.
Flexible duct connecters shall be provided at all location where the ductwork crosses.
Duct shall be connected to FAHU ’s FCU’s with flexible insulated duct connector.
Duct shall be connected to fans with flexible duct connector.
Duct work surface shall be cleaned with dry cloth to remove any surface dust and cut
ends of angles & flanges which will be paint coated with zinc rich paint.
Suitable plenum box be connected to main duct through pre-insulated flexible duct,
and duly insulated and connect through round collars fixed to plenum.
All open ends shall be covered & protected after installation of ductwork with
polyethylene sheet.
The insulated duct is identified as per approved identification system.
4.7 Plumbing
Liaise with other contractors and facilities manager to isolate water supplies.
Isolate Hot & cold water pipes where necessary.
Drain down the water system where necessary.
When chasing out the walls firstly use the cable/pipe finder to locate any electric
cables or pipe work.
Mark the wall for the area to be chased out.
On plasterboard walls carefully cut out using a knife or saw.
If necessary remove any skirting boards by driving the bolster chisel behind the board
and carefully levering it away from the wall (gloves should always be worn)
If necessary to take up any floorboards these should first be checked with the
cable /pipe finder to ensure the area below the board is clear.
Using the bolster chisel lever up the board, remove all nails.
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 12 of 16
When taking up carpet and lifting floorboards attention will be paid to the trip hazard c
reated, do not leave open floorboards and upturned carpets any longer than is necess
ary, sufficient warning signs must be posted where there is a risk of other contractors
entering the site.
Carry out replacement of parts or repairs.
Ensure waste pipes and other plastic pipe works are connected correctly.
Where plastic pipe is connected with solvents, staff will follow all safe use instructions.
Where solder work has to be carried out, prepare pipe work for solder joints.
Obtain the appropriate hot work permit from the facilities manager.
Ensure the correct type of fire extinguisher is on hand during hot work.
Protect surrounding area with heat shields.
Ensure adequate ventilation for solder work.
Connect and solder all necessary joints.
Check all joints.
Liaise with facilities manager to turn water supplies back on.
Carry out further checks for water tightness and quality of finish.
Chlorinate the system if required and check for successful completion.
Request facilities manager to inspect works.
Issue certificate of completion and chlorination to facilities manager.
Pack tools and equipment and leave area clean and tidy.
Maintain fire watch for 2 – 4 hours where hot work has been carried out.
Report to site office and sign off permit to work.
Remove all unwanted things like as demolished building waste, electrical and other
debris. Mobilize to prescribed industrial waste disposing and clean the site.
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 13 of 16
9. Measure and mark cutting lines on materials, using ruler, pencil, chalk, and
marking gauge.
10. Shape or cut materials to specified measurements, using hand tools,
machines, or power saw.
11. Assemble and fasten materials to make framework or props, using hand
tools and wood screws, nails, dowel pins, or glue.
12. Build or repair cabinets, doors, frameworks, floors, and other wooden
fixtures used in buildings, using woodworking machines, carpenter's hand
tools, and power tools.
13. Erect ladders for assembling structures above ground level.
14. Remove damaged or defective parts or sections of structures and repair or
replace, using hand tools.
15. Finish surfaces of woodwork or wallboard in houses and buildings, using
paint, hand tools, and paneling.
16. Inspect ceiling or floor tile, wall coverings, siding, glass, or woodwork to
detect broken or damaged structures.
17. Work with and/or remove hazardous material.
18. Coordinating the Work and Activities of Getting members of a group to work
together to accomplish tasks.
19. Permit to Work shall be provided and HTM standard shall be followed
strictly.
Installation of Workstation and Modification with its accessories needs to follow the
established codes and safety procedures strictly. Care should be taken to ensure that
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 14 of 16
The Engineer/Supervisor should be familiar with the specification and HMC QA/QC
inspection requirements. The intent is to establish a high level of assurance that the end
product meets the project specifications and requirements.
The engineer should verify that the supervisor is familiar with this Method Statement and
is issued with copies of the inspection checklists.
The engineer should satisfy procedures provided by QA/QC inspections to ensure that
the installation of Workstation and Room Modification with its accessories meet specified
engineering requirements. As part of the assessment, the HMC QA/QC Inspection
Procedures must ensure a qualitative acceptance criteria for determining the prescribed
activities have been accomplished with satisfactorily level.
The Engineer/Supervisor/ should verify that the personnel have sufficient knowledge of
the procedure for the installation Workstation and Room Modification with its accessories.
Review any training and qualification records for those individuals who will do the task to
determine whether they are skilled enough to follow the procedure before the actual work
is carried out.
Head Of Engineering
(HMC-AWH) Approving authority for the method statement
CIVIL ENGINEER Mandate holder for construction and responsible for executio
n of works as per approved method statement
Site Engineer (AL DHANA) Execute the work & check the method statemen
t and its proper implementation.
QA/QC Engr. Liaison to QA/QC Engineer and check the implementation at site
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 15 of 16
As per standard requirement complying project specification, approved material submittal and
local & international standards not restricted with given under headings-
7.1 Equipment’s
8.1 Preparation
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 16 of 16
Safety Inspection
It is responsibility of the Site Engineer and Supervisor to inspect the areas physically
under their control in complete installation activity.
CLIENT MAIN CONTRACTOR SUB CONTRACTOR
Rev No.
TITLE: Page
METHOD STATEMENT FOR SUPPLY INSTALLATION OF ELECTRO MECHANICAL WORKS
Page 17 of 16
Risk Assessment – process of evaluating the risk arising from a hazard taking into
account the adequacy of any existing controls and deciding whether or not the risk is
acceptable
Tolerable Risk - Tolerable risk is defined as the risk that has been reduced to a level that
can be endure by HMC having regard to its legal obligations and its own HSE Policy
After the risk assessment of the identified hazard has been performed, it is mandatory
that necessary mitigating and control measures ( approved by safety inspector) are
established and implemented to reduce the risk into an acceptable level, if cannot be
eliminated, before start the work.