Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
2- Surveying works
Purpose
Responsible Manager:
Site engineering
Surveyor
Labor and Equipment::
Surveyor
Total station
Work Procedures:
2|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
3- Excavation Works
Purpose:
Excavator/JCB.
Dump Truck used for
disposal of debris.
Labors.
Responsible Manager:
• Site engineer.
Work Procedures:
3|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
4- P.C Foundation
Purpose:
Make a leveling layer under the
foundations. It forms a strong
layer under foundations to
ensure that the load is distributed
evenly in all directions. Soil
isolation from reinforced
concrete foundations. Reducing
the effect of moisture on rebar.
Labor and Equipment:
• Concrete Mixer Trucks.
• Vibrators.
• Concrete Pumps.
4|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
• Carpenter + Helper.
• Surveyor.
Materials:
• Ready mix concrete
Responsible Manager:
• Site engineer.
• Surveyor.
Work Procedures:
• The bottom of the excavation should be dry and compacted to a
uniform level before pouring the 300 mm thick or as per drawings
Surveyor to complete markings and layout of water tank location.
Submit the inspection request prior to fix the formworks.
Clean the area and remove waste materials prior to fixing the
formworks. Formworks shall comply with relevant specifications and
standards. Submit the work inspection request after the formwork
installation prior to pouring the concrete.
Pouring of concrete for the p.c. foundation of the water tank using
concrete pump after the consultant approval of the previous activities.
Arrange and use vibrators during concreting works.
Provide necessary curing and removal of formworks for concrete
water tank and apply the waterproofing as per applicable Work
Procedures:.
Clean and remove all debris prior to start the waterproofing
application.
5|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
Production No Of Duration
Item Crew Description Quantity
Rate Crews (Days)
Shuttering of
Carpenter + Assistant 735m3 30 m3/day 5 5
P.C
2 Carpenter + 2
Concrete Vibrator
Pouring of Operator + Foreman +
735m3 150 m3/day 2 3
P.C 4 Workers + Pump +
5 Truck Mixer (8 m3)
+ 2 Concrete Vibrator
Horizontal
Installer + Assistant 2100m2 100m2/day 4 6
Membrane
6|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
Materials:
Approved water proofing membrane.
Responsible Manager
• Site engineer.
Work Procedures:
7|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
8|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
9|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
Work Procedures:
•Surveyor to complete markings and layout of water tank location.
•Steel fixer will fix the reinforcement in accordance to the drawings
issued for construction. Provide concrete covering for the
reinforcement based on the approved drawings.
•Submit the inspection request prior to fix the formworks.
•Install the water stop as per drawings and approval by the consultant.
•Check the Plumbing Pipe Sleeves for water tank and other MEP
sleeves as applicable according to the coordination drawings. The
contractor should not fix the formworks without the approval from
QA/QC and consultant and inspection request to be signed by both
parties.
• Clean the area and remove waste materials prior to fixing the
formworks. Formworks shall comply with relevant specifications and
standards. Submit the work inspection request after the formwork
installation prior to pouring the concrete.
• Pouring of concrete for the Raft foundation of the water tank using
concrete pump after the consultant approval of the previous activities.
• Arrange and vibrators during concreting works.
• Provide necessary curing and removal of formworks for concrete
water tank as per tender specs.
10 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
Productio No Of Duratio
Item Crew Description Quantity
n Rate Crews n (Days)
Shuttering of
R.C Raft Carpenter + Assistant 1808m3 30 m3/day 5 12
Foundation
Reinforcement
of R.C Raft Steel fixer + Assistant 1808m3 7 m3/day 12 22
Foundation
2x 3x8
Hrs. x
Steel Fixer + 2 2days
Carpenter + 2 يومين
Concrete Vibrator صب
Pouring of R.C
Operator + Foreman 150 متواصل
Footing/Raft 1808m3 2
+ m3/day
foundation 3
4 Workers + Pump +
5 Truck Mixer (8 m3) ورديات
+ 2 Concrete Vibrator عمالة
11 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
12 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
•Before placing concrete, all dirt, debris and other foreign matter shall
be removed.
•Before placing concrete, make sure all the reinforcement is ready,
cover blocks provided, all MEP installations completed and all
approvals have been taken.
Reinforcing Rebar Works:
The reinforcing bars in conformity with the valid drawings shall be
used in the construction. Steel workers shall bend all rebar under
supervision of the foremen.
These foremen have to organize bending works according to the valid
revision of related project. After that steel fixers shall install all
reinforcing steel.
Erection of rebar shall take place in layers from bottom to top, and the
embedded items (if exist) shall be installed at the required level.
13 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
The concrete will be placed into layers not more than 600mm. or
agreed by the consultant. (The layer thickness will be controlled by
marking on the hose pipe).
During concrete placement operations it will be ensured that
ambient temperature is 42°C while concrete temperatures 32°C.
The cubes of concrete will be made for lab testing as per standards
and specifications (after 7 days and 28 days)
No Of
Productio Duratio
Item Crew Description Quantity Crew
n Rate n (Days)
s
Shuttering of
Carpenter + Assistant 1041m3 3 m3/day 14 25
R.C walls
Reinforcement
Steel fixer + Assistant 1041m3 3 m3/day 14 25
of R.C walls
Steel Fixer + 2
Carpenter + 2
Concrete Vibrator
Pouring of R.C Operator + Foreman 150
1041m3 2 4
Col./Walls/Slab + m3/day
4 Workers + Pump +
5 Truck Mixer (8 m3)
+ 2 Concrete Vibrator
14 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
15 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
Concrete Pouring
16 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
Productio No Of Duration
Item Crew Description Quantity
n Rate Crews (Days)
Shuttering of Carpenter +
1000m3 2.5 m3/day 20 20
R.C Slab Assistant
Reinforcement Steel fixer +
1000m3 3 m3/day 20 17
of R.C Slab Assistant
Steel Fixer + 2
Carpenter + 2
Concrete Vibrator
Pouring of R.C Operator +
2X3.5X (24hr)
Col./Walls/Sla Foreman + 1000m3 150 m3/day
8 Hrs. +8hr
b 4 Workers + Pump
+ 5 Truck Mixer (8
m3) + 2 Concrete
Vibrator
Resources & Durations
17 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
Materials:
Approved water proofing
membrane.
Responsible Manager
• Site engineer.
Work Procedures:
18 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
e
10- Backfilling
Labor and Equipment:
Loader.
2 Plate Compactor.
Tipper Truck.
Labor.
Materials:
Sand.
Responsible Manager
• Site engineer.
Work Procedures:
20 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank
No Of
Quantit Production Duratio
Item Crew Description Crew
y Rate n (Days)
s
Loader + 2 Plate
Backfillin
Compactor + Tipper 455m3 200 m3/day 2 2
g
Truck + labor