You are on page 1of 13

LARSEN & TOUBRO LIMITED

Construction of IICC-Dwarka, New Delhi Civil & Associated Works


Contractor's Submission
Submission of Method statement for Screed
— L&T/IICC/QACIC/ARCH/MST10051R0

Arch Civil Elec Gen Mech Syst


Discipline
-V
Explanatory
Submission of Method statement for Screed
Notes — Rev 00

Contractor's Submission Form


Date: 3 A ril 2019
Contact Document Control
Name: Mr T.N. Anandan Copy # One Copy

Tel: 9004043364 Action Required


Email:
tnanand@lntecc.com For Information For Approval
-
\
I

Received by Employer's Representative


E mP Date

Date: 03 0
Signature: . . ,

Preparation & Issue

NAME POSITION SIGNATURE DATE


PREPARED BY
Prabhat Sengupta Asst. Manager Ck kiAkst
REVIEWED BY
T.N Anandan Quality Manager .-i. ,r. A--,-,----'4:1 3,4'10 tef
APPROVED BY

(Client)

L&T Construction
IICC PROJECT. SECTOR-25, DWARKA, NEW DELHI
DOC CONTROL
Dispatch No : -I 6-13 9

j
Dispatched y : Pf P-

Signature - :

Date of Di atch : 0 3 jo Lt H 9
LARSEN & TOUBRO LIMITED Quality Management System
BUILDINGS & FACTORIES IC
India International Convention & Expo Centre (UGC), L8.1711CC/QAQC/ARCH/MST/005/R0
Sector-25 Dwarka , New Delhi
Doc Title: Method statement for Screed Page 1 of,‘

METHOD STATEMENT
FOR SCREED— Rev 00

Prepared L&T Internal Review Approved


By: Reviewed & Endorsed By By
Company L&T L&T CLIENT
Prabhat Sanjeev Amit TN
Name B. Modi V.Ramesh
Sengupta Sharma Chawla Anandan
Quality Project Project Project
Asst. i Project
Position Fin shing EHS Quality
Manager Manager Dire or
Mana gr an er Head
92.
Signature

Date a. 04p,A. tik 2_ lii wx .2__/Ile% -.'.1.11'ili -1aillart


-2 VAINC%
9--

e
t

REVISION RECORD SHEET


MST Ref No Rev Description of Revision Date
No

L&T/IICC/QAQC/ARCH/MS
00 Submission of Method Statement — 00 Allikel
T/005/R0
Quality Management System
LARSEN & TOUBRO LIMITED
BUILDINGS & FACTORIES IC
e M L81711CC/QAQC/ARCH/MST/005/R0
India International Convention & Expo Centre CC),
Doc Title: Method statement for Screed Page 2

CONTENTS
S.NO TITLE PAGE No.
i Title 01

ii Contents 02

1 Scope of Work 03

2 Access/Egress 03

3 Technical References 03

4 Responsibility 03 — 05

5 Plant & equipment's 05

6 Safety 05

7 Scaffolding 05

8 Training 05

9 Procedure/Sequence of Work 06

10 Quality Assurance & Control 07

11 Records 07

12 Annexure 07- 13

onstr
,8
LARSEN & TOUBRO LIMITED Quality Management System
BUILDINGS & FACTORIES IC
India International Convention & Expo Centre (IICC), L&T/IICC/CIAQC/ARCH/MST/005/R0
Sector-25 Dwarka , New Delhi
Doc Title: Method statement for Screed Page 3

1. SCOPE OF WORK
The purpose of this method statement is to describe the sequence of activities which will be
followed to execute Screed at India International Convention & Expo Centre (IICC) Project at
Sector -25 Dwarka, New Delhi

2. ACCESS / EGRESS
 Proper access and egress will be ensured before and of work.
till completion
and exits shall be clearly
 Temporary signage will be provided at access and egress.
Approaches defined by barricades and warning/caution signs. periodically.
 Proper illumination will be ensured at site during work and
shall be monitored
 Necessary safety precautions will be taken for works
at heights.
 Project Architectural specification — Schedule D
Annexure 2.
 IS Codes (IS-2571).
 Project Quality Plan.
 Project EHS plan. ■ Approved drawings.

 Approved Mix Design

4. RESPONSIBILITY

PROJECT  Organize and manage all resources, field


MANAGER activities required to the
execution team with due regard to safety and meeting product quality
requirements.
 Planning of resources in line with schedule, specifications,
CONSTRUCTION drawing details and liaison with Client, statutory and regulatory
 To ensure that all the equipment, tools and tackles required to execute
MANAGER / the
SECTION IN- works according to approved construction Schedule are available in good
CHARGE condition and provide any additional equipment as required.
 To ensure all the equipment's I vehicles are handled by licensed /
skilled
operators.
 To provide all necessary support to his construction team and ensure
that
the works are carried out as per the approved Method
Statements/procedures.
 Co-ordinate with site engineer, Surveyors, Safety
Engineer, Quality
Engineer, and frontline supervisors for safe & proper execution of the
works.
 To ensure that, checked levels shall be entered in level books as per
the
approved formats & requirements on daily basis.
 To ensure that levels are jointly being signed by the contractor and
Client
LARSEN & TOUBRO LIMITED Quality Management System
, e BUILDINGS & FACTORIES IC
India International Convention & Expo Centre °ICC), L&T/IICC/QAQC/ARCH/MST/005/R0
Sector-25 Dwarka , New Delhi
Doc Title: Method statement for Screed Page 4

required.
 To ensure curing arrangements are done properly.
SITE ENGINEER  Understanding the drawings prior to start of work and all
details are
provided to execute the work. If not, then take clarification from Client.
 Compliance to EHS and QA/QC requirements prior to
commencement of work.
 Engaging workmen in work according to plan.
 Cross checking the activities intermittently during day's work and
ensuring the activity is done within tolerance limits.
 Mobilizing the materials required for work prior to start of work.
Preparing safe to start work card for all activities and giving PEP talk
based on the safe to start work card as part of the work instruction to
workmen working under him highlighting the risk involved in the task.
 To ensure safety of workmen working in his area. To ensure
proper working platform with access to keep materials.
 To ensure all working and checking tools are available at site with
working team before start of work.
 To ensure proper housekeeping at site at the end of day's
work.
 Understanding EHS requirements of
project from EHS plan, EHS
management systems, EHS Manual & following the same in execution of
work.
 Marking legibly grid reference/ Date of construction.
 Ensuring implementation of proper work methodology for all
activities.
SURVEYOR  To establish bench marks from agreed reference points,
provide required
setting out and line and level markings and follow up regular checks.
 Co-ordinate with site engineers and ensure that the survey
works are carried out according to the latest drawing.
SAFETY INCHARGE  Maintain survey
Shall inspect in details and reports.
maintaining safe working environment &
conditions and compliance to Project EHS Plan. Shall facilitate in EHS
Risk analysis and ensure required preventative measures.
 Identify potentially unsafe acts, areas and practice and
educate people
 Monitor EHS practices, persuade to minimize non
compliance
 Report incidents beyond control and unsafe occurrences. Issue
stop work notice for unsafe work.
 Investigate unsafe occurrences and initiate preventive steps.
 Discuss near miss accidents with staff and workmen
 Conduct safety training programs and celebrations
P&M/ ADMIN  Ensure availability of all statutory related to safe use of all
INCHARGE documents construction equipment's and dumpers, excavators, and
vehicles such as passenger vehicles (if
any). to carry o r 0 s r
 To facilitate site team for all ,
QUALITY enabling
 work without any interruption.
Communicating with all site staff about the Quality
INCHARGE req6irements as) .4r Q M S
, ,
LARSEN & TOUBRO LIMITED Quality Management System
BUILDINGS & FACTORIES IC K
India International Convention & Expo Centre (C), L8,1711CC/QAQC/ARCH/MST/005/R0
Sector-25 Dwarka , New Delhi

Doc Title: Method statement for Screed Page 5

 Shall ensure all inspections and tests are conducted as per


approved Inspection and Test Plan.
 Shall ensure only approved materials incorporated in works.
 Closure of Non-conformance, if any.

5. PLANT & EQUIPMENT


A. Plant & Equipment Schedule

Machinery/Tools/Equipment engaged to carryout Screed are as follow:


 Site Mixer/Spade.
 Total station/ Leveling instrument.
 Graduated straight edge, measuring tape, Auto
level.
 Spirit level.
 Steel & Wooden trowel .
 Thread, line and pin strings.
 Trowel, Wire Brush.
 Concrete Pump

B. Personal Protective Equipment


like safety helmets, safety
 All workmen should wear proper Personal Protective
and reflective jackets & face
Equipment (PPEs) belt, hand gloves, nose mask, gum
boots/safety shoes, safety glass, shield etc.as applicable.

6. SAFETY
 All the manpower involved in the job shall wear Protection equipment.
appropriate personal
 Proper approach to the work spot, and proper illumination formwork activity.
shall be maintained.
 Ensure that relevant risk assessment is available with the
engineer during
 Full body harness must be used while working at
height.
 Ensure all power tools are inspected by safety
Department. on the job specific

process.
7. TRAINING
 Proper Tool box talk shall be given by Engineers to
con S fr ,
Supervisors and labors requirements including approved HIRA. -
7
,

 Ensure that all workers engaged are properly gone


through induction -,- \

_,.... ,

".10r-25, 010'
Q
LARSEN & TOUBRO LIMITED Quality Management System
BU IL DI NG S & F A CT O R I E S I C
e India International Convention & Expo Centre (IICC),
L8.1711CC/QAQC/ARCHNIST/005/R0
Sector-25 Dwarka , New Delhi

Doc Title: Method statement for Screed Page 6

8. SEQUENCE! METHOD OF WORK


8.0.1 Screed

A. INTERDEPARTMENTAL INTERFACE

The EPCC finishing department to sought clearance from EPCC Civil department for laying of Screed with hardener
The clearance/comments will be shared to EPCC Finishing department as per their requirements by EPCC civil
department and vice versa.

After the completion of the activity, EPCC finishing department has to seek for internal clearance from EPCC QA/QC
team
The EPCC QA/QC team will issue clearance/comments for the completed activity.
Then the EPCC finishing team raises inspection request of the activity to Employer's engineer.
Then the Employer's Engineer will accord acceptance (duly verified and approved by Employer's representative
Finishing Team) or comments if any for which IR has been raised.

Comments if any will be recorded in LAT/BFRICC/SOP/ID1/003/R1 interdepartmental HOTO will be attached to the
IR

B. Setting Out and Preparatory Works

Setting out to be carried out for the panels to be casted.


With the use of MS channels the sides of the panels will be secured.
Formwork material such as plywood and timber can also be used preparing the sides of the panel.
Level Pads as per the slope given in approved Drawing will be made with concrete
Survey sheet after securing the sides of the panel and putting level pads will be prepared and witnessed by
Employer's Engineer.

Alternative casting of panels will be done.


The maximum size of panel will be restricted at 16 sqmt or as per Architecture detail design.
Thoroughly clean the surface of all damaging substance, loose laitance, oil grease, etc. If necessary. This shall be a
Quality Hold Point
MS mesh shall be laid at all panel joints with mesh of size 300mm-10 SWG
It will be placed such that 150 mm of mesh will be casted in the panel and the rest will casted with the adjoining
panel.

Ensure pipeline for laying of Screed is completed.

C. Laying of Screed

The prepared 1:2:4/M15 (Approved Mix Design) concrete shall be laid immediately after mixing.
The concrete shall be spread evenly and leveled carefully.
s1/2
Wooden trowels shall be used and concrete will be leveled carefully. /ss.
="-,
During Concrete the Low places shall be filled, humps removed and the whole Surface sh81r,bp
again leveled.
LARSEN & TOUBRO LIMITED

e
Quality Management System
B U I L D I N G S & F A C T O R I E S I C
India International Convention & Expo Centre (IICC),
L&TRICC/QAQUARCH/MS17005/R0
Sector-25 Dwarka , New Delhi

Doc Title: Method statement for Screed Page 7

The layer shall be compacted by ramming or by vibrator and troweled and allowed to set.
Ensure that over vibration to the concrete is not done.

D. Groove Cutting Post Screed ( Within 72 Hours of casting)

Post screed level sheet will be made by Survey & Site Team.
When the surface is free from residual bleed water and is sufficiently hardened to allow light foot traffic groove cutting
will start.

Marking of the grooves will be done by survey and site team.


With the help of a diamond groove cutter the grooves will be cut as per Architecture detail design.
The depth of the groove will be a maximum of 1/4 the thickness of screed that is a maximum of 25 mm

The width of the groove will be 2-5 mm


Post completion of activity final survey sheet will be prepared and attached with IR.

E. Curing
Curing shall be carried out for 6 Days by keeping the screed moist.
Curing register will be maintained on site.

9. QUALITY ASSURANCE & CONTROL

Ensure necessary testing/checking is done as per ITP. Daily records of quality checks shall be maintained.

Guidelines for Good Workmanship as per technical specs shall be followed.

10. RECORDS
All mandatory Registers/records of EMPLOYER/EMPLOYER'S ENGINEER shall be maintained for the Project.

1) ITP
2) Check List
3) HIRA
4) Drawing No- 017203 -A-SP-38WD-1105
5) Drawing No- 017203 -A-SP-38-WD-2105

6 40
' r-2 5,
i

LARSEN & TOUBRO LIMITED • BUILDINGS & FACTORIES IC QUALITY mANAGEmENT SYSTEM

India International Convention & Expo Centre (IICC), Form no:


Sector-25 Dwarka , New Delhi
L & T / 9 F / f I C C / C L / 0 0 0 5 / R O

CHECKLIST -SCREED

AREA I BUILDING: Date:

FLOOR NO: GRID REFERENCE:

S.n DRAWING REF:


o SAFETY
A B PROCESS CHECK
YES NO NA YES NO NA

1 Are all necessary PPEs provided to all the staff 1

1 Li

and labours I
Ensure level pads or spots provided

2
2 Has all workers trained about the hazards in Ensure Survey sheet of Level dabs as per slope given in
Plastering drawing. I I-1

3 is Risk Assessment report available for this I


PI 3 Ensure the joints are treated with 300 mm wide GI Mesh
potential activity
4
4 Is hard barricading for slabs, life line around I I 1 .

1
1 Ensure that panel size does not exceed 16 sornt
slab & safe access provided to work place

5 Is adequate illumination provided to work at ' 5

I 1 11
Ensure alternative casting of panels
night

6 Is surplus Materials stacked sufficiently away

7
from work place

I I
1 I 6 Ensure proper vibration of of Screed and avoid over vibration
PI
LI
Are proper warning signage's provided at site 1 I 7 Ensure Groove cutting as per MST/ Approved Drawing
I

8 Whether staging is provided on firm / well

Fl
n Prepare Post Screed Survey Sheet
compacted ground/concrete and firmly fixed n n 8

9
Whether staging walkway provided to workers
for their safe access movements q L i ____

II
10 Check for Housekeeping and rubbish removal
in vicinity

PRE CHECK Post Check

I.
1 Check for Side shuttering of panels 1 Check for finishing
1 1 ❑

2
2 Ensure the surface must be clean, free from Checkfor
dust, loose material and other harmful Curing
Register
materials
3
Ensure only alternative panels to be casted
I
4
Ensure level pads are made with concrete

5 Ensuremarkingsdoneonsideformwork/channelfortoplevelofScreed
1

Remarks

01
-
1 S ti.-

7-' ::',"

EPCC EMPLOYER/EMPLOYER'S ENGINEER EPCC EMPLOYER/EMPLOYER'S ENGINEER


INSPECTION & TEST PLAN
PROJECT: INDIA INTERNATIONAL CONVENTION & EXPO CENTER (IICC) PROJECT Form No. Client : IICC Ltd

Doc No. : L&TIIICC/CIAQUARCH/MST10051R0


IICC LTD MST! ITP NO:
L&T-IICC•QAQC-ITP-ARCH-SCREED.005/R0
NAME OF CLIENT: AECOM INDIA PVT LTD
NAME OF PMC : L&T CONSTRUCTIONS REV NO: 0 Page : 1
NAME OF CONTRACTOR: DATE: 2.04.2019

-,---t-- - - - - - ._._
Employer/Emipoyer's
SIN Component Reference Document Acceptance Criteria Format of Record QCP Vendor/Sub-contractor L&T Engineer
Nature of Check I Test Method of check Quantum of Check
!

o. /process QHP
E C W C W IR C 1W ,R
M aterial Delivery

r
a Cement Inspection/Review Each Load IS MTC ✓ ✓ ✓ ✓ ✓

✓ ✓ ✓ ✓
b Sand - Silt Correction & Sieve Analysis InspectionlReview Each Load IS 1542 LTR ✓ ✓
1

✓ ✓ r
c Water Inspection/Review Once in 3 months IS 456 Third Party Lab Report ✓ ✓ ✓

✓ ✓
d Aggregates- Sieve Analysis InspectionlReview Each Load IS 383 LTR ✓ ✓ ✓ ✓

Execution of Works

Surface Preparation

Check for Clean Surface and Cleaning has been done Visual All works Approved Drawings

Checksheet:L&T/BF/IICC/F/CL1005/R0 ✓ ✓ ✓ ✓
a
As per approved drawing, Method ✓ ✓ ✓
Preparation of Level Pads with concrete Check All works _ Statement & Technical
Checksheet::L&T/BF/IICC/F/CL/005/R0 ,/' ✓

specification. ✓ ✓ ../
2 Side Formwork with Check All works Approved Drawings Checksheet::L&T/BRICC/FICL1005/R0 ✓ ✓ ✓

✓ ✓ ✓
Survey Sheet Check All works Approved Drawings Surcey Sheetr ✓ ✓ ✓

.
Laying of Concrete
b
✓ ✓ ✓
Ensure proper Vibration Check All works Check List ChecksheerL&T/BRIICC/F/CL/005/R0 ✓ ✓ ✓

Cutting of grooves Check All works Check List ChecksheeLL&T/BF/IICC/F/CL/005/R0 ../ ✓ ✓ ✓ ✓ '

Post Execution
Check for Levelling and Finshing Survey r r r r
a All works Check List & Survey Sheet r v

Curing
___.....-_,_ ...... .- -..,.. ..L ...„ ,.. .,.
4
a Check for curing as per approved MS Inspection All works As per Approved MS
Note : Far this ITP all standard specifications, code of prectice, shall general] be the latest edition, and including all applicable official amendments and revisions
QCP QUALITYCONTROLPOINT
NAME Pr bhat S upta T. N. Anandan
QHP QUALITY HOLD POINT
SIGNATURE ,

1 ' r-i J'r'-'-'-'F-' LTR LAB TEST REPORT

QAIQC M er QAJQC Head (L&T) EMPLOYERS ENGINEER W WITNESS POINT

PREPARED BY REVIEWED BY APPROVED BY S SURVEILLANCE

E EXECUTE

R RECORD REVIEW

C CHECK

et