Professional Documents
Culture Documents
APPLICATION WORK
PROCEDURE | METHOD
STATEMENT
1 PURPOSE.
2 SCOPE.
3 APPLICABLE DOCUMENTS.
4 MANPOWER.
5 TOOLS AND EQUIPMENT.
6 GENERAL REQUIREMENTS.
7 METHODS/PROCEDURES.
8 QUALITY CONTROL.
9 SAFETY ACTION PLAN.
10 ATTACHMENT.
EPOXY GROUTING
APPLICATION WORK
PROCEDURE | METHOD
STATEMENT
1.0 PURPOSE
1. This method statement shall provide ARCC of minimum
guidelines to carry out epoxy grouting application works for
JAZAN REFINERY and TERMINAL PROJECT Package 12-
Naptha and Aromatics.
2.0 SCOPE
2.1 This method statement covers the epoxy grouting
application for J10-K-0701 & JlO K-0703.
2.2 Grouting application shall be in accordance with Standard
Drawing, vendors recommendation, clients procedure and
Saudi Aramco Standard.
4.0 MANPOWER
4.1 Construction Manager shall implement all HSE
requirements and ensure the implementation of this method
statement.
4.2 Civil/Mechanical Supervisor shall be responsible for
implementation at site. Civil Foreman with qualified crews
and personnel will be responsible for the direct supervision
and implementation of this method statement. Basic
manpower to be mobilize for site application shall include but
not limited to:
4.2.1 Carpenter
4.2.2 Mason
4.2.3 Helper
4.2.4 Surveyor
4.2.5 Rodman / Chainman
4.3 HSE Officer/Supervisor
4 .4 QC Inspector
6.2.17 Insert filler packing around the jack bolt so that the jack
bolt can be turned even after the grouting has become
hardened.
7.2 Testing
7.2.1 Epoxy Grout Sampling and Testing
7.2.1.1 Sampling and testing shall be performed by a Saudi
Aramco approved independent testing laboratory.
7.2.1.2 Third Party Agency’s Quality personnel assigned to the
Work must be technically competent to perform their duties.
7.2.1.3 Grout samples for compressive test shall be taken as
per ASTM C579, Method B Modified
7.2.1.4 Minimum compressive strength shall be 80 MPa
(12,000psi) at 7days.(PIP STS03601, Sec. 5.1.1.1).
7.3 Curing
7.3.1 Cure the grouted area as per manufacturer
recommendation, or to provide protection from direct
sunlight/ heat cover/ shade.
10.0 ATTACHMENT
10.1 Attachment 1 – Job Hazard and Risk Analysis.
10.2 Attachment 2 – Epoxy grouting sequence.
EPOXY GROUTING APPLICATION WORK PROCEDURE | METHOD
STATEMENT
EPOXY GROUTING APPLICATION WORK PROCEDURE | METHOD
STATEMENT