Method Statement
1. Purpose
The purpose of this Method Statement is to define the activities and the sequences which are to be carried out
and to describe in general, the methodology to be used in work execution related to Gypsum Plastering works for
Kalyani Roshni Wework Project to ensure compliance with the conditions of contract, contract specifications and
Health, Safety and Environmental requirements consistent with the approved drawings, relevant specifications and
BOQ. Thus, the highest possible level of construction quality can be achieved when planning and executing the works
described herein.
2. Scope of work:
The scope of this Method Statement specifically covers the Gypsum Plaster Works in general for Kalyani Roshni
Wework at locations as mentioned in the drawings and shall be carried out in compliance with the approved technical
3. Location of Work:
As per approved sample
Method Statements
Work permit
PPE’s checklist
All work shall be executed in compliance with the requirements of Project Specifications & Emergency Response
2|Page
Method Statement
5. Access & Egress to the work area:
Will use Scaffolds of specified make adhering to all parameters.
Unloading area will be kept free from any obstacles.
Safe area will be located for shifting of materials.
Any obstruction in the shifting passage needs to be cleared.
6. Pre-Testing Checks
Safety induction/orientation
Job specific training
Tool box talk
Work permits
Availability of tools in Healthy condition
3|Page
Method Statement
b) Marking & Levelling
Level pad will be marked at level of 1.0 mtr.
Button mark will be fixed
d) Application
Take full hands with plaster out of the bucket and apply them pad by pad, one next
to the other to the wall. The pads should be thicker as the final plaster thickness
given by the gages. The plaster pads should not start to flow down. Otherwise, the
consistency of the plaster is still too liquid (in case mix more powder in)
When the bucket is emptied, another parallel mixed bucket of plaster can be applied
the same way.
Then take the ruler and level the plaster along the gages
Scratched off material can be applied in not completely filled spots
Within maximum three “scratches”, the plaster surface should be closed well and
even
When the plaster starts to set, a final “scratch” can be done, to smoothen the
surface
Termination line should be in line with the level.
After the application, the area will be cleaned using vacuum cleaner.
10. Manpower
The sufficient number of workers (Gypsum Workers, helpers, Foreman etc.) will be employed as per site
requirement to perform their duties and they will have sufficient tools and tackles to completed the work
assigned to them.
4|Page
Method Statement
11. Housekeeping: -
All work area shall be kept free from any dirt, debris, unwanted materials, etc.
All materials placed in piles shall be done so in a manner that maintains safe clearance and that Prevents
tripping or movement.
All loose materials shall be secured.
Accumulation of any materials that may create fire hazards is strictly prohibited.
Excessive amount of materials is not to be stacked on floors or other supported areas in any manner that
may possibly over weights any structural area. Passages, stairways shall be kept clear of observation