1- Surveying works
Purpose:
Site engineering
Surveyor
Labor and equipment:
Surveyor
Total station
Work Procedures:
1|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
2- Excavation Works
Purpose:
Excavator/JCB
Dump Truck used for
disposal of debris
2 Labors
Responsible Manager:
• Site engineering
Work Procedures:
2|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
No Of
Production Duration
Item No Crew Description Quantity Crew
Rate (Days)
s
Excavator + 2 Tipper
Excavation Truck + Surveyor + 11893m3 400 m3/day 2 15
Labor
Resources & Duration
3- Soil Replacement
Purpose:
Replacing the existing soil with another soil that has special
specifications. The replacement process is carried out in an
engineering way to reach soil suitable for foundation according to the
design.
Labor:
Loader
2 Plate Compactor
Tipper Truck
labor
Materials:
Sand
Responsible Manager:
• Site engineering
3|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Work Procedures:
4|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
4- P.C. Foundation
Purpose:
Make a leveling layer under the
foundations. It forms a strong
layer under foundations to
ensure that the load is
distributed evenly in all
directions. Soil isolation from
reinforced concrete foundations.
Reducing the effect of moisture
on rebar.
Labor and equipment:
• Concrete Mixer Trucks
• Vibrators
• Concrete Pumps
• Carpenter + Helper
• Surveyor
Materials:
Ready mix concrete
Responsible Manager:
• Site engineering
• Surveyor
5|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Work Procedures:
• The bottom of the excavation should be dry and compacted to a
uniform level before pouring the 300 mm thick or as per drawings
Surveyor to complete markings and layout of water tank location.
Submit the inspection request prior to fix the formworks.
Clean the area and remove waste materials prior to fixing the
formworks. Formworks shall comply with relevant specifications and
standards.
Pouring of concrete for the p.c. foundation of the water tank using
concrete pump after the consultant approval of the previous activities.
Arrange and use vibrators during concreting works.
Provide necessary curing and removal of formworks for concrete
water tank and apply the waterproofing as per applicable procedure.
Clean and remove all debris prior to start the waterproofing
application.
Apply the waterproofing membrane as per drawings and the
procedure for application of waterproofing.
6|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
No Of
Production Duration
Item No Crew Description Quantity Crew
Rate (Days)
s
Shuttering of
Carpenter + Assistant 540m3 30 m3/day 4 5
P.C
2 Carpenter + 2
Concrete Vibrator
Pouring of Operator + Foreman +
540m3 150 m3/day 2 2
P.C 4 Workers + Pump +
5 Truck Mixer (8 m3)
+ 2 Concrete Vibrator
Horizontal
Installer + Assistant 3500m2 100m2/day 5 7
Membrane
Torch
knife
Materials:
Approved water proofing membrane.
Responsible Manager
• Site engineer.
Work Procedures:
8|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Repeat till the entire length of the membrane is bonded firmly onto
the surface then the second membrane is laid in the same way with
an overlap of 150mm at the end and 100mm at the side.
An extra length of minimum 300mm of the horizontal membrane
shall be left to carry up the vertical surface to maintain continuity
of the membrane and be protected as above.
Before applying the waterproofing membrane, concrete surfaces
shall be primed with primer recommended by the manufacturer of
the membrane but the again it should be inspected by the Engineer
24 hours after the placement.
The extra portion of 300 mm of the horizontal membrane left shall
be turned up and wrapped on to the vertical primed surfaces. The
continuity of the membrane shall be maintained by minimum laps
of 150mm.
All areas of the membrane exposed above ground shall be
protected with appropriate flashing.
Inspection would be submitted for approval of the Engineer.
Before fixing of steel reinforcement for foundation, the membrane
shall be covered by one layer of polythene sheet and poured with
50 mm thick layer of cement sand screed.
9|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
10 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
11 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
12 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
13 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
14 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
•The cubes of concrete will be made for lab testing as per standards
and specifications (after 7 days and 28 days)
Productio No Of Duratio
Item Crew Description Quantity
n Rate Crews n (Days)
Shuttering of Carpenter +
1041m3 3 m3/day 14 25
R.C walls Assistant
Steel Fixer + 2
Carpenter + 2
Concrete Vibrator
Pouring of R.C Operator +
150
Col./Walls/Sla Foreman + 1041m3 2 4
m3/day
b 4 Workers +
Pump + 5 Truck
Mixer (8 m3) + 2
Concrete Vibrator
15 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
16 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
17 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
18 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Materials:
Approved water proofing
membrane.
Responsible Manager
• Site engineer.
Work Procedures:
20 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
10-Backfilling
Equipment:
Loader.
2 Plate Compactor.
Tipper Truck.
Labor.
Materials:
Sand.
Responsible Manager:
Site engineer.
Work Procedures:
21 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Carpenter + helper.
Steel Fixer + helper.
Truck mixer.
Concrete Pumps.
Material
Reinforcement rebars.
Responsible Manager
• Site engineer.
Work Procedures
After finishing the ground slab and appearing the steel bars for the
columns, which are consists of external bars and internal bars inside the
column dimensions.
Reinforced Concrete Columns
Erect Formworks 3 sides G.F. Col.
Rebar G.F. Col.
Close Formworks Fourth side G.F. Col.
Pouring G.F. Col.
DE shuttering Formworks G.F. Col.
23 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Production No Of Duration
Item No Crew Description Quantity
Rate Crews (Days)
Shuttering of
Carpenter + Assistant 85m3 1.5 m3/day 5 12
R.C Columns
Reinforcement
Steel fixer +
of R.C 85m3 2 m3/day 5 9
Assistant
Columns
Steel Fixer + 2
Carpenter + 2
Concrete Vibrator
Operator + Foreman
Pouring of R.C
+ 85m3 150 m3/day 1 1
Col./Walls/Slab
4 Workers + Pump +
5 Truck Mixer (8 m3)
+ 2 Concrete
Vibrator
24 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Purpose
The beams connect
between columns, carrying
and support roof slab and
transfer loads to columns.
Labor and Equipment
Carpenter + helper.
Steel Fixer + helper.
Truck mixer.
Concrete Pumps.
Material
25 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
26 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
27 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Installer
Helper
Material
Epoxy coating
Responsible Manager
• Site engineer.
Work Procedures
28 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Purpose:
Concrete blocks are Versatile, durable and strong, completely fire
resistant, excellent sound insulation. Also ideal background for dry
lining wet finishes and fixings. Inherent thermal mass acts as heat store.
These are proven and familiar building method with no risk. Widely and
readily available and Cost effective.
Labor and Equipment:
Mason.
Helper.
Water level, plumb bob, chisel, concrete swivel, 3m long
Aluminum straight edge bar, steel angle 90o/45o/135o, rubber
hammer, brush, bucket, one wheel trolley.
Material:
29 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Clean the floor, under wall course of dirt using brush. Remove
any slurry, laitance, leaving a sound concrete.
Setting out for unit masonry work for each building in respect to
coordinates from approved shop drawing.
Lay out walls for accurate spacing of surface bond patterns and for
accurate location of
Wet bricks before laying, allow units to absorb water so they are
dump but not wet at the time of laying the course.
Wet the floor under walls
For starting course on footings spread out full mortar bed,
including areas under cell, following the approved setting of walls.
Masonry unit will be laid with full coverage mortar on horizontal
and vertical shells and will maintain a joint thickness of 10mm
minimum and 12mm maximum for joints.
Connection between walls and partition should be bonded, tied by
using wall angle to be nailed in the column before the succeeding
layer is laid. For a partition to be connected to an adjacent wall,
this will be done by toothing.
Submitting “Work Inspection Request” to the consultant to get
approval on the first course. It should be signed by all concerned
related discipline for coordination purposes.
After layout approval, courses shall be laid to comply with
specified construction tolerances, with courses accurately spaced
and coordinated with other construction. No higher than six
courses shall be laid in one day.
At stopping and resuming work in each course, rack back one-half
running bond or one-third unit length for one third running bond,
clean exposed surfaces of set masonry and remove loose masonry
units and mortar before laying fresh masonry.
30 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Material:
Portland cement.
Sand.
Responsible Manager
Site engineer.
Work Procedures
Clean the surface and remove any dust, contaminated materials on
plaster bases and substrates for direct application of plaster,
removing loose material and substances that may impair the work.
Form ties and other obstruction shall be removed or trimmed back
even with the surface of the solid base.
32 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
33 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
34 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
Drip tray
Drill machine
Pail
Sand paper
Rug cloth
Material:
Approved paints
Responsible Manager
Site engineer.
Work Procedures
1. Mock-up
35 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Pump Station
36 | P a g e