Title :- Method Statement for False ceiling
Scope of work: - Installation of Gypsum Plain board ceiling, Moisture resistant
board ceilings
Drawing References: -
Document References: -
Madhanraj
1|Page
Method Statement
Contents
1. Purpose.........................................................................................................3
2. Scope of works..............................................................................................3
3. Location of works..........................................................................................3
4. References, Standards & Specifications.......................................................3
5. Access/Egress...............................................................................................4
6. Lighting.........................................................................................................4
7. Roles and Responsibilities............................................................................4
8. Plant and Equipment & Safety......................................................................4
9. Pre-Testing Checks.......................................................................................5
10. Materials.....................................................................................................5
11. Permits required to start the activity.........................................................6
12. Operational Sequence of work...................................................................6
13. Manpower...................................................................................................9
14. Housekeeping: -..........................................................................................9
15. Material Handling: -....................................................................................9
16. Interface with other subcontractors & contractors: -................................9
2|Page
Method Statement
1. Purpose
The purpose of this Method Statement is to define the activities and the sequences which are to be carried
out and to describe in general, the methodology to be used in work execution related to Gypsum board
False ceiling, Moisture resistant false ceiling for Kalyani Roshni Wework project, to ensure compliance
with the conditions of contract, contract specifications and Health, Safety and Environmental requirements
consistent with the approved drawings, relevant specifications in BOQ, and manufacturers
recommendations. Thus, the highest possible level of construction quality can be achieved when planning
2. Scope of works
The scope of this Method Statement specifically covers Supply and installation of Gypsum False ceiling in the
areas list enclosed, in general at Kalyani Roshni Wework project, at locations as mentioned in the
approved drawings and shall be carried out in compliance with the approved technical specifications, project
3. Location of works
Method Statements
Work permit
PPE’s checklist
3|Page
Method Statement
8. Plant and Equipment & Safety
Equipment and Tools:
Keyhole saw – Small triangular saw for cutting out holes for outlet boxes, pipes, and other
penetrations.
Assorted trowels and taping knives – Bladed tools for applying and smoothing tape and joint
compound over joints and fastener heads.
Tray / Box to contain joint compound while finishing joints and fastener heads.
PPE:
Helmet
Safety goggle
Safety hand gloves
Reflective jacket
Safety shoes
Dust protection masks
All the workmen should be competent / physically fit and trained to perform such work
9. Pre-Testing Checks
Safety induction/orientation
Job specific training
Tool box talk
Work permits
•Availability of tools in Healthy condition
4|Page
Method Statement
10. Materials
Item Material
1 Approved material for Various type of False Ceilings as per the approved MAS
5 Screws, fasteners
a) Pre-Construction Activities: -
Ensure all required document and material approvals have been obtained.
Ensure materials have been obtained from approved suppliers (As per BOQ)
Ensure sufficient raw materials are available at site prior to start of the works.
Ensure work area is clear and safe.
Ensure all constraints on operations have been identified and precautions are taken.
Ensure QC and HSE monitoring documents and procedures are established and approved.
Arrange sufficient Man-Power, equipment and services as required for the works and ensure
lighting, power and access arrangements are in place.
Implement Employee induction procedures and Tool Box Talks for ongoing risk assessment and
identification of hazards.
Erect scaffold and access platforms in accordance with approved temporary works documents
and safety procedures
Ensure that respective levels of ceiling/coves etc are marked as per approved drawings.
b) Dependencies: -
Clearance from MEP & Civil vendors to start ceiling framing works
Ensure that the MEP services level are in line with the coordinated drawings
Handover of MEP clearance too start ceiling Board closing works & finishing’s
Ceiling lights marking to facilitate cutouts.
5|Page
Method Statement
Level Markings:
Draw the require false Ceiling Finish line from the finish Floor by using Laser line marker
or Water Level. Transfer this line on all corners of room. Mark a line on periphery of wall
by using chalk line.
Framing:
Fix the perimeter channel on the periphery of wall with suitable fasteners (600 mm c/c)-
Hilti HPS 8 x45mm.
Mark the position of fasteners on true slab at 1220 mm c/c both directions.
At junction of two lines, drill a hole with the help of 8mm dia. Drill bit. Insert 8mm dia &
45mm long fastener inside a hole. (Diamond Make).
Fix the soffit cleat to the Fastener (27x37x25mm x 1.6mm) at 1220mm c/c. Ensure the
nut of DIamond fastener is properly tightened with Soffit cleat.
Fix the Ceiling angle (25x10mm) of suitable length to the soffit cleat at 1220mm c/c with
help of M6 Nut & bolt.
Using instrument transfer level and fix perimeter top flange level on to the Ceiling Angle.
Then mark the position of Intermediate Channel.
Fix the intermediate channel(15x45x15x0.90mm) to the flange of Ceiling angle(25mm)
with M6 Nut & bolt. Ensure Intermediate channel resting on Perimeter Channel.
fix Ceiling Section (80x51x26mm) perpendicular to the intermediate channel by using
connecting clip.
Ensure the overlapping of Ceiling section & Intermediate channel should not be less the
150mm. Used metal to metal screws.
Cross -Check the level of all frame work to ensure entire frame is in Line & Level.
Boarding:
Do boarding by using 6x4ft gypsum board. Ensure that the length of board perpendicular
to Ceiling Section. (Square Joint of Board screw fix on Ceiling section)
Put the 25mm drywall screws on board at 150mm on periphery of Ceiling & at 230mm
on ceiling section. Staggered the board joints.
6|Page
Method Statement
Ensure that, the drywall screws are 10mm away from tapered edge & 13mm away from
square edge to avoid breakage of the gypsum board.
Jointing Finishing:
Finish all the joints of boards with the jointing compound & paper tape. Don't remove
paper from square edge joint of Gypsum board.
Fill the joints of boards with jointing compound & embed the paper tape.
Spread first coat of compound 100mm -150mm on tape. After drying do the sanding to
remove excess material. Apply second coat – 200mm-250mm wide & third coat 300-
450mm wide.
Fold the paper tape along the Centre line (crease) & apply with jointing compound on the
internal joints of the partition & ceiling.
Do sanding after drying of each coat and handover for painting.
13. Manpower
The sufficient number of workers (Gypsum workers, helpers, Foreman etc.) will be employed as per
site requirement to perform their duties and they will have sufficient tools and tackles to completed
the work assigned to them
14. Housekeeping: -
All work area shall be kept free from any dirt, debris, unwanted materials, etc.
All materials placed in piles shall be done so in a manner that maintains safe clearance and that
Prevents tripping or movement.
All loose materials shall be secured.
Accumulation of any materials that may create fire hazards is strictly prohibited.
Excessive amount of materials is not to be stacked on floors or other supported areas in any manner
that may possibly over weights any structural area.
Passages, stairways shall be kept clear of observation.
7|Page