You are on page 1of 3

WORK METHOD STATEMENT

PROJECT NAME – ITC Infotech - Green Center

WORK METHOD STATEMENT FOR APPLICATION OF BOND IT & ELITE


90/100 PLASTER IN CEILING

OBJECTIVE:

The objective of this method statement is to carry out the BOND IT & ELITE 90 by meeting
the technical specification and complying with Standards.

SCOPE:

The scope of this method statement includes the BOND IT & ELITE 90 /100 works at ITC
INFOTECH - Green Center Project while executing, it in accordance with technical
specifications.

REFERENCE:

 Manufacturer Specification
 BOQ – Ref No -4.06
 Approved Drawing

TOOLSAND TACKLES

 Straight edge, Plumb


 Trowel, Aluminium Bottom
 Measuring tape (steel),
 Thread, plumb bob, right angle,
 POP mixing Tray.
 Tarpaulin, PVC sheet
 Hand gloves
MATERIAL USED:

 Approved BOND IT PRIMER


 Gyproc Elite 90/100
 Water

SAFETY PRECAUTION:

 Induction to all the personnel involved by Exotic safety manager.


 Issue of a permit by PMC
 Use of appropriate PPE.
 Barricading if required
 Prevention of use of any hazardous material
 Appropriate supervision

WORK METHOD STATEMENT


WORK METHOD STATEMENT

PROCEDURE:

Background Preparation

Surfaces should be reasonably dry, clean and protected from the weather, and suitable for
the chosen specification. In addition, before plastering concrete backgrounds, ensure that
any mould oil or other agents present are removed from the surface. No-fines concrete does
not require wetting prior to plastering. Plaster should not be applied onto a ‘green’
background or when any free water is visible. Clean water should be applied 5-10 minutes
before plaster application to control the suction. In-situ or pre-cast concrete which are
exceptionally smooth or having low suction will require pre-treatment with Gyproc Bond-It
bonding agent.

Mixing

Gyproc Elite-100 /90 is pre-mixed with aggregate and only clean water needs to be added
to prepare it for use. Mixing should be carried out in a clean tray or bath. Excessive
mechanical mixing should be avoided. Tools and water used in mixing must be clean.
Contamination from previous mixes can shorten the setting time and in turn reduce the
strength of the plaster when set. Water to plaster ratio (1 part of water: 1.25 part of plaster by
weight) should be maintained to have good cohesive workable mix. Prepare plaster mix as
much as required depending upon the immediate scope of work. Once the mix has begun to
set, additional water is not to be added, as performance properties of plaster will get altered,
thus affecting workability, cohesiveness, adhesion properties and strength.

Application

POP should be applied with firm pressure, built out to the required thickness, and ruled to
an even surface and left as an undercoat to form a key for finish coat. A thin plaster mix is
made and applied as a finish coat to provide smooth surface. It can be applied to an average
thickness range of 3-15 mm on walls in one coat and up to 10 mm on ceilings. For punning
S/C plaster surface should be wetted before application to provide firm bonding. After
complete drying for usually 72 hours (depends upon thickness and weather conditions) the
plain smooth levelled surface is ready for painting.

RESPONSIBILITIES.

 Construction Manager: He shall be responsible for overall management of


construction activities.
 Site Engineer: He shall be responsible for Executing in safe work method as per
Drawings and guide the supervisors and work men.
 QA/QC In charge: He shall be responsible for ensuring the quality of work &
material as per the Specifications and standards.
 HSE Manager/Engineer: He shall be responsible for assisting to
engineer/supervisor to ensure the safety of workers during the progress of work.

WORK METHOD STATEMENT


WORK METHOD STATEMENT
 Safety inductions of each staff and workers shall be done and daily PPE check to be
done and toolbox talk shall be carried out before the start of work. General safety
awareness as well as safety precautions and guidelines for activity to be carried out
in that day shall be discussed.
 Stores officer: He shall be responsible for storing of all materials. Also responsible
for maintaining the record of incoming and outgoing and up to date stock details of
materials.

WORK METHOD STATEMENT

You might also like