ID Task Name Duration Start Finish Predecessors July 2021 August 2021 eptember 202 October 2021 ovem

1 26 1 30 1 34 1 38 1 42
27-06 25-07 22-08 19-09 17-10
1 SUBMISSION OF SHOP DRAWING 7 days Mon 02-08-21 Tue 10-08-21

2 APPROVAL OF SHOP DREAWING 7 days Tue 10-08-21 Wed 18-08-21

3 REMOVING OF HARD LANDSCAPE TILES 7 days Wed 18-08-21 Thu 26-08-21

4 EXCAVATION 16.5 days Fri 20-08-21 Mon 13-09-21

5 CABLE LAYING 5 days Mon 13-09-21 Fri 17-09-21

6 BACKFILLING 5 days Mon 13-09-21 Mon 20-09-21 4

7 KAHRAMAA CABINET FIXING 3 days Fri 20-08-21 Tue 24-08-21

8 REINSTATEMENT OF HARD LANDSCAPING & 7 days Fri 17-09-21 Mon 27-09-21


SOFT LANDSCAPING

9 TERMINATION & CONNECTION 3 days Thu 23-09-21 Mon 27-09-21

10 KAHRAMMA COORDINATION 42 days Mon 02-08-21 Tue 28-09-21

Task Milestone External Tasks


Project: LUSAIL MOSQUE PROGRAM
Split Summary External Milestone
Date: Mon 16-08-21
Progress Project Summary Deadline

Page 1