Professional Documents
Culture Documents
FOR INFORMATION
Manuel
First Issue 03-07-2021 Abaid Ullah
Muniz
Ali Rana
Project:
SHUQAIQ III INDEPENDENT WATER PROJECT
Contractor:
Acciona Agua
Document Title:
TABLE OF CONTENT
ITEM NO.: DESCRIPTION
1. PURPOSE
2. SCOPE OF WORK
3. SUBMITTALS
4. MATERIALS
5. WORKMANSHIP
6. STANDARD
7. PROJECT MANAGEMENTS
11. DISINFECTION
13 SAFETY
14. ENVIRONMENT
1.0 PURPOSE
This procedure establishes the instructions for the preparation and control of Inspection and
Test Plan (ITP) for plumbing & Sanitary work activities and notification to Acciona Agua
management for their selected inspection point in a timely manner. The method statements
applied to the installation of water supply and drainage for Shuqaiq III IWP.
3.0 SUBMITTALS
A. Product Data: Submit manufacture’s product data, including test reports for each type of
cPVC accessories and other manufactured products, as well as certifications of compliance
with the specified requirements for each type. B. Submit cPVC samples
showing color and texture for engineer selection and approval.
4.0 Materials
Schedule” will be submitted. Total care shall be taken to ensure that the materials that finally
arrive at site and meet all requirements of SHUQAIQ III IWP.
5.0 WORKMANSHIP
6.0 Standards
All work shall be performed accordance with this method statement and the following
standard, codes, and references.
ASTM D1784 or ASTM D 2729 standard specification for unplasticized Polyvinyl Chloride
(cPVC) pipe,
No permanent works will commence until such approval has been given.
Beginning of the Project. Any revisions to the site organization will be duly
Management.
issued at the end of the project. These instructions will have to be formally
The site engineers shall co-ordinate with other Departments handling other services
8.1 Make sure that walls are at least rough-plastered and finish levels are
marked by the civil contractor. If proper final levels are not marked, the
SHUQAIQ III IWP
pipes could be too deep or too shallow inside. Pipes deep in the wall will
8.4 Assemble piping starting from branch left in shaft and install in the wall
8.6 Plug all openings and test the pipe work for leaks under specified pressure
authorized personnel.
8.8 Close the wall chases with cement mortar. If site conditions require a depth
9.2 Locate and mark positions of soil and waste outlets. Make core drills where
necessary.
9.3 Assemble pipe headers and connect them to branches left in the shaft for
SHUQAIQ III IWP
9.4 Make sure that pipes are in proper slope and are supported adequately.
that floor traps are installed in level (not tilted) so that the water seal is not
diminished.
9.6 Supervise the filling of sunken floors by civil team so that the
9.7 Keep all open ends plugged to prevent ingress of construction debris.
All installation works shall be as shown on the drawings and shall conform to the applicable
ASTM standards.
All fixtures shall be fastened and/or supported in accordance with the given requirements.
Flush the installed pipe work (water supply and drainage) to remove debris or
blockages, if any.
Check CP fittings for leaks and firmness. Refit them if necessary. Ensure
that proper tools are used. They must not make scratches or any other kind
11 Disinfection
put to use. The following simple procedures will ensure satisfactory results:
Flush and clean water tank(s) and distribution pipe work with potable
Fill the tank(s) with water mixed with chlorine solution at the rate of 50
parts per million. Retain chlorinated water in the system allowing the
Repeat the procedure till odor of chlorine is felt at all locations when
Checked at random.
Drain out chlorinated water and fill the system with potable water.
QA/QC Engineer will be in close contact with the representative of Client during the entire
operation.
QA/QC Engineer in association with site Engineer will be responsible for the implementation
of the inspection stages as this is required by the ITP.
QA/QC Engineer and site Engineer will be in close cooperation, coordination with Client
during the process/progress of the work in order to implement the inspection requirements.
QA/QC Engineer shall be responsible for site inspection/test activities, co-ordination with
concerned authorities of the Client.
Maintain records of quality control checks and mark up arrangement drawings to record the
location.
All the above work will be continuously monitored as the work proceeds. Records of these
inspections and quality control inspection reports shall be maintained for final documentation.
13.0 SAFETY
care shall be taken as regards all the safety aspects of the works. Relevant
on the installation.
All works are to be carried out in accordance with the site safety plan.
Assessment of Risks
(PLUMBING WORKS)
13.1.1 Falls from height, trip hazards, slipping hazard, electrocution, spillage of hazardous
substance, injury, and scaffolding overturn.
13.2.1 Fall of persons and materials, Manual Handling, electrocution, water pollution, soil
pollution, scaffolding overturn, Tool injury to people, Injury due to wire or rebar, material
storage, unsafe act, unsafe condition, material collapse during lifting,
13.3 NB. A Full Separate Job Specific Risk Assessment Must be Prepared and Attached
Training to the workers, fall prevention and fall protection, toolbox meeting before starting the
work, safe working procedure, proper tools and tackles, Worn proper PPE’s. Signage, tag line
while lifting materials, proper barricade, qualified and trained persons for the job, manual
SHUQAIQ III IWP
handling, material handling, proper stacking of tools and materials, proper housekeeping,
store all the hazardous materials in the bonded area.
Safety Helmet, Safety Glass, Safety Vest, Safety Shoes, safety Harness in the high level,
Hand gloves, Leather Hand Gloves for hot Work, latex coated gloves for electrical works, face
shield for cutting and grinding works
Provide First aider and fire watcher to all area, the emergency contact number must be
displayed in the site, all the access and aggress should be clear all the times.
Always keep fire extinguisher near the work area, All the access and aggress to the work
area should be clean, Gas cylinders must be stored in proper place
13.3.5 Information to
The site Engineer will inform the method of statement to the Supervisor and the
workers.
The supervisor will monitor the work all the time and the site engineer will instruct them
regarding the work activities and the project manager will control all the work activities. The
HSE person will monitor the safety and environmental aspect regarding the day to day work
activities.
13.3.7 Attachments:
SHUQAIQ III IWP
Risk assessments,
14.0 ENVIRONMENT
Pollution and soil pollution due to spillage of cement or leakage of oil, gas from vehicles or
equipments
Keep all the hazardous substance in bonded area, do not keep any hazardous materials near
the working areas , Keep dip tray for all equipments, avoid oil spillage from the vehicles and
equipments.
The Environment Engineer will control all the spillage to avoid the water, soil and air
pollutions.