Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting

station No. (5) In Badr City.


Construction Method for Underground Water Tank

1- Site planning and preparation

Purpose

 Remove all obstacles on


the site, such as power
cables
 Determining the location of
cement and iron caravan
that are stored

Responsible Manager

 Contractor
 Engineer of the owner

Work Procedures:

 Determining the location of the project according to the general


site drawing, on which the location of each facility shown, its
dimensions, its increases, and its relationship with other facilities.
 Actual traffic on every small and large site and recording notes so
that the site delivery record includes all details and limits future
problems.

1|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

2- Surveying works
Purpose

 Determined to complete markings,


gridlines, level and layout of plain
concrete for water tank location.

Responsible Manager:

 Site engineering
 Surveyor
Labor and Equipment::

 Surveyor
 Total station
Work Procedures:

 Before work starts, survey department will establish baselines and


benchmarks from which co-ordinates and elevations will be taken to
set out the foundation works.

 A starting point is selected and must be in a security position for the


device and allow a clear view of the points
 surveyor directs the binoculars to any direction and assumes the
direction of the north, and then raises the project points and natural
phenomena.
 Survey the levels of the project: the surveyor will raise the levels
required by the project and before exiting the surveyor station to the
site must be confirmed

2|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

3- Excavation Works

Purpose:

 excavate soil under the


ground tank by using
excavator to excavate
soil with a depth of
4.4m
Labor and Equipment:

 Excavator/JCB.
 Dump Truck used for
disposal of debris.
 Labors.
Responsible Manager:
• Site engineer.
Work Procedures:

 Excavations will generally be executed in open cut to the size,


slope and elevation shown on the construction design calculations
 Survey will verify set out and check edge slope and bottom
foundation level of excavation.
 Excavation will be carried out with excavator and the excavated
material loaded directly into dump truck and transported to
temporary stockpile area.

3|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

 The final bottom of foundation level will be inspected by quality


control (QC) and compacted as per design requirements before
pouring P.C concrete.
Resources & Duration
No Of
Production Duration
Item No Crew Description Quantity Crew
Rate (Days)
s
Excavator + 2 Tipper
Excavation Truck + Surveyor + 10309m3 400 m3/day 2 13
Labor

4- P.C Foundation
Purpose:
Make a leveling layer under the
foundations. It forms a strong
layer under foundations to
ensure that the load is distributed
evenly in all directions. Soil
isolation from reinforced
concrete foundations. Reducing
the effect of moisture on rebar.
Labor and Equipment:
• Concrete Mixer Trucks.
• Vibrators.
• Concrete Pumps.

4|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

• Carpenter + Helper.
• Surveyor.
Materials:
• Ready mix concrete
Responsible Manager:
• Site engineer.
• Surveyor.
Work Procedures:
• The bottom of the excavation should be dry and compacted to a
uniform level before pouring the 300 mm thick or as per drawings
 Surveyor to complete markings and layout of water tank location.
 Submit the inspection request prior to fix the formworks.
 Clean the area and remove waste materials prior to fixing the
formworks. Formworks shall comply with relevant specifications and
standards. Submit the work inspection request after the formwork
installation prior to pouring the concrete.
 Pouring of concrete for the p.c. foundation of the water tank using
concrete pump after the consultant approval of the previous activities.
 Arrange and use vibrators during concreting works.
 Provide necessary curing and removal of formworks for concrete
water tank and apply the waterproofing as per applicable Work
Procedures:.
 Clean and remove all debris prior to start the waterproofing
application.

5|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

 Apply the waterproofing membrane as per drawings and the Work


Procedures: for application of waterproofing

Resources & Duration

Production No Of Duration
Item Crew Description Quantity
Rate Crews (Days)
Shuttering of
Carpenter + Assistant 735m3 30 m3/day 5 5
P.C
2 Carpenter + 2
Concrete Vibrator
Pouring of Operator + Foreman +
735m3 150 m3/day 2 3
P.C 4 Workers + Pump +
5 Truck Mixer (8 m3)
+ 2 Concrete Vibrator
Horizontal
Installer + Assistant 2100m2 100m2/day 4 6
Membrane

6|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

5- Horizontal Water Proofing Membrane


Purpose:
The purpose of the application of waterproofing is to prevent the water
to percolate or penetrate into any underground concrete members. When
the water penetrates into the sub-grade concrete like foundation such as:
mat foundation, footing, tie beam etc. the steel reinforcement that
embedded in the concrete would corrode due to chemical reaction
caused by water and the structure would eventually fail.
Labor and Equipment:
 Installer + Assistant.
 Wheel borrow
 Metal tape
 Torch
 knife

Materials:
 Approved water proofing membrane.
Responsible Manager
• Site engineer.
Work Procedures:

 Any undulations or protrusions on the surface would be removed


in order to obtain smooth surface. The surface must be thoroughly
cleaned and free from dust, dirt loose materials, oil or grease.
 For horizontal waterproofing membrane application. Two layer of
4mm thick bituminous membrane shall be laid fully torched on
blinding concrete with minimum of 100m end laps and 150mm
side laps.

7|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

 The blinding surface shall be primed with the primer


recommended by the manufacturer of the membrane prior to
placing the membrane. Prior to succeeding works the applied
primer shall be inspected by the Engineer 24 hours after the
placement.
 Waterproofing membrane installation shall be performed using
cylinder fed propane gas torch, trowel to seal the seams of the
membrane and knife for cutting.
 The membrane is then placed in the correct torching on position
then re-rolled for about half of its length without changing its
orientation.
 The membrane is then un-rolled again and torched on pressing the
melted area against the substrate.
 Repeat till the entire length of the membrane is bonded firmly onto
the surface then the second membrane is laid in the same way with
an overlap of 150mm at the end and 100mm at the side.
 An extra length of minimum 300mm of the horizontal membrane
shall be left to carry up the vertical surface to maintain continuity
of the membrane and be protected as above.
 Before applying the waterproofing membrane, concrete surfaces
shall be primed with primer recommended by the manufacturer of
the membrane but the again it should be inspected by the Engineer
24 hours after the placement.
 The extra portion of 300 mm of the horizontal membrane left shall
be turned up and wrapped on to the vertical primed surfaces. The
continuity of the membrane shall be maintained by minimum laps
of 150mm.
 All areas of the membrane exposed above ground shall be
protected with appropriate flashing.
 Inspection would be submitted for approval of the Engineer.

8|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

 Before fixing of steel reinforcement for foundation, the membrane


shall be covered by one layer of polythene sheet and poured with
50 mm thick layer of cement sand screed.

Resources & Durations

Crew Productio No Of Duration


Item No Quantity
Description n Rate Crews (Days)
Vertical
Installer +
Membran 2000m2 100m2/day 4 5
Assistant
e

6- R.c. Raft Foundation


Labor and Equipment:
• Concrete Mixer Trucks.
• Vibrators.
• Concrete Pumps.
• Carpenter + Helper.
• Surveyor.
Materials:
• Ready mix concrete.
• Reinforcing rebars.
• Plywood Sheets.
Responsible Manager:
• Site engineer.
• Surveyor.

9|Page
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

Work Procedures:
•Surveyor to complete markings and layout of water tank location.
•Steel fixer will fix the reinforcement in accordance to the drawings
issued for construction. Provide concrete covering for the
reinforcement based on the approved drawings.
•Submit the inspection request prior to fix the formworks.
•Install the water stop as per drawings and approval by the consultant.
•Check the Plumbing Pipe Sleeves for water tank and other MEP
sleeves as applicable according to the coordination drawings. The
contractor should not fix the formworks without the approval from
QA/QC and consultant and inspection request to be signed by both
parties.
• Clean the area and remove waste materials prior to fixing the
formworks. Formworks shall comply with relevant specifications and
standards. Submit the work inspection request after the formwork
installation prior to pouring the concrete.
• Pouring of concrete for the Raft foundation of the water tank using
concrete pump after the consultant approval of the previous activities.
• Arrange and vibrators during concreting works.
• Provide necessary curing and removal of formworks for concrete
water tank as per tender specs.

10 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

Resources & Durations

Productio No Of Duratio
Item Crew Description Quantity
n Rate Crews n (Days)
Shuttering of
R.C Raft Carpenter + Assistant 1808m3 30 m3/day 5 12
Foundation

Reinforcement
of R.C Raft Steel fixer + Assistant 1808m3 7 m3/day 12 22
Foundation

2x 3x8
Hrs. x
Steel Fixer + 2 2days
Carpenter + 2 ‫يومين‬
Concrete Vibrator ‫صب‬
Pouring of R.C
Operator + Foreman 150 ‫متواصل‬
Footing/Raft 1808m3 2
+ m3/day
foundation 3
4 Workers + Pump +
5 Truck Mixer (8 m3) ‫ورديات‬
+ 2 Concrete Vibrator ‫عمالة‬

11 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

7- Formwork for water tank walls


Labor and Equipment:
• Truck Mixer
• Concrete Mixer Trucks
• Vibrators
• Concrete Pumps
• Carpenter + Helper
Materials:
• Ready mix concrete
• Reinforcing rebars
• Plywood Sheets
Responsible Manager
• Site engineering
Work Procedures::
•Formworks should support the loads imposed on them by the fresh
concrete together with additional stresses imposed by vibrating
equipment and by construction traffic.
•Formwork/Shuttering will be installed as per approved drawings and
secured against lateral force by concrete.
•Formwork thus erected and installed will be rigid. watertight and
dimensionally stable.

12 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

•Before placing concrete, all dirt, debris and other foreign matter shall
be removed.
•Before placing concrete, make sure all the reinforcement is ready,
cover blocks provided, all MEP installations completed and all
approvals have been taken.
Reinforcing Rebar Works:
 The reinforcing bars in conformity with the valid drawings shall be
used in the construction. Steel workers shall bend all rebar under
supervision of the foremen.
 These foremen have to organize bending works according to the valid
revision of related project. After that steel fixers shall install all
reinforcing steel.
 Erection of rebar shall take place in layers from bottom to top, and the
embedded items (if exist) shall be installed at the required level.

Concrete Placement Work Procedures:


 The concrete work shall confirm to all requirements of ECP-203-
2011 Structural use of concrete.
 No concrete shall be placed in the permanent works until the
consultant has approved the materials.
 No concrete shall be placed in any part of the permanent structure
until the consultant consent has been given in writing.
 The concrete shall be deposited as nearly as possible in its final
position. It shall be placed so as to avoid segregation of concrete
and displacement of the reinforcement, other embedded items or
formwork.
 Maximum free fall height / free drop height shall be minimized to
1.5m to avoid segregation.

13 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

 The concrete will be placed into layers not more than 600mm. or
agreed by the consultant. (The layer thickness will be controlled by
marking on the hose pipe).
 During concrete placement operations it will be ensured that
ambient temperature is 42°C while concrete temperatures 32°C.
 The cubes of concrete will be made for lab testing as per standards
and specifications (after 7 days and 28 days)

Resources & Durations

No Of
Productio Duratio
Item Crew Description Quantity Crew
n Rate n (Days)
s
Shuttering of
Carpenter + Assistant 1041m3 3 m3/day 14 25
R.C walls

Reinforcement
Steel fixer + Assistant 1041m3 3 m3/day 14 25
of R.C walls

Steel Fixer + 2
Carpenter + 2
Concrete Vibrator
Pouring of R.C Operator + Foreman 150
1041m3 2 4
Col./Walls/Slab + m3/day
4 Workers + Pump +
5 Truck Mixer (8 m3)
+ 2 Concrete Vibrator

14 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

8- Pouring of roof slab


Labor and Equipment:
• Truck Mixer.
• Concrete Mixer Trucks .
• Vibrators.
• Concrete Pumps.
• Carpenter + Helper.
Materials:
• Ready mix concrete.
• Reinforcing rebars.
• Plywood Sheets.
Responsible Manager:
• Site engineer.
Work Procedures:
Erection of Formwork and Support System

 The Table formwork shall be erected . All alignments & levels


shall be checked & The formwork shall be erected.
 All alignments & levels shall be checked & verified from
established datum on the project site. Concrete Edges Shall Be
Chamfered.

15 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

Reinforcing Rebar Works

 The reinforcing bars in conformity with the valid drawings shall be


used in the construction. Steel workers shall bend all rebar under
supervision of the foremen.
 These foremen have to organize bending works according to the
valid revision of related project. After that steel fixers shall install
all reinforcing steel.
 Erection of rebar shall take place in layers from bottom to top, and
the embedded items shall be installed at the required level.

Concrete Pouring

 Ready mix concrete supplied by the ready mix concrete supplier


will be used for concreting. The design mix and materials for the
grade of concrete specified will be prepared by the ready-mix
concrete supplier's laboratory and will be approved by clients.
 Admixtures as specified in accordance with the Technical
specifications will be added to the concrete during mixing. The
concrete will be transported by transit mixer and pumped to the
locations.
 The process of compacting concrete by vibration consists
essentially of the elimination of entrapped air and forcing the
particles into a closer configuration

16 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

Productio No Of Duration
Item Crew Description Quantity
n Rate Crews (Days)
Shuttering of Carpenter +
1000m3 2.5 m3/day 20 20
R.C Slab Assistant
Reinforcement Steel fixer +
1000m3 3 m3/day 20 17
of R.C Slab Assistant
Steel Fixer + 2
Carpenter + 2
Concrete Vibrator
Pouring of R.C Operator +
2X3.5X (24hr)
Col./Walls/Sla Foreman + 1000m3 150 m3/day
8 Hrs. +8hr
b 4 Workers + Pump
+ 5 Truck Mixer (8
m3) + 2 Concrete
Vibrator
Resources & Durations

17 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

9- Vertical Water Proofing Membrane


Purpose:
The purpose of the application of waterproofing is to prevent the water
to percolate or penetrate into any underground concrete members. When
the water penetrates into the sub-grade concrete like foundation such as:
mat foundation, footing, tie beam etc. the steel reinforcement that
embedded in the concrete would corrode due to chemical reaction
caused by water and the structure would eventually fail.
Labor and Equipment:
 Installer + Assistant.
 Wheel borrow
 Metal tape
 Torch
 knife

Materials:
 Approved water proofing
membrane.
Responsible Manager
• Site engineer.
Work Procedures:

 Any undulations or protrusions on the surface would be removed


in order to obtain smooth surface. The surface must be thoroughly
cleaned and free from dust, dirt loose materials, oil or grease.
 An extra length of minimum 300mm of the horizontal membrane
shall be left to carry up the vertical surface to maintain continuity
of the membrane and be protected as above.

18 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

 For vertical application, two layer of 4mm thick modified


bituminous waterproofing membrane shall be applied to all vertical
surfaces of gunited shoring or blockworks wall.
 Before applying the waterproofing membrane, concrete surfaces
shall be primed with primer recommended by the manufacturer of
the membrane but the again it should be inspected by the Engineer
24 hours after the placement.
 The extra portion of 300 mm of the horizontal membrane left shall
be turned up and wrapped on to the vertical primed surfaces. The
continuity of the membrane shall be maintained by minimum laps
of 150mm.
 The membrane on the exposed external vertical surfaces shall be
carried up to a minimum of 150 mm above the finished ground
level (i.e. side walk, parapet, etc.) and tucked into a continuous
groove provided for the same and secured firmly with approved
sealant/mastic recommended by the manufacturer of the
membrane.
 The membrane fixed on the gunited or concrete wall shall be
protected from any damage due to rebar fixing, formworks,
concreting of raft, retaining wall works with approved type
protection board fixed to the membrane.
 All areas of the membrane exposed above ground shall be
protected with appropriate flashing.
 Inspection would be submitted for approval of the Engineer.

Resources & Durations


No Of
Crew Productio Duration
Item No Quantity Crew
Description n Rate (Days)
s
Vertical Installer +
(50+40)x2x4.1=738m2 100m2/day 2 4
Membran Assistant
19 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

e
10- Backfilling
Labor and Equipment:

 Loader.
 2 Plate Compactor.
 Tipper Truck.
 Labor.
Materials:
 Sand.
Responsible Manager
• Site engineer.
Work Procedures:

 Once the waterproofing of external face of water tank is inspected


and approved by consultant the backfilling around water tank shall
be carried in 250mm thick layers and its density shall be tested.
The backfilling shall carry out up to the required grade level.
During backfilling.
 Clean the backfill site of wood, the remains of the threads, the
block and any residues.
 Accurately determine the size of the backfill.
 The backfill must be sprayed, not thick dumping as a mound.
 Avoid damaging and twisting his life and iron skewers by bending
during backfilling and stacking.
 Get smaller the more times you get smaller.
 The finished surface must be level.

20 | P a g e
Project: Lifting station number (4) and the Carrier line, DN1600 mm, to lifting
station No. (5) In Badr City.
Construction Method for Underground Water Tank

 Backfilling in one go will cause slump and cracking of patio and


floor tiles and may damage drainpipes.
 Do not start backfilling before gaining adequate strength.
 Do not neglect the nooks and crannies.
Resources & Durations

No Of
Quantit Production Duratio
Item Crew Description Crew
y Rate n (Days)
s
Loader + 2 Plate
Backfillin
Compactor + Tipper 455m3 200 m3/day 2 2
g
Truck + labor

21 | P a g e