The present status of existing MCC is Transformer 1 & 2 ( NA5 & NA11 ) & bus coupler (NA6)
were in on condition and bus coupler (NA10) is in switched off condition.
Lay the LV cable to new DB in 11 KV switch gear room from existing MCC and
2
energize the Battery charger for switchgear protection.
Lay the new LV cable from new MCC to pump numbers 3, 4,6,7,8 & 9 and terminate
3
the power cable in the MCC side... Refer drawing number
Arrange for the inspection of MCC panel by Kahramaa customer department and
6
install the new KWH meter.
Commission the transformer – 3 after checking the protection interlock and energize
7
the MCC pertaining to TX- 3
Shift the VFD connection for pump number 4 from existing MCC ( NA12) to new
8
MCC (Q48) by taking PTW
Shift the VFD connection for pump number 8 from existing MCC ( NA17) to new
9
MCC (Q49) by taking PTW
Shift the VFD connection for pump number 9 from existing MCC ( NA18) to new
10
MCC (Q50) by taking PTW
Switch on the bus coupler between Transformer 2 & 3 (QB2) and energize the bus
11
bar of Transformer – 2 and ensure that QM2 in switched off condition
-1-
Method Statement for
9191 ecniS napaJ akasO
Electrical work Related to
replacement of MCC in New Doc. Date
Ref. : MS – NSPS - EL – 03
: 31.12.2008
GTC71 / 2005 Salwa pumping station : .Rev
Shift the VFD connection for pump number 7 from existing MCC ( NA13) to new
12
MCC (Q24) by taking PTW
Switch off existing transformer number – 2 after obtaining approval from ENA
15 department. Arrange to remove the KWH meter by the Meter Section of customer
department by submitting all relevant documents.
Switch off bus coupler (QB2) and energize the bus bar pertaining to TX- 2.by
17
switching on QM2
Ensure that Bus coupler ( NA10 ) should be in switched off condition and remove the
18
part of existing MCC ( NA11, NA12, NA13, NA17 & NA18 ) by obtaining PTW.
Install last part of new MCC (Q1 to Q4 ) and complete the installation pertaining to
19
transformer – 1 section
Shift the VFD connection for pump number 6 from existing MCC ( NA4) to new MCC
20
(Q23) by taking PTW
Shift the VFD connection for pump number 7 from existing MCC ( NA13) to new
21
MCC (Q24) by taking PTW
-2-
Method Statement for
9191 ecniS napaJ akasO
Electrical work Related to
replacement of MCC in New Doc. Date
Ref. : MS – NSPS - EL – 03
: 31.12.2008
GTC71 / 2005 Salwa pumping station : .Rev
Shift the VFD connection for pump number 1 from existing MCC ( NA16) to new
23
MCC (Q19) by taking PTW
Shift the VFD connection for pump number 2 from existing MCC ( NA1) to new MCC
24
(Q20) by taking PTW
Shift the VFD connection for pump number 5 from existing MCC ( NA3) to new MCC
25
(Q21) by taking PTW
Shift all auxiliary loads from existing MCC to new MCC – Refer method statement
26
MS – NSPS – EL – 04.
Switch off existing transformer number – 1 after obtaining approval from ENA
29 department. Arrange to remove the KWH meter by the Meter Section of customer
department by submitting all relevant documents.
Switch off bus coupler (QB1) and energize the bus bar pertaining to TX- 1.by
31
switching on QM1
-3-