Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting

station No. (5) In Badr City.


Construction Method for Pump Station

1- Surveying works
Purpose:

 Determined to complete markings,


gridlines, level and layout of plain concrete
for pump station.
Responsible Manager:

 Site engineering
 Surveyor
Labor and equipment:

 Surveyor
 Total station
Work Procedures:

 Before work starts, survey department will establish baselines and


benchmarks from which co-ordinates and elevations will be taken to
set out the foundation works.

 A starting point is selected and must be in a security position for the


device and allow a clear view of the points
 surveyor directs the binoculars to any direction and assumes the
direction of the north, and then raises the project points and natural
phenomena.
 Survey the levels of the project: the surveyor will raise the levels
required by the project and before exiting the surveyor station to the
site must be confirmed

1|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

2- Excavation Works
Purpose:

 excavate soil under the


pump station by using
excavator to excavate soil
with a depth of 7 m
Labor and equipment:

 Excavator/JCB
 Dump Truck used for
disposal of debris
 2 Labors
Responsible Manager:
• Site engineering
Work Procedures:

 Excavations will generally be executed in open cut to the size, slope


and elevation shown on the construction design calculations
 Survey will verify set out and check edge slope and bottom
foundation level of excavation.
 Excavation will be carried out with excavator and the excavated
material loaded directly into dump truck and transported to temporary
stockpile area.
 The final bottom of foundation level will be inspected by quality
control (QC) and compacted as per design requirements before
pouring P.C concrete.

2|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

No Of
Production Duration
Item No Crew Description Quantity Crew
Rate (Days)
s
Excavator + 2 Tipper
Excavation Truck + Surveyor + 11893m3 400 m3/day 2 15
Labor
Resources & Duration

3- Soil Replacement
Purpose:

 Replacing the existing soil with another soil that has special
specifications. The replacement process is carried out in an
engineering way to reach soil suitable for foundation according to the
design.
Labor:

 Loader
 2 Plate Compactor
 Tipper Truck
 labor
Materials:
 Sand
Responsible Manager:
• Site engineering

3|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Work Procedures:

 Filling low-level areas shall be to the level of sub grade as designated.


After completion of clearing and grubbing, the Contractor shall carry
out the necessary leveling in order to control the thickness of the
layers of fill.
 The existing natural ground shall be scarified in place to a minimum
depth of 75mm for the full width of the embankment. The scarified
material shall be leveled and compacted to a minimum of 95%
maximum dry density.
 Where an existing embankment is being widened, the existing
embankment slope shall be trimmed and compacted into benches of
minimum width 1m and depth 500mm before placing and compacting
each layer of new embankment material unless otherwise directed by
the Engineer to suit particular circumstances.
 The Contractor shall not proceed with filling and compaction any
subsequent layer before testing and securing the approval of the
Engineer for the previous layer.
 Each fill thickness shall not exceed 250mm.
 Complete the termite control application (if applicable) based on the
manufacturer recommendation and same procedure apply on the tie
beams and pile cap with approval by the consultant.

4|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

4- P.C. Foundation
Purpose:
Make a leveling layer under the
foundations. It forms a strong
layer under foundations to
ensure that the load is
distributed evenly in all
directions. Soil isolation from
reinforced concrete foundations.
Reducing the effect of moisture
on rebar.
Labor and equipment:
• Concrete Mixer Trucks
• Vibrators
• Concrete Pumps
• Carpenter + Helper
• Surveyor
Materials:
 Ready mix concrete
Responsible Manager:
• Site engineering
• Surveyor

5|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Work Procedures:
• The bottom of the excavation should be dry and compacted to a
uniform level before pouring the 300 mm thick or as per drawings
 Surveyor to complete markings and layout of water tank location.
 Submit the inspection request prior to fix the formworks.
 Clean the area and remove waste materials prior to fixing the
formworks. Formworks shall comply with relevant specifications and
standards.
 Pouring of concrete for the p.c. foundation of the water tank using
concrete pump after the consultant approval of the previous activities.
 Arrange and use vibrators during concreting works.
 Provide necessary curing and removal of formworks for concrete
water tank and apply the waterproofing as per applicable procedure.
 Clean and remove all debris prior to start the waterproofing
application.
 Apply the waterproofing membrane as per drawings and the
procedure for application of waterproofing.

6|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

No Of
Production Duration
Item No Crew Description Quantity Crew
Rate (Days)
s
Shuttering of
Carpenter + Assistant 540m3 30 m3/day 4 5
P.C
2 Carpenter + 2
Concrete Vibrator
Pouring of Operator + Foreman +
540m3 150 m3/day 2 2
P.C 4 Workers + Pump +
5 Truck Mixer (8 m3)
+ 2 Concrete Vibrator
Horizontal
Installer + Assistant 3500m2 100m2/day 5 7
Membrane

Resources & Durations

5- Horizontal Water Proofing Membrane


Purpose:
The purpose of the application of waterproofing is to prevent the water
to percolate or penetrate into any underground concrete members. When
the water penetrates into the sub-grade concrete like foundation such as:
mat foundation, footing, tie beam etc. the steel reinforcement that
embedded in the concrete would corrode due to chemical reaction
caused by water and the structure would eventually fail.
Labor and Equipment:
 Installer + Assistant.
 Wheel borrow
 Metal tape
7|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

 Torch
 knife

Materials:
 Approved water proofing membrane.
Responsible Manager
• Site engineer.
Work Procedures:

 Any undulations or protrusions on the surface would be removed


in order to obtain smooth surface. The surface must be thoroughly
cleaned and free from dust, dirt loose materials, oil or grease.
 For horizontal waterproofing membrane application. Two layer of
4mm thick bituminous membrane shall be laid fully torched on
blinding concrete with minimum of 100m end laps and 150mm
side laps.
 The blinding surface shall be primed with the primer
recommended by the manufacturer of the membrane prior to
placing the membrane. Prior to succeeding works the applied
primer shall be inspected by the Engineer 24 hours after the
placement.
 Waterproofing membrane installation shall be performed using
cylinder fed propane gas torch, trowel to seal the seams of the
membrane and knife for cutting.
 The membrane is then placed in the correct torching on position
then re-rolled for about half of its length without changing its
orientation.
 The membrane is then un-rolled again and torched on pressing the
melted area against the substrate.

8|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

 Repeat till the entire length of the membrane is bonded firmly onto
the surface then the second membrane is laid in the same way with
an overlap of 150mm at the end and 100mm at the side.
 An extra length of minimum 300mm of the horizontal membrane
shall be left to carry up the vertical surface to maintain continuity
of the membrane and be protected as above.
 Before applying the waterproofing membrane, concrete surfaces
shall be primed with primer recommended by the manufacturer of
the membrane but the again it should be inspected by the Engineer
24 hours after the placement.
 The extra portion of 300 mm of the horizontal membrane left shall
be turned up and wrapped on to the vertical primed surfaces. The
continuity of the membrane shall be maintained by minimum laps
of 150mm.
 All areas of the membrane exposed above ground shall be
protected with appropriate flashing.
 Inspection would be submitted for approval of the Engineer.
 Before fixing of steel reinforcement for foundation, the membrane
shall be covered by one layer of polythene sheet and poured with
50 mm thick layer of cement sand screed.

Resources & Durations

Crew Productio No Of Duration


Item No Quantity
Description n Rate Crews (Days)
Vertical
Installer +
Membran 3500m2 100m2/day 5 7
Assistant
e

9|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

6-R.C. Raft Foundations


Labor and equipment:
• Concrete Mixer Trucks
• Vibrators
• Concrete Pumps
• Carpenter + Helper
• Surveyor
Materials:
• Ready mix concrete
• Reinforcing rebars
• Plywood Sheets
Responsible Manager:
• Site engineering
• Surveyor
Work Procedures:
•Surveyor to complete markings and layout of water tank location.
•Steel fixer will fix the reinforcement in accordance to the drawings
issued for construction. Provide concrete covering for the
reinforcement based on the approved drawings.
•Submit the inspection request prior to fix the formworks.
•Install the water stop as per drawings and approval by the consultant.
•Check the Plumbing Pipe Sleeves for water tank and other MEP
sleeves as applicable according to the coordination drawings. The
contractor should not fix the formworks without the approval from

10 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

QA/QC and consultant and inspection request to be signed by both


parties.
•Clean the area and remove waste materials prior to fixing the
formworks. Formworks shall comply with relevant specifications and
standards. Submit the work inspection request after the formwork
installation prior to pouring the concrete.
•Pouring of concrete for the Raft foundation of the water tank using
concrete pump after the consultant approval of the previous activities.
•Arrange and vibrators during concreting works.
•Provide necessary curing and removal of formworks for concrete
water tank as per tender specs.

11 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Resources & Durations

Crew Production No Of Duration


Item Quantity
Description Rate Crews (Days)
Shuttering of
Carpenter +
R.C Raft 3350m3 30 m3/day 7 16
Assistant
Foundation
Reinforcement
Steel fixer +
of R.C Raft 3350m3 7 m3/day 16 30
Assistant
Foundation
Steel Fixer + 2 3x
Carpenter + 2 3shiftx8
Concrete Vibrator Hrs. x
Pouring of R.C Operator + 3days
Footing/Raft Foreman + 3350m3 150 m3/day 3 ‫أيام‬ 3
foundation 4 Workers + ‫صب‬
Pump + 5 Truck ‫متواصل‬
Mixer (8 m3) + 2
Concrete Vibrator

12 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

7- Formwork for Pump Station Walls


Labor and equipment:
• Truck Mixer
• Concrete Mixer Trucks
• Vibrators
• Concrete Pumps
• Carpenter + Helper
Materials:
• Ready mix concrete
• Reinforcing rebars
• Plywood Sheets
Responsible Manager:
• Site engineering
Work Procedures:

 Formworks should support the loads imposed on them by the fresh


concrete together with additional stresses imposed by vibrating
equipment and by construction traffic.
 Formwork/Shuttering will be installed as per approved drawings and
secured against lateral force by concrete.
 Formwork thus erected and installed will be rigid. watertight and
dimensionally stable.
 Before placing concrete, all dirt, debris and other foreign matter shall
be removed.
 Before placing concrete, make sure all the reinforcement is ready,
cover blocks provided, all MEP installations completed and all
approvals have been taken.

13 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Reinforcing Rebar Works


 The reinforcing bars in conformity with the valid drawings shall be
used in the construction. Steel workers shall bend all rebar under
supervision of the foremen.
 These foremen have to organize bending works according to the valid
revision of related project. After that, steel fixers shall install all
reinforcing steel.
 Erection of rebar shall take place in layers from bottom to top, and the
embedded items (if exist) shall be installed at the required level.
Concrete Placement Procedure
•The concrete work shall confirm to all requirements of ECP-203-
2011 Structural use of concrete.
•No concrete shall be placed in the permanent works until the
consultant has approved the materials.
•No concrete shall be placed in any part of the permanent structure
until the consultant consent has been given in writing.
•The concrete shall be deposited as nearly as possible in its final
position. It shall be placed so as to avoid segregation of concrete and
displacement of the reinforcement, other embedded items or
formwork.
•Maximum free fall height / free drop height shall be minimized to
1.5m to avoid segregation.
•The concrete will be placed into layers not more than 600mm. or
agreed by the consultant. (The layer thickness will be controlled by
marking on the hose pipe).
•During concrete placement operations it will be ensured that ambient
temperature is 42°C while concrete temperatures 32°C.

14 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

•The cubes of concrete will be made for lab testing as per standards
and specifications (after 7 days and 28 days)

Resources & Durations

Productio No Of Duratio
Item Crew Description Quantity
n Rate Crews n (Days)
Shuttering of Carpenter +
1041m3 3 m3/day 14 25
R.C walls Assistant

Reinforcement Steel fixer +


1041m3 3 m3/day 14 25
of R.C walls Assistant

Steel Fixer + 2
Carpenter + 2
Concrete Vibrator
Pouring of R.C Operator +
150
Col./Walls/Sla Foreman + 1041m3 2 4
m3/day
b 4 Workers +
Pump + 5 Truck
Mixer (8 m3) + 2
Concrete Vibrator

15 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

8- Pouring of Ground Slab


Labor and equipment:
• Truck Mixer.
• Concrete Mixer Trucks.
• Vibrators.
• Concrete Pumps.
• Carpenter + Helper.
Materials:
• Ready mix concrete.
• Reinforcing rebars.
• Plywood Sheets.
Responsible Manager:
• Site engineer.
Work Procedures:
Erection of Formwork and Support System

 The Table formwork shall be erected . All alignments & levels


shall be checked & the formwork shall be erected.
 All alignments & levels shall be checked & verified from
established datum on the project site. Concrete Edges Shall Be
Chamfered.

16 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Reinforcing Rebar Works

 The reinforcing bars in conformity with the valid drawings shall be


used in the construction. Steel workers shall bend all rebar under
supervision of the foremen.
 These foremen have to organize bending works according to the
valid revision of related project. After that, steel fixers shall install
all reinforcing steel.
 Erection of rebar shall take place in layers from bottom to top, and
the embedded items shall be installed at the required level.
Concrete Pouring

 Ready mix concrete supplied by the ready mix concrete supplier


will be used for concreting. The design mix and materials for the
grade of concrete specified will be prepared by the ready-mix
concrete supplier's laboratory and will be approved by clients.
 Admixtures as specified in accordance with the Technical
specifications will be added to the concrete during mixing. The
concrete will be transported by transit mixer and pumped to the
locations.
 The process of compacting concrete by vibration consists
essentially of the elimination of entrapped air and forcing the
particles into a closer configuration.

17 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Resources & Durations

Crew Productio No Of Duration


Item Quantity
Description n Rate Crews (Days)
Shuttering of Carpenter + 2.5
1000m3 20 20
R.C Slab Assistant m3/day
Reinforcemen Steel fixer +
1000m3 3 m3/day 20 17
t of R.C Slab Assistant
Steel Fixer +
2 Carpenter
+ 2 Concrete
Vibrator
Pouring of Operator +
R.C Foreman + 150 2x3.5shift (24hr)
1000m3
Col./Walls/Sl 4 Workers + m3/day x8 Hrs. +8hr
ab Pump + 5
Truck Mixer
(8 m3) + 2
Concrete
Vibrator

18 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

9- Vertical Water Proofing Membrane


Purpose:
The purpose of the application of waterproofing is to prevent the water
to percolate or penetrate into any underground concrete members. When
the water penetrates into the sub-grade concrete like foundation such as:
mat foundation, footing, tie beam etc. the steel reinforcement that
embedded in the concrete would corrode due to chemical reaction
caused by water and the structure would eventually fail.
Labor and Equipment:
 Installer + Assistant.
 Wheel borrow
 Metal tape
 Torch
 knife

Materials:
 Approved water proofing
membrane.
Responsible Manager
• Site engineer.
Work Procedures:

 Any undulations or protrusions on the surface would be removed


in order to obtain smooth surface. The surface must be thoroughly
cleaned and free from dust, dirt loose materials, oil or grease.
 For vertical application, two layer of 4mm thick modified
bituminous waterproofing membrane shall be applied to all vertical
surfaces of gunited shoring or blockworks wall.
19 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

 Before applying the waterproofing membrane, concrete surfaces


shall be primed with primer recommended by the manufacturer of
the membrane but the again it should be inspected by the Engineer
24 hours after the placement.
 The extra portion of 300 mm of the horizontal membrane left shall
be turned up and wrapped on to the vertical primed surfaces. The
continuity of the membrane shall be maintained by minimum laps
of 150mm.
 The membrane on the exposed external vertical surfaces shall be
carried up to a minimum of 150 mm above the finished ground
level (i.e. side walk, parapet, etc.) and tucked into a continuous
groove provided for the same and secured firmly with approved
sealant/mastic recommended by the manufacturer of the
membrane.
 The membrane fixed on the concrete wall shall be protected from
any damage due to rebar fixing, formworks, concreting of raft,
retaining wall works with approved type protection board fixed to
the membrane.
 All areas of the membrane exposed above ground shall be
protected with appropriate flashing.
 Inspection would be submitted for approval of the Engineer.

Resources & Durations


No Of
Crew Productio Duration
Item No Quantity Crew
Description n Rate (Days)
s
Vertical
Installer +
Membran 1550m2 100m2/day 4 4
Assistant
e

20 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

10-Backfilling
Equipment:

 Loader.
 2 Plate Compactor.
 Tipper Truck.
 Labor.
Materials:
 Sand.
Responsible Manager:

 Site engineer.

Work Procedures:

 Once the waterproofing of external face of water tank is inspected and


approved by consultant the backfilling around water tank shall be
carried in 250mm thick layers and its density shall be tested. The
backfilling shall carry out up to the required grade level. During
backfilling.
 Clean the backfill site of wood, the remains of the threads, the block
and any residues.
 Accurately determine the size of the backfill.
 The backfill must be sprayed, not thick dumping as a mound.
 Avoid damaging and twisting his life and iron skewers by bending
during backfilling and stacking.
 Get smaller the more times you get smaller.

21 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

 The finished surface must be level.


 Backfilling in one go will cause slump and cracking of patio and floor
tiles and may damage drainpipes.
 Do not start backfilling before gaining adequate strength.
 Do not neglect the nooks and crannies.
Resources & Durations
No Of
Quantit Production Duratio
Item Crew Description Crew
y Rate n (Days)
s
Loader + 2 Plate
Backfillin
Compactor + Tipper 455m3 200 m3/day 2 2
g
Truck + labor

11-Formwork for Ground Floor Columns


Purpose:

 The Columns is the main items that


carry all slabs and the supports of the
slab system and transfer loads to the
foundations.
Labor and Equipment:

 Carpenter + helper.
 Steel Fixer + helper.
 Truck mixer.
 Concrete Pumps.
Material

 Ready mix concrete.


22 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

 Reinforcement rebars.
Responsible Manager
• Site engineer.
Work Procedures

 After finishing the ground slab and appearing the steel bars for the
columns, which are consists of external bars and internal bars inside the
column dimensions.
 Reinforced Concrete Columns
 Erect Formworks 3 sides G.F. Col.
 Rebar G.F. Col.
 Close Formworks Fourth side G.F. Col.
 Pouring G.F. Col.
 DE shuttering Formworks G.F. Col.

23 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Resources & Durations

Production No Of Duration
Item No Crew Description Quantity
Rate Crews (Days)
Shuttering of
Carpenter + Assistant 85m3 1.5 m3/day 5 12
R.C Columns
Reinforcement
Steel fixer +
of R.C 85m3 2 m3/day 5 9
Assistant
Columns
Steel Fixer + 2
Carpenter + 2
Concrete Vibrator
Operator + Foreman
Pouring of R.C
+ 85m3 150 m3/day 1 1
Col./Walls/Slab
4 Workers + Pump +
5 Truck Mixer (8 m3)
+ 2 Concrete
Vibrator

12-Roof Slab & Beams

24 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Purpose
The beams connect
between columns, carrying
and support roof slab and
transfer loads to columns.
Labor and Equipment

 Carpenter + helper.
 Steel Fixer + helper.
 Truck mixer.
 Concrete Pumps.
Material

 Ready mix concrete.


 Reinforcement rebars.
Responsible Manager
• Site engineer.
Work Procedures
Erection of Formwork and Support System

 The Table formwork shall be erected . All alignments & levels


shall be checked & the formwork shall be erected.
 All alignments & levels shall be checked & verified from
established datum on the project site. Concrete Edges Shall Be
Chamfered.

25 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Reinforcing Rebar Works

 The reinforcing bars in conformity with the valid drawings shall be


used in the construction. Steel workers shall bend all rebar under
supervision of the foremen.
 These foremen have to organize bending works according to the
valid revision of related project. After that, steel fixers shall install
all reinforcing steel.
 Erection of rebar shall take place in layers from bottom to top, and
the embedded items shall be installed at the required level.
Concrete Pouring

 Ready mix concrete supplied by the ready mix concrete supplier


will be used for concreting. The design mix and materials for the
grade of concrete specified will be prepared by the ready-mix
concrete supplier's laboratory and will be approved by clients.
 Admixtures as specified in accordance with the Technical
specifications will be added to the concrete during mixing. The
concrete will be transported by transit mixer and pumped to the
locations.
 The process of compacting concrete by vibration consists
essentially of the elimination of entrapped air and forcing the
particles into a closer configuration.

Resources & Durations

26 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Crew Quantit Productio No Of Duratio


Item No
Description y n Rate Crews n (Days)
Shuttering of Carpenter +
540m3 2.5 m3/day 10 22
R.C Slab Assistant

Reinforcement Steel fixer +


540m3 3 m3/day 10 18
of R.C Slab Assistant
Steel Fixer + 2
Carpenter + 2
Concrete
Vibrator
Pouring of R.C Operator +
150 2
Col./Walls/Sla Foreman + 540m3 2
m3/day x2shift
b 4 Workers +
Pump + 5 Truck
Mixer (8 m3) + 2
Concrete
Vibrator

13- Epoxy Coating

27 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Purpose: protection of concrete

Labor and Equipment:

 Installer
 Helper
Material

 Epoxy coating
Responsible Manager
• Site engineer.
Work Procedures

 Paint material shall be of the approved one in accordance with


specification. Surface preparation before Painting shall conform to
the manufacturer's instruction to each kind of paint material.
 Number of coat dry film thickness shall comply with the approved
paint schedule. Where required, final coat shall be carried out after
or almost all of the work nearby is completed to minimize damage.
Resources & Durations

Quantit Production No Of Duration


Item Crew Description
y Rate Crews (Days)
Epoxy
Painter Assistant 2200m2 25m2/day 8 11
Coating

14- Masonry Works

28 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Purpose:
Concrete blocks are Versatile, durable and strong, completely fire
resistant, excellent sound insulation. Also ideal background for dry
lining wet finishes and fixings. Inherent thermal mass acts as heat store.
These are proven and familiar building method with no risk. Widely and
readily available and Cost effective.
Labor and Equipment:

 Mason.
 Helper.
 Water level, plumb bob, chisel, concrete swivel, 3m long
Aluminum straight edge bar, steel angle 90o/45o/135o, rubber
hammer, brush, bucket, one wheel trolley.
Material:

 Blocks: Solid and Hollow Blocks.


 Sand.
 Cement.
 Water
Responsible Manager
• Site engineer.
Work Procedures

 A survey and inspection on completion of structural work for


structural element recording deviations and deficiencies, if any a
complete report of each building shall be submitted to the Engineer
prior to commencing building masonry assemblies on Foundation.

29 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

 Clean the floor, under wall course of dirt using brush. Remove
any slurry, laitance, leaving a sound concrete.
 Setting out for unit masonry work for each building in respect to
coordinates from approved shop drawing.
 Lay out walls for accurate spacing of surface bond patterns and for
accurate location of
 Wet bricks before laying, allow units to absorb water so they are
dump but not wet at the time of laying the course.
 Wet the floor under walls
 For starting course on footings spread out full mortar bed,
including areas under cell, following the approved setting of walls.
 Masonry unit will be laid with full coverage mortar on horizontal
and vertical shells and will maintain a joint thickness of 10mm
minimum and 12mm maximum for joints.
 Connection between walls and partition should be bonded, tied by
using wall angle to be nailed in the column before the succeeding
layer is laid. For a partition to be connected to an adjacent wall,
this will be done by toothing.
 Submitting “Work Inspection Request” to the consultant to get
approval on the first course. It should be signed by all concerned
related discipline for coordination purposes.
 After layout approval, courses shall be laid to comply with
specified construction tolerances, with courses accurately spaced
and coordinated with other construction. No higher than six
courses shall be laid in one day.
 At stopping and resuming work in each course, rack back one-half
running bond or one-third unit length for one third running bond,
clean exposed surfaces of set masonry and remove loose masonry
units and mortar before laying fresh masonry.

30 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

 Fill cores in hollow masonry units with mortar under bearing


plates, beams, lintel and post, door and window opening jambs.
 Leave opening for E/M embedment and fixture after approved
successful installation, complete the masonry to match the adjacent
wall. Opening for E/M embedment routing, grinder and chisel will
be used.
 Lintel beams will be casted-in-situ. Use concrete lintels minimum
depth 200mm for all openings in masonry assemblies with 200mm
minimum bearing at each jamb.
 Install mortar in joint between top of partition and the soffit after
filling gap with solid piece blocks and install compressible filler.
 Fill space between hollow metal frames and masonry solidly with
mortar.
 Clean unit masonry as work progresses by dry brushing to remove
mortar fins and smears before tooling joints.
 Remove and replace masonry units that are loose, chipped and
broken. Install new units to match adjoining units with fresh
mortar.
 Curing of masonry will be for 3 days by sprinkling of water twice
a day.
 Construction Tolerances.
 Plumb variation for vertical lines and surfaces of columns, walls,
and arises should not exceed 3mm in 3m, nor 6mm in 12m.
 Variations from level for bed joints and lines of exposed lintels,
sills, parapets, horizontal grooves should not exceed 3mm in 6m,
nor 6mm in 12 m.
 Variations of Linear Building Line for columns, walls and partition
do not exceed 6mm in 6m, nor 10mm in 12m.
 Variations in Mortar-Joint Thickness should be 3mm with a
maximum thickness of 12mm.
31 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

15- Plastering Works


Purpose:
This Method of Statement includes the following;
 Internal Portland cement plaster:
 External Portland Cement plaster:

Labor and Equipment:


 Plasterer.
 Helper.
 Plastering Accessories: Metal Lath, angle beads, special pieces for
internal angles and corner.

Material:
 Portland cement.
 Sand.

Responsible Manager
 Site engineer.

Work Procedures
 Clean the surface and remove any dust, contaminated materials on
plaster bases and substrates for direct application of plaster,
removing loose material and substances that may impair the work.
Form ties and other obstruction shall be removed or trimmed back
even with the surface of the solid base.

32 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

 Dissimilar Backgrounds: where rendering is to be continued


without break across joints between dissimilar solid backgrounds
which are in the same plane, cover joints with 200mm wide
galvanized steel lathing as specified & approved fixed with
corrosion resistant fasteners at not more than 600mm centers along
both edges, apply mesh over electro-mechanical embedded
conduits.
 Apply forcefully dash coat on concrete and concrete masonry
surfaces indicated for direct plaster application. Dash coat is to
cover full surface to be plastered and is to provide rough surface of
sharp protrusions ranging 3.0mm and 5.0mm. Dash-Coat Mix: 2
volume parts Portland cement to 3 volume parts fine sand, 1 part
bonding agent to 3 part clean water mixed to a mushy-paste
consistency shall be left untroweled, undisturbed and moist cured
for at least 24 hours after application and before plastering.
 Install temporary grounds and screeds to ensure accurate rodding
of plaster to true surfaces. Check the straightness in each corner
and add grout to hold the external corner beads in correct and
internal position to be fixed using corrosion resistant fasteners.
 Before plastering starts, dampen, by spraying water concrete dash
coat surfaces that are to receive plaster with clean water.
 All plaster shall be prepared in a mechanical mixer mix 1:5 (1 part
cement and 5 part sand) using sufficient water to produce a
workable consistency. Mix fiber 0.6 kg/m3 of the mortar or plaster
by first mixing with some water (30%). After all the ingredients
have been added including the remaining mixing water, the plaster
should be mixed for a further few minutes until uniform fibre
dispersion. Plaster not used within 1.5h from start of mixing shall
be discarded.
 The second coat shall be applied with sufficient material and
pressure to ensure tight contact with dash coat.

33 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

 The surface of the second coat shall be brought to a true, even


plane with a rod or straightedge, filling surface defects in place
with plaster.
 Applied plaster shall be floated as smooth as possible and then
steel-troweled. Steel troweling shall be delayed as long as possible
and used only to eliminate the uneven points and to force
aggregate particles into the plaster surface.
 Each plaster coat shall be applied to an entire wall or ceiling panel
without interruption to avoid cold joints and abrupt changes in the
uniform appearance of succeeding coats. Wet plaster shall abut set
plaster at naturally occurring interruptions in the plane of the
plaster, such as corner angles, openings and control joints where
this is possible.
 Make internal angles and corners square.
 Finished grooves shall be neat, of uniform width and depth, sharp
straight edges and exact vertical and horizontal lines. Elevation
grooves shall be cut before plaster sets by using molded guide or
wooden strip and fixing it in temporary grout and screed.
Regarding recessed, follow the Work Procedures same as grooves.
 Form cornices by plastering additional coats against pre-formed
wood templates fixed onto plastered elevation. Make form wood
templates to shapes, dimensions and projection indicated on
drawings. Apply additional under coats in thickness not more that
10mm until obtaining required projection. Final finishes refer to
item D.
 Plaster should not deviate more than plus or minus 3mm in 3m
from a true plane in finished plaster surfaces, as measured by a 3-
m straight edge placed in any location on surface.

34 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

16- Painting Works


Purpose:
Painting works will be carried out after completion of preparatory works
such as the installation of block, plaster preparation, and plaster works.
Works shall be carried out in compliance with the drawings, project
specifications, and materials.
Labor and Equipment:
 Wheel borrow

 Drip tray

 Drill machine

 Pail

 Sand paper

 Rug cloth

Material:
 Approved paints

Responsible Manager
 Site engineer.
Work Procedures
1. Mock-up

35 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station

Mock up sample would be made for selection and approval of the


Engineer prior to commencement of the works.
2. Preparation
Hardware materials which are already fixed and not to be painted shall
be removed. Removal if not possible, it shall be covered/protected
appropriately before surface preparation and painting will commence.
Clean and prepare concrete or cement plaster surfaces to be painted.
Efflorescence, chalk, dust, dirt, grease and oils shall be removed.
The surface of the area to be painted would be prepared by removing
loose particles, blemishes, and deleterious materials by way of sanding.
3. Paint Application
The paint system would be emulsion paint for internal but to be
approved by the Engineer. The surface to be painted when prepared one
coat of paint to be applied as primer. Curing would be made by drying
until 4 hours is attained prior to the succeeding coat to be applied.
Two coats of Stucco would be applied after the primer has reached its
curing period. But each coat shall have an interval time of 4 hours for
curing. Before the application of second coat stucco sanding would be
done for cleaning and removing of splattered, blemishes and stains on
the painted surface.
Then two coats of final paint would be applied as per the approved
color.
For working at height, fixed and movable scaffolding would be erected
as per area requirements. Scaffolding when erected shall be inspected
with Safety officer prior to usage. Operatives will be inductive before
working at site. Pre-start meeting would be conducted before the start of
painting activities and tool box meeting would be regularly conducted
by safety officer for all concern operatives.
Inspection Request to be submitted for checking and approval of the
Engineer.

36 | P a g e