July 8, 2019. I finished the steelworks item of our assigned POW in the morning.
Then in the afternoon, I worked out with the tinsmithry and ceiling works items.
July 10, 2019. We went with Engr. Agbayani, together with Engr. Pamisa, in
visiting the sites of the University Center for Gender and Development, College of
Business and Management Phase II, and the Office of the Student Affairs Multipurpose
Hall. And then we worked out with our assigned POW, with me still on the plumbing
works item.
(a) (b)
(a) Second Floor and (b) Third Floor of CBM Building Phase II
UCGAD Building
July 11, 2019. We witnessed the ground breaking ceremony of the College of
Education Building Phase II in the morning. Before the program started, Engr.
Obedencio toured us in the construction sites of Educ Phase I and College of Human
Ecology Lab Bldg. In the afternoon, we accompanied him in visiting the CAS Annex
Bldg. Phase II and the ICA Bldg. Phase II. We observed the pumping out of water on
the footings of the ICA Bldg. Then we resumed with our POW in the office.
Engr. Obedencio touring the trainees on the Educ Bldg. Phase I and CHE Laboratory Buildings,
respectively
Visiting the CAS Annex Phase II and the ICA Bldg. Phase II
July 11, 2019. We resumed with our assigned POW, with me finishing up with
the plumbing works and the painting items.