Professional Documents
Culture Documents
REFERENCE DOCUMENTS:
5 Safety Officer 1. The day-to-day activities of maintaining safety on project site, they
must: Understand and comply with requirements of the safety
manual.
2. Cooperate with the safety engineer to create and maintain safe
working conditions.
3. Assist the site engineers and foremen to organize the work area so
that the men can perform their duties with maximum efficiency and
minimize risk to themselves or to equipment.
4. Inspect equipment and tools before use to ensure correct storage
and properly utilization. Maintain record of all injuries and damages
on site, submit reports as required.
RISK ASSESSMENT:
1.3 Grinding & Pipe 1.Electric Shock. 1.Grinding & Cutter machine
cutter machine 2.Struck by grinding/cutter wheel. power supply should be routed
3.Unauthorised operation. through ELCB.
4.Defective machine. 2.Double Insulated power
5.Grinding & cutting sparks cables shall be used.
3.Ensure use of standard cable
glands near the machine. No
joints allowed in power cable of
grinding & cutter machine.
4.Machine wheel guards should
be ensured
5.The grinding & cutter wheel
should be checked for the RPM
and the expiry date.
6.Handling and storage of
grinding & cutter wheels shall
be as per standards.
7.Grinder & pipe cutter shall
use face shield with helmet in
addtion to safety goggles
underneath the shield.
8.Ring test, idle run of wheel,
physical inspection of wheel
may be performed by the
grinder ,pipe cutter before
installing the wheel to the
grinding & cutting machine.
9.Ensure availability of
standard spanners / keys to fix
or dismantle the grinding &
cutting wheel from the
machine..
10.Only trained and
experienced grinder,cutter to
be do the job. Trade validation
of the grinder is mandatory.
11.The grinding & cutting
machine should be inspected
from RASS & TCPL as per its
standary frequency and tagged
for fit.
12.Internalinspection at site to
be done on monthly basis and
recorded in the register.
13.Additional PPE’s coverall,
face sheild, apron, heat
resistant hand gloves, ear plug
shall be used by the grinder &
cutter.
14.Ensure no combustible
material or person works in the
vicinity of grinding & cutting
spark. Use barriers to prevent
the spark from flying in the
surrounding area of the
activity.
15.Ensrue availability of fire
extinguishers in the area where
grinding &cutting is being
performed.
1.6 Pressure Testing 1.Water leakage during the testing. 1. Ensure the testing area
Of Pipe barricaded by caution tape
2.Coagulation of water on the ground and displayed the signage
level. board
2. Ensure that electrical cables
are not cross the testing
area.
3. The pipe must be welded /
clamped immediately after
erection
4. Twisted wire must be
installed during pressurized
3. Ensure Communication
with proper hand signals,
whistles, intermediate
signal man, etc. during
erections
1.10 General, 1. Adopting short cut 1. Daily TBT should be given
Activity method,negligence,wrongpercepti to all workers.
on, absent mind, using cell phone. 2. Everyone should know
2. Proper Illumination emergency procedure &
Contact Number.
3. Training for motivation is
reqd.
4. Ensure effective
supervision.
2. Manually 1. Shifting the 1. Fall of Material from height. 1. Allow only authorize
MS pipe fixing required 2. Slippage of materials. Failure of /Trained person to work.
materials at lifting material. 2. Ensure work specific tool
work location. 3. Fall from height. box/training to all the
2. Make a proper 4. Due uneven surface ladder can be workmen conducted by the
scaffold toppling. site Engineer.
arrangement for 5. Injury due to rough edges. Check the access for
access at height. 6. Injury due to sudden arc flash. fabrication /welding work &
3. Fixing the MS 7. Eye burn/ Irritation due to workers movement before
pipe vertical up welding. start the job.
to as per 8. Serious injury. 3. Horizontal lifeline to be
standard. 9. Fire. fixed and worker who will
4. Fixing of fix the 'U' Clamp, threaded
Horizontal pipe rod & anchor his full body
and support, harness.
clamp to be 4. Ensure the availability of
done. Fire extinguisher near
5. Verticality to be fabrication /welding
checked with machine.
plumb after 5. Ensure the double body
fixing. earthing of all electrical
equipment/ machinery and
all power cable should be
overhead & double
insulated.
6. Ensure the all-power supply
should be through 30 M.
AMPS ELCB.
7. Job specific PPE to be used.
3. Shifting and 1. Make proper 1. Contact with rough edge. 1. Ensure Work Permit from
fixing of arrangement of 2. Fall of material. client, if required and
Accessories scaffold and 3. Failure of lifting equipment. further issue work permit to
fixing (Like - working platform 4. Slippage of material contractor by Civil Engineer
butterfly for working at only after physical
valve, landing height. verification of work
valve, hose location.
reel drum, pr. 2. Workers will lift 2. Allow only authorize
Gauge, Deluge Valves manually /Trained person to work.
Valve, flow to the location 3. Ensure work specific tool
switch, by rope. box/training to all the
Sprinklers 3. After alignment, workmen conducted by the
etc.) bolt will be done site engineer and safe route
in the flanges to be discussed with workers
4. Bolt tightness & operator
will be done & 4. Ensure the lifting area
washers fitted to barricaded by caution tape
ensure and displayed the signage
board.
5. Not less than 8mm wire rope
should be ensure for
anchoring the bull body
harness, Safety Helmet,
safety Shoes, reflective
jacket, Goggles)
6. PPE (Cut Resistance hand
gloves, Leather hand gloves
Helmet with attached face
shield, Welding apron, hand
sleeve leg guard, Safety
Helmet, safety Shoes,
reflective jacket, Goggle)
RESOURCES:
Tools Required:
MOBILIZATION:
Preparation and Planning
1. Precautions, manpower, and equipment are available before the commencement of work.
2. The Site Team shall make sure that access roads are always clear from any obstruction and the site
is always accessible.
Site clearance
1. Before commencing the work, the area shall be cleared of all debris, materials, or other
obstructions.
2. The Site Team with the assistance of the Safety Officers shall coordinate logistics and materials
movement through the site following the direction on site.
3. The Work Permits and Operator Certificates shall be compiled and files for reference by authorized
personnel.
Pre-construction Safety Meetings
1. The meeting shall be scheduled prior to the beginning of the work and before any Subcontractor
starts on the project.
2. Safety awareness meetings will be conducted every working day morning/every other day to brief
the workforce on safety prevention measures. The equipment check for safety shall be recorded/
documented during the daily Safety Awareness Meeting.
3. Traffic safety will be discussed to emphasize these meetings.
4. Each worker will be instructed to follow specific safety requirements related to his trade. They will
be required to follow installed safety signs, observe barricades and use PPEs.
5. The Safety personnel will perform hazard risk analysis by identifying all steps, hazards identified in
those steps, with a focus on the relationship between the work task, the tools, and the work
environment. After identifying uncontrolled hazards; the Contractor will take steps to eliminate or
reduce them to an acceptable risk level.
6. General Contractual Safety, Health, and Environmental requirements.
7. Roles of the contractor, subcontractors, authorized representatives, and all project workers.
8. Accident reporting requirements.
9. Specific details of the work to be performed along with the use of personal protective equipment.
10. Emergency procedure.
Operating Procedures
A site investigation has to be carried out to develop safety precautions and measures prior to the
commencement of the work. After such investigation, relevant signboards will be displayed and
barricades will be installed where and as necessary, such as but not limited to the following:
1. Relevant information, advanced signs, warning, and mandatory signs will be placed as required.
2. After completion of the work, safety cones and barricades have to be removed accordingly.
METHODOLOGY:
OFFLOADING:
1. Special care must be taken to ensure that units are offloaded from the containers.
4. In the case in which the lifting tube is utilized, it must be inserted into the specific hole, then
the sling, which is equipped with a particular loop, must be connected to the tube. After that,
the section can be lifted.
5. Note: It is strongly recommended that offloading and installation operations will be carried out by
specialists with the necessary equipment and proper tools.
6. Special care must be taken to ensure that pipes are offloaded from the containers.
8. In the case in which the lifting tube is utilized, it must be inserted into the specific hole, then
the sling, which is equipped with a particular loop, must be connected to the tube. After that,
the pipes can be lifted.
9. Note: It is strongly recommended that offloading and installation operations will be carried out by
specialists with the necessary equipment and proper tools.
STORAGE:
1. All material while unloading shall not be dropped, but slowly lowered to the ground.
5. While stacking, it shall be ensured that pipes of bigger sizes are placed below and smaller
sizes on top.
6. All pipes shall be covered and shall not be exposed to direct sunlight.
7. All other items such as valves, fittings, gauges, etc. shall be kept on racks within site
stores and shall be segregated as per size, model, type etc. for easy retrieval.
9. Insulation material shall be segregated as per size, thickness for easy retrieval.
10. All supporting materials shall be stored in a covered storage area, segregated according to size,
type, model, etc. for easy retrieval.
11. Manufacturer’s instructions for storage shall be followed for applicable items.
12. Any items found damaged or not suitable as per project requirements shall be removed from site.
If required to store temporarily, they shall be clearly marked and stored separately to prevent any
advertent use.
PREPARATION:
1. Check and ensure all drawings used for installation are latest and
approved for construction.
2. Mark the pipe routing and support locations in the trench as per approved drawings.
3. Check the co-ordination of piping layout with other services and decide pipe route with
minimum bends/offsets.
4. Check and ensure sufficient clearance around the pipe for applying insulation / cladding as
applicable.
5. Check the access and clear space around valves, vent points, drain points locations for
maintenance and servicing.
7. Clean and apply primer / red oxide on all ERW black pipes.
INSTALLATION:
2. Fix the anchors and threaded rods with clevis hangers/ structural supports as applicable.
Threaded rod length shall be sufficient to allow for levelling of piping. Supports details as per
attached sketches.
4. Prepare the pipe ends according to the type of joints ie. threaded joints, welded joints /
grooved coupling joints.
6. For grooved joints pipe end should be square and cut with machine.
7. Flow process of grooving the pipe will incorporate a 1 Mtr long sprit level at least two nos. of
pipe stand for 6 Mtr long pipe and a completion check for squareness.
8. End preparations for welded joints shall be done as per approved welding procedure.
9. After the end preparation clean the pipe ends and ensure no material and dust is left inside.
10. Depending on site conditions, assemble the piping into manageable lengths on the floor.
Using threaded, welded/groove coupled jointing as applicable.
11. Qualified and approved welder with current certificates shall be engaged for welding
works.
12. Install the pipe sections at heights as per approved drawing in a neat and tidy manner.
13. Insert the approved hard insulating material of suitable thickness between the pipe and
support.
16. Hole saw cutter shall be used to cut the holes in the pipe work for fixing branch
connections for Victaulic fittings.
18. Install the piping connections with valves and accessories wherever equipment’s are
installed as per approved drawings.
19. Fix the blind plugs / temporary valves on all drain, air vent, pressure gauge, thermometer
and test points tapping’s approved drawings.
20. Check and ensure proper supporting is provided as per approved drawings.
21. Make temporary tapping provisions at multiple points for easy and quick filling and draining
of pressure testing water.
22. Ensure all joints are properly tightened in line with manufacturer recommendation.
23. While installation is going on of the pipe work, the insulation will be fitted to the pipe work
prior to pressure testing. But all fittings and joints will be left exposed until the pressure testing
and inspection is completed.
24. Raise t h e “ WIR” f o r piping installation by NMX QA/QC and consultant. Obtain signoff for
hydraulic pressure testing.
PRESSURE TESTING:
1. The chilled water piping shall be tested according to the system working pressure and PN
ratings of the pipes, pipe fitting and valves used in the piping.
3. Estimate the piping volume and make arrangement for required quality of clean water.
4. Arrange for temporary piping / hose pipe connections for filling and draining the water.
5. Fix the temporary valves at air vent / drain points and pressure gauges.
8. If leakages are observed, arrest the leakage immediately. If leakages are major, isolate the
leaking portion with nearest isolating valve and / or stop the water filling.
11. Observe for the leakages and pressurize the system using hydraulic test pump.
12. During pressurization observe the joints and entire piping system for leakages.
13. Pressurize the system till pressure on the pressure gauge at lowest part of the system indicates
pressure.
14. Observe the pressure gauges readings for 8 hours and ensure there is no drop in gauge pressure.
15. Raise the “WIR” for witnessing the hydraulic pressure testing by QA/QC and consultant.
16. Obtain signoff with clearance for insulation only after satisfactory pressure testing.
PIPE INSULATION:
1. The pipe surface shall be thoroughly cleaned to remove dust, traces of oil, grease etc. All welded
joints are painted with red oxide primer.
2. For smaller pipe sizes, pre-for me insulation pipe section of suitable thickness, as per approved
drawings/submittals to be used. For larger pipe sizes insulation sheet shall be used in thickness
described in the materials submittal.
3. Smaller pipe which are not exposed to direct sunlight and insulation is not susceptible for damage,
insulation may be done by inserting the pipes in to insulation sections during pipe installation.
4. When insulation is done after pressure testing following procedure shall be followed.
5. Slit the pipe insulation section, longitudinally and apply adhesive on inner surface and longitudinal
slit as recommended by manufacturer.
6. Apply the adhesive on the surface of the pipe to be insulated, as recommended by manufacturer.
7. Fix firmly the insulation on the pipe surface and hand press the insulation to remove any air locks.
The longitudinal seam shall be joined properly by hand pressing.
8. Fix the elastomeric self-adhesive tape over the longitudinal seam.
9. Continue the same procedure for successive lengths. Adhesive shall be applied on circumferential
joint properly. Seal the circumferential joint by fixing self-adhesive tape.
10. For larger pipe sizes, cut the insulation sheet of suitable width to suit pipe size. The length shall
be as manageable as per site conditions.
14. Raise the “WIR” for QA/QC and consultants and obtain the signoff.
INSPECTION:
1. WIR” by QA/QC and Consultant shall be raised for piping installation, pressure testing, joint
insulation and signed by Consultant.
2. Inspection shall be carried out as per installation checklist during installation, testing and
insulation stages.
Note :
If required for a specific work, detailed method of control for any additional hazards will be provided
separately.