IBI CHEMATUR ENGINEERING & CONSULTANCY LTD.

IIBIC/WI/C-04

WORK INSTURCTION FOR


CONSTRUCTION Of WATER TANKS Page 1 of 8

1. Objective:

This work procedure narrates the guidelines for carrying out Construction of Water Tank.

1. Applicability :

This procedure is applicable for GNFC, TDI- DAHEJ PROJECT.

2. Reference Document:

(i) Technical Order Specifications (TOS).


(ii) Quality Assurance Plan(QAP)
(iii) Tender Documents
(iv) Working Drawings

3. A-Equipment:

Excavator, Dumper, Grader, Power Roller/ Soil Compacter, Diesel Operator/Electrical operated
dewatering pump, Mixer Machine, Batching plant/Volumetric/Weigh Batcher, Transit Mixers,
Concrete Pump, and Concrete Vibrator with Needle (40 dia & 60 dia).

3. B-Instrument:

Theodolite, Leveling Instrument & Total Station (with Calibration Certificate).

4. Raw Material Testing:

Raw Material shall meet as per IS Criteria & T.O.S or otherwise specified. All Test Records
shall be recorded in hard copy with consultants.

5. Responsibility:

 The Principle Contractor shall be responsible for the overall implementation of


this procedure.
 All FE”s will collect the drg. From FDC released by Home Engineer Office for
construction of concern work. He will study the entire drg. Execution point of
view and settled the query if any through FQC/QAM/CM.

PREPARED BY CHECKED BY REVIEWED BY APPROVED BY REV

Hiren Thakkar N.P.THAKKAR SHARAD JHAVERI M.R.PATEL 0


IBI CHEMATUR ENGINEERING & CONSULTANCY LTD. IIBIC/WI/C-04

WORK INSTURCTION FOR


CONSTRUCTION Of WATER TANKS Page 2 of 8

6.
A. Surveying :

 Construct local/temporary benchmark, transverse pillars, grid pillars, grid lines and transfer
level from the existing approved reference pillars.
 Check the existing benchmark as well as Co-ordinates with respect to Permanent BM as
marked/fixed by Client before starting the Project work.
 Take ground spot levels (N.G.L) in a grid pattern of 10.0 m intervals and prepare the field
book of spot levels for Construction of Water Tank. For this purpose before taking levels,
vegetation & other debris shall be removed from the ground.

 Site Clearance :
Area for construction shall be cleared of all materials including bushes, trees,
vegetation, obstructions, and rubbish. Permission of CLIENT Engineer shall be obtaining
before uprooting/removing any tree.

 Excavation:

 Check the boundaries of all excavation area distinctively on the ground for safety purpose.
 Excavation shall be started from top and proceeded to downward.
 After Excavation, the surface shall be rolled by 8-10 T capacity power rollers or Soil
Compactor. The sub-base thus prepared shall be lightly sprinkled with water if necessary &
rolled again by 8-10 capacity of power roller.
 The Size & depth shall verify by checking levels after final compaction of the surface and
recorded in hard copy.
 If Excavation doesn’t reach the required depth, re-excavation shall be made. And if it is
more than required the same will be filled by lean concrete of proportion 1:5:10.
 After verifying depth & visual Compaction, Modified Proctor density tests MDD in gm/cc &
OMC in % carried out by contractors by taking Core-cutting samples at excavated surface to
know the % compaction. All records of the test results shall be maintained in hard copy with
consultants.
 Carting of the excavated earth shall be done only at nearby plot area as shown by Client and
same shall not be deposited with in 1.5M from the top edge of excavation.

 Back Filling with Approved Soil:

 Yellow Soil Borrow area samples to be approved first so as to meet the characteristic of
yellow soil.
 Hydro-test shall be checked before filling.
 Filling work can be start with the permission of Engineer in charge only

PREPARED BY CHECKED BY REVIEWED BY APPROVED BY REV

Hiren Thakkar N.P.THAKKAR SHARAD JHAVERI M.R.PATEL 0


IBI CHEMATUR ENGINEERING & CONSULTANCY LTD. IIBIC/WI/C-04

WORK INSTURCTION FOR


CONSTRUCTION Of WATER TANKS Page 3 of 8

 Filling work shall be laid in layers with proper compaction by soil compacter.
 The moisture shall be checked by Moisture Meter at site before filling and the work shall
proceed if it comes in permissible limit.
 For compaction, Modified Proctor density tests MDD in gm/cc & OMC in % carried out by
contractors by taking Core-cutting samples or Sand Replacement method for each layer to
know the % compaction.
 Minimum 95% compaction required for yellow soil. All records of the test results shall me
maintained in hard copy with consultants.
 The same procedure shall be follow for each layer to get 95% of compaction.
 The Each layer thus prepared shall be lightly sprinkled with water, if necessary, & compacted
with soil compacter.

 P.C.C Work for Tank Bottom area:

 Bottom surface layer levels shall be verified before execution.


 Thickness & Grade shall be as per drawing & specification.
 Shutting work shall be in proper lined & leveled.
 Dimensions shall be checked as per drawing.
 For Volumetric proportion measuring box shall be used for nominal mix.
 Ensure the quality parameters like proportion of Coarse Aggregates, Fine Aggregates,
Cement, water & admixture (if mentioned) as per grade mentioned in Drawing & Detail
Specification.
 Compaction shall be done properly with compacters/rimmer.
 Thickness shall be verified by taking top of P.C.C levels at an interval of 5m or 10 m.
 Curing shall be done properly.

Reinforcement:

 Reinforcement bars should confirm to ‘TOS’.


 Field test shall be checked such as elongation, Hardness, bend test etc as per directed.
 Reinforcement shall not be brittle & equally not too hard.
 It should be free from corrosion, oil, dirt, grease, loose rusting etc which may destroy or
reduce the bond.
 BBS shall be approved as per IS 2502:1963 to proceed the work.
 BBS shall be as such prepared that it reduce % of wastage.
 Reinforcement shall be binded with double wire of Gauge as per TOS.
 Reinforcement shall be placed on the marked orientation of the structure.
 All laps shall be staggered & lap length shall be as per directed.
 For columns/walls verticality of steel should be checked & spacer bars/chairs shall be
provided to avoid sacking between two layers of steel.

PREPARED BY CHECKED BY REVIEWED BY APPROVED BY REV

Hiren Thakkar N.P.THAKKAR SHARAD JHAVERI M.R.PATEL 0


IBI CHEMATUR ENGINEERING & CONSULTANCY LTD. IIBIC/WI/C-04

WORK INSTURCTION FOR


CONSTRUCTION Of WATER TANKS Page 4 of 8

Formwork

 Quality of shuttering materials (ply, battens, props, spans, nails etc) shall be as per TOS and
Indian Standard.
 Shuttering shall be well planned & designed as such that it can resist load of structure & shall
not deform underweight & pressure.
 Shuttering should be capable to resist lateral, vibration loads, self weight.
 Supports of shuttering should be rested on the hard surface & fixed properly.
 Centring, leveling & lining should be checked.
 Shuttering oil should be approved before applying.
 Inserts, pockets, conduits, puddle flanges etc. shall be confirmed/checked as per drawing as
fixed as such that they may not deformed.
 MS Props should be used for supports & cross Bracings in place of Wooden Bamboos.
 Shuttering shall be made watertight to avoid the wastage of cement slurry.
 Re-used Shuttering should be properly clean, oiled and properly stacked.

 R.C.C Work

 Calibration of the Batching Plant/ Volumetric/Weigh batcher shall be done & the certificate
for the same shall be submitted
 Methodology for the overall procedure shall be approved first before execution.
 The steel bending shall be verified as per certified B.B.S only.
 Clear cover to reinforcement shall be as per drg.
 Water Stopper bar shall be provided at construction joint in walls as mentioned in drawing
and the same shall be approved before execution. Test result copy shall be recorded.
 Water Stopper bar shall be in lined & leveled.
 Grade of Concrete shall be confirmed before execution.
 Water Proofing compound & admixture shall be approved before execution and ensure the
consumption as mentioned in TOS.
 The chemicals shall be used before expiry date.
 Raw material required should be sufficient for the respective work.
 Batching plant/mixer machine/transit mixer/concrete pump/vibrators should be in good
condition. And standby equipment shall be arranged.
 Manpower shall required be sufficient, if required in mass concreting, manpower shall be
arranged to work in shifts.
 Set of cube moulds, slump cone shall be arranged.
 After above all checks, Pour-card shall be signed
 During concrete work, Slump test shall be check at every batch to know workability of
concrete. Water-cement Ratio shall be maintained. Slump/Cube Register shall be maintained.
 During Concrete work, surface Vibrator & needle vibrator shall be used for compaction.
 Levels of top of concrete shall be marked as per drg.

PREPARED BY CHECKED BY REVIEWED BY APPROVED BY REV

Hiren Thakkar N.P.THAKKAR SHARAD JHAVERI M.R.PATEL 0


IBI CHEMATUR ENGINEERING & CONSULTANCY LTD. IIBIC/WI/C-04

WORK INSTURCTION FOR


CONSTRUCTION Of WATER TANKS Page 5 of 8

 Post checking shall require after completion of work to avoid the discrepancy.
 Cube test shall be checked at regular intervals directed.
 Curing shall be done by Gunney bags.

 Safety plan:

 No material shall be placed/stacked near the edge of excavation pit/opening.


 Ensure no underground live cables/service pipes/drains are crossing the excavation area.
 Excavation shall be done from top to bottom.
 The excavation area shall be barricaded with coloured ribbon and sign board/red warning
signals shall be put up during night.
 All earth moving machinery shall have all safety measures like reverse horn, back light etc.
 All labours should work with safety PPE’s (Safety shoes, Safety Google, Safety Gloves, Full
Body Harness in case of work at height, Safety Helmet etc).
 Safety Talk (Tool Box Talk) shall be done at least once in a week for awareness of labours.
 Scaffolding/Stagging shall be approved first to work safely in case of work at height.
 Cutting Tools shall be in healthy condition.

 Inspection Records :

 All records related to existing benchmarks as well as derived benchmarks established in Plot
area as per Project drawings shall be duly verified by Consultant-IBIC and the same shall be
maintained in the register.

 All records of spot levels shall be approved by IBIC and the same shall be maintained in the
register and it shall be transferred on a drawing.

1. RECORDS.

 Following records shall be maintained and produce as and when required.

1 Level record
2 Testing Reports
3 Daily Progress report
4 Drawing file
5 Pour Card
PREPARED BY CHECKED BY REVIEWED BY APPROVED BY REV
6 Site Instruction

Hiren Thakkar N.P.THAKKAR SHARAD JHAVERI M.R.PATEL 0


IBI CHEMATUR ENGINEERING & CONSULTANCY LTD. IIBIC/WI/C-04

WORK INSTURCTION FOR


CONSTRUCTION Of WATER TANKS Page 6 of 8

PREPARED BY CHECKED BY REVIEWED BY APPROVED BY REV

Hiren Thakkar N.P.THAKKAR SHARAD JHAVERI M.R.PATEL 0