You are on page 1of 7

Development of Surat MMTH on Engineering

Procurement& Construction (EPC)

Surat, Gujarat Division of West Zone Railway

Method of Statement for Anti Termite TTreatment (ATT) works @ MMTHS Project

NAME DESIGNATION SIGNATURE DATE


Prepared by:

Reviewed by:

Approved by:

REVISION NO: REVISION STATUS DATE ISSUED REMARKS

1
METHOD STATEMENT FOR
ANTI TERMITE TREATMENT (ATT)
WORKS

PROJECT: Development of Surat MMTH


CLIENT: Surat Integrated Transportation Development Corporation (SITCO)
CONSULTANT (PMC): Aarvee STUP Tractebel - JV

2
TABLE OF CONTENTS

1. SCOPE

2. PURPOSE

3. ROLE & RESPONSIBILITIES

4. RELEVANT DRAWINGS AND WORKS SPECIFICATION

5. WORK PROCEDURES

6. QUALITY MEASURE

7. SAFETY

8. ATTACHMENTS

3
Method Statement of anti-termite treatment.

1. SCOPE:
 This Method statement outlines and provides the guidelines to be followed for Anti termite
Treatment in relation with MMTHS Project, Surat-Gujarat, India.
 This work will follow all requirements, specifications, local codes or any other governing
regulatory agency or body after getting employer’s approval.

2. PURPOSE:
 The scope of the work is a proper way of Anti-termite Treatment (vertically and
horizontally) with the use of (approved anti –termite Material) on all concrete in contact
with the soil.
 The purpose of this document is to execute Anti termite Treatment as per standard
specification/guide line and to meet the process, quality, safety as per best industry
practices and customer satisfaction.
 The principle of the treatment is to create a continuous chemical barrier below and
around the buildings/structures so as to deny subterranean termites into the
buildings/structures.

3. ROLE & RESPONSIBILITIES:


 Project in charge: He shall be responsible to guide and give direction to the entire site team
to execute the job as mentioned in this WMS.
 Project Manager: He shall be responsible to arrange & provide required resources to execute
the job. Furthermore, he will ensure the implementation of this method statement during
work execution.
 Planning Engineer: Required Schedule, resources shall be well planned in consultation with
project manager.
 QA/QC Engineer: He shall be responsible to check the material and mix proportion, termite
treatment process mentioned in this work method statement. They will oversee the procedure
adopted and will ensure that there is no deviation from the EPC Contract. All record to be
maintained by the QC engineer.
 Site Engineer: He shall be responsible to perform the job accordingly to the WMS. He is also
responsible to ensure safety, quality and other requirements applicable for the job. Joint
measurement along with sub vendor to be carried out after completion of treatment.
 Safety Engineer: He shall be responsible to ensure safety prior to commencement of job at site.
Adequate no’s of Safety officer shall be deployed by him for safety supervision or as per site
requirements

4
4. RELEVANT DRAWINGS AND WORKS SPECIFICATION
SPECIFICATION:
 The work shall be done as per the approved GFC Layout plan of the project and
other relevant structural and architectural drawing of the project.
 Work shall be follows according to the IS:6313 Part2
Part2-2001
2001 and will follow the
procedures as per this code.

5. WORK PROCEDURE:

As per IS:6313.2.2001
 Treatment of top Surface of Plinth Filling:
 The top surface of the consolidated earth within plinth walls shall be treated with chemical emulsion at
the rate of 5 l/m2 of the surface before the sand bed or sub grade is laid.
 If the filled earth has been well rammed and the surface d
does
oes not allow the emulsion to seep through,
holes up to 50 to 75 mm deep at 150 mm centers both ways may be made with 12 mm diameter mild
steel rod on the surface to facilitate saturation of the soil with the chemical emulsion.
 Treatment at Junction of the wall and the floor:
 Special care shall be taken to establish continuity of the vertical chemical barrier on inner wall surface
from ground level up to level of the filled earth surface.
 Rodding if necessary to facilitate soaking, shall be carried out along the junction of wall & floor at
150mm interval and upto 300mm down
down.
5
 The chemical emulsion shall be poured along the wall at the rate of 7.5 l/m2 of vertical wall or column
surface so as to soak the soil right to the bottom. The soil should be tamped back into place after the
operation.
 Treatment of Soil along external perimeter of building:
 After the building is complete, the earth along the external perimeter of the building should be rodded at
intervals of 150 mm and to a depth of 300 mm.
 The rods should be moved backword and forward parallel to the wall to break up the earth and chemical
emulsion poured along the wall at the rate of 7.5 l/m2 of the vertical surface. After the treatment the
earth should be tamped back into place.
 Treatment of Soil Surrounding Pipes, Wastes and Conduits:
 When pipes, wastes and conduits enter the soil inside area of the foundations, soil surrounding the point
of entry shall be loosened around each such pipe, waste or conduit for a distance of 150 mm and to a
depth of 75 mm before treatment is commenced.

 Treatment for Expansion Joints


 Expansion joints at ground floor level are one of the biggest hazards for the termite infestation. The soil
beneath these joints should receive special attention. This treatment should be supplemented by
treating through the expansion joints after the sub-grade has been laid, at the rate of 2 liters per linear
meter.

6. QUALITY MEASURES:

 Treatment should not be carried out when it is raining or when the soil is wet with rain or sub-
soil water. The foregoing requirements applies also in the case of treatment to the filled earth
surface within the plinth area before laying the sub-grade for the floor
 Ensure Proper depth and whole spacing for effective treatment of soil.
 Once formed, treated soil barriers shall not be disturbed. If, by chance, treated soil barriers are
disturbed, immediate steps shall be taken to restore the continuity and completeness of the
barrier system.
 The chemical emulsions described shall be applied uniformly at the prescribed rate in all the
stages of the treatment
 Performance warranty shall be submitted after completion of treatment.

6
7. SAFETY:

 Site Engineer and Safety Supervisor shall carry out the safety site inspections to ensure that
safety requirements laid out in the safe work plan are followed before, during and after the
work. Safety Engineer / Supervisor shall review HSE Plan and secure Work Permit shall be
obtained prior to start of block work.
 Wherever necessary barricading and signage’s will be provided for work area. The checks
shall be conducted as & when necessary.
 All the chemicals mentioned are poisonous and hazardous to health. These chemicals can
have an adverse effect upon health when absorbed through the skin, inhaled as vapours or
spray mists or swallowed.
 Persons handling or using these chemicals should be warned of these dangers and advised
that absorption through the skin is the most likely sources of accidental poisoning.
 These chemicals are brought to the site in the form of emulsifiable concentrates. The
containers should be clearly labelled and should be kept securely closed.

 Particular care should be taken to prevent skin contact with concentrates.


 Prolonged exposure to dilute emulsions should also be avoided. Workers should wear clean
clothing and should wash thoroughly with soap and water especially before eating and
smoking. In the event of severe contamination, clothing should be removed at once and the
skin washed with soap and water. If chemicals splash into the eyes they shall be flushed with
plenty of soap and water and immediate medical attention should be sought.
 In case of poisoning, suitable measuresshall be taken for protection in accordance with IS-
4015 and may refer to nearest hospital/first aid centre.

8. ATTACHEMNTS:

 ITP & MTP for Anti termite Treatment


 Quality Checklist for Termite Treatment
 PCI Specification/Procedure for ATT.

You might also like