You are on page 1of 3

ATL21.SE.

JV
Main Contractor: ATL21.SE.JV
Subcontractor:

Family Entertainment Centre Project


ITP for Block works

LOGO OF CLIENT

LOGO OF
ENGINEER

Name of Project

Inspection and Test Plan (ITP) for Block Works

Rev

Date

00

Comments

Prepared By

Initial Issue

Dawood
QA/QC Engineer

Date:

Page 1 of 3

Reviewed By

Approved By

Construction
Zone Manager

Project Manager

Inspection and Test Plan Number

ATL21.SE.JV
Main Contractor: ATL21.SE.JV
Subcontractor:

Family Entertainment Centre Project


ITP for Block works

Inspection & Test Plan


LOGO
OF
ENGR.

Title/Description

Block works

Unit Area: All buildings


Inspection Test Requirements
Activi
ty No.

Discipline: Block work


Reference Documentation

LOGO OF COM

Rev. 00
Inspections / Verification

Activity / Description
Test or
Inspection
Performed

Stage/Frequency

Code/Specification

Acceptance Criteria

Verifying Documents
/Demonstrated Evidence
Report Checklist
(Reference Number)

Subcontra
ctor

Main
Contract
or

Consulta
nt

Approved Submittals

Material Receiving Inspectio


Report (MRIR)

Material Receiving Inspectio


Report (MRIR)

IRF
Method Statement Checklis
Checklist number

Approval / Permits/Preliminaries
Preparation of

ITP,

Method Statement

Material Submittals

Drawings

1.1

Approval

Prior to Start of
Work

QCS 2014 SEC 1


PART 7 / As per
Project Specification

Specification Section
Number
Specification Section
Number

Code 1/ 2

Material Inspections (Delivery on Site)

2.1

Materials

Visual

Material Arrival on
Site

2.2

Accessories

Visual

Material Arrival on
Site

3
3.1

ITP No. :

As per approved Material


Submittals

Work Process
Prior to Start Blockwork

3.1.1

3.2

Mock up

Visual

One Wall Panel


with all required
accessories used

As per approved IRF


Approved Drawings
As per approved shop drawing
Specification Section
All required accessories
Number
included in the mock up
Blocks Laying/ Installation

Date:

Page 2 of 3

Inspection and Test Plan Number

ATL21.SE.JV
Main Contractor: ATL21.SE.JV
Subcontractor:

Setting out & Surface


Preparation

3.2.1

3.2.2

3.2.3

First Course

Block layer installation

3.2.4

4.0

Final Inspection

As - built Drawings

Family Entertainment Centre Project


ITP for Block works

Visual

Prior to laying of
every first course

Approved Shop
Drawing for Block
work layout

As per approved survey


layout
No unsatisfactory condition

Checklist:
Checklist number

Visual

Every 18 bays for


CFS bldg.
For other buildings
every completed
First course

Approved Shop
Drawing for block
work layout

Dimension is correct as per


approved block work layout
drawing

Method Statement
Approved Shop Drawing

Visual

During block laying


works

Approved shop
drawings for block
work layout

Checklist:
Checklist number

Checklist:
Checklist number

Approved As-Built Drawing

Visual

Approval

Every 18 bays for


CFS Bldg.
For other buildings
every completed
First Course

Approved Shop
Drawings block work
layout
Specification Section
Number

Progressively

All accessories required are


installed and verified.
All MEP required
embedment's and openings
are placed and verified
Construction Tolerances:
1. For Vertical lines. Plumb
shall not vary by more than
6mm in 6m height.
2. For vertical alignment of
exposed head joints, do not
vary from plumb by more
than 6mm by 3m, nor 12mm
max.
3. For horizontal line, do not
vary from level by more
than 6mm in 6m, nor 12mm
max.
4. For exposed bed joints,
do not vary from thickness
by more than +/- 3mm &
adjacent course with a max.
thickness limited to 12mm.
5. For exposed head joints,
do not vary from thickness
by more than +/- 3mm.

Code 1

Legend: I-Inspection, T-Test, W-Witness Point, H-Mandatory Hold Point for Inspection, R-Document Review, S-Surveillance, E-Execution, RE-Records

Date:

Page 3 of 3

Inspection and Test Plan Number

You might also like