Diversion works
CLIENT : MERAAS
CONSULTANT : PARSONS
CONTRACTOR : KTC-INTERNATIONAL CO .
REVISION
TABLE OF CONTENTS
I. PURPOSE.
IV. SPECIFICATIONS.
VI. RESPONSIBILITY.
X. METHOD STATEMENTS
I. PURPOSE
To give details of and to obtain Engineer’s approval for the method to be carried out
for the DEWA HV cable shifting as described here under.
The scope of this document is to lay down a step by step procedure to be followed
for cable laying & relocation works. Shop drawings and Method statements to be
approved by PARSON and DEWA prior to execution of work.
Shop drawings
Shop Drawings showing existing cable location & proposed new location with cross
section.
IV. SPECIFICATIONS
VI. RESPONSIBILITY
Project/Site Engineer – The Site/Project Engineer shall organize and manage all
Activities relating to construction mentioned in the scope of works. He shall be
Responsible for planning and overall supervision and execution of all works .He is
Responsible to facilities all inspection requests and coordinate with consultant. He is
responsible to ensure that the HSE measures have been carried out for the
particular activity.
Site Supervisor/ Foreman – He shall arrange, prepare and follow up activities on
site. He shall manage and control the Machinery, Operators, Drivers and workers
on site.
Method Statement for 11kV Cable
Diversion works
2. EQUIPMENT
Excavator will be used to excavation of new trench and without any
existing services.
Cable Detectors confirming to safety standards.
Hand Shovel.
3. MACHINERY LIST
Excavator
Skid loader
Cable winch
Plate compactors
Machinery transport trailers
Light vehicles
Tipper Truck
X. METHOD STATEMENT
All the site works are to be carried out in the presence of DEWA supervision;
a) By using cable detectors and trial pits to identify the existing cables.
Method Statement for 11kV Cable
Diversion works
b) Manually excavate the trench .If allowed use excavator for top hard layer
removal
c) Excavate up to warning tape level and remove warning tape
d) Further excavate up to HDPE protection tile level and collect tiles not to be
reuse Contractor to hand over to DEWA.
e) Excavate further down carefully and expose the existing cables DEWA
inspector to inspect the existing cables.
f) Manually or by machine Excavate (in parallel) new trench for re laying.
(slewing) the cable (if find any joints/ damage the cable complete the job as
per DEWA instructions).
g) If Duct Banks are there, they should be ready in the new trench formation
and trench details to be inspected by DEWA.
h) After the cable manually laying (diversion) to new trench.
i) After Laying(diversion) the cable backfilling with soft sand surround and
level the trench for entire length.
j) Install HDPE tape and continue backfilling with existing soil without
stones.
k) Carryout rest of the backfilling in layers with excavated soil by Skid loader
and place warning tape at 300mm below FGL, water and compact
mechanically
a) All operations will be carried out in a safe working manner, and in each and
every stage , execution shall be adopted full accordance with the approved
“Health, safety and Environment Policy” manuals.