Professional Documents
Culture Documents
w w w. a s p i r e b r i d g e. o r g
Photo: DSI.
Departments
Editorial 2
12 Concrete Calendar 4
Perspective—Quantitative Assessment of
Resilience and Sustainability 10
Aesthetics Commentary 27
Concrete Bridge Technology—Observations
from 30 Years of Inspecting Post-Tensioned
Structures 28
Concrete Bridge Technology—Seismic Behavior
of Reinforced-Concrete-Filled Steel Tubes 32
Concrete Bridge Technology—Sarah Mildred
Long Bridge Tower Foundation Construction 34
Photo: Johnson, Mirmiran & Thompson. Concrete Bridge Technology—Implementation
of an Electrically Isolated Tendon Post-Tensioning
System in the United States 36
Advertisers’ Index
DYWIDAG-Systems Max USA Corp. . . . . . . . . . . . . . . . . . . . .44 Poseidon Barge Ltd . . . . . . . . . . . . . . . . . 11
International USA Inc. . . . . . . . . . . . . . . .5
Mi-Jack Products Inc . . . Inside Back Cover Stalite . . . . . . . . . . . . . . . . . . . . . . . . . . .31
FIGG . . . . . . . . . . . . . . . . Inside Front Cover
PERI . . . . . . . . . . . . . . . . . . . . . .Back Cover Williams Form . . . . . . . . . . . . . . . . . . . . .52
HDR Inc. . . . . . . . . . . . . . . . . . . . . . . . . . .3
PCI . . . . . . . . . . . . . . . . . . . . 15, 27, 45, 50
Photo: PCI.
Designing for versatility will be key as technology improves life Dr. Reid W. Castrodale
Technical Editor
William N. Nickas, Editor-in-Chief Dr. Krista M. Brown
Program Manager
Nancy Turner • nturner@pci.org
A s members of the bridge engineering profession,
we want our structures to have a service life of
75–100 years or even longer. None of us wants to see a
example, the slab tracks originally designed for buses
might be adapted for elevated, personal autonomous
vehicle pods. If that happens, we will need to formulate
Associate Editor
Emily B. Lorenz • elorenz@pci.org
20-year-old bridge removed for structural or operational operational protocols, such as how to manage a Copy Editor
reasons. But, if we are to build long-lasting bridges, we disabled autonomous vehicle on a confined corridor. Elizabeth Nishiura
need to anticipate the vehicular trends of the future. My Will connected trucks operate in the corridors and on
Layout Design
curiosity about those trends was sparked earlier this year structures? That innovation could have implications
Walt Furie
when I attended the Transportation Research Board’s for the strength requirements of the structures or the
annual meeting, where participants could observe and weight limit of the individual trucks. Editorial Advisory Board
ride the Federal Highway Administration’s autonomous An area of uncertainty is throughput in our future William N. Nickas, Precast/Prestressed
vehicle. I then attended a chapter meeting of the traffic systems. I have heard it might increase, but it Concrete Institute
International Bridge, Tunnel and Turnpike Association, could decrease if computer-controlled autonomous Dr. Reid W. Castrodale, Castrodale
where I was eager to learn what financial professionals vehicles require increased headways to reduce the risk Engineering Consultants PC
and transportation planners envision for the future of for collisions. When autonomous technologies control Gregg Freeby, American Segmental Bridge
Institute
bridges and highways. vehicles, exceeding the speed limit will not be an option.
Pete Fosnough, Epoxy Interest Group of the
One crucial variable in bridge design is the Researchers are currently engaged in studies to Concrete Reinforcing Steel Institute
fleet of vehicles that will be on the roads in future model how emerging vehicular technologies will affect Alpa Swinger, Portland Cement Association
decades. Trend watchers predict that electric vehicles the functioning of households, and they have already Miroslav Vejvoda, Post-Tensioning Institute
will be one-third of the inventory by 2040 and one- noted differences between urban and rural areas of Cover
half of the inventory by 2050. They also anticipate the United States. In some cases, autonomous vehicles DYWIDAG-Systems International provided the
that autonomous vehicles will be on the roads soon, and phone-based applications will likely select routes post-tensioning for the Gerald Desmond Bridge
although the widespread impact of these vehicles on the that are not on the current mainline arterials, perhaps in Long Beach, Calif. Photo: DYWIDAG-Systems
transportation network is harder to predict.1 to avoid tolls or heavy traffic. At the same time, our International.
vehicles and phones will collect data on our driving Ad Sales
routines and preferences and use that information to Jim Oestmann
make subsequent decisions about what routes to take Phone: (847) 924-5497
and what tolls will be incurred. Fax: (847) 389-6781 • joestmann@arlpub.com
Pilot projects in Colorado and Ohio will answer some
Reprints
questions about vehicle-to-vehicle and vehicle-to-road Lisa Scacco • lscacco@pci.org
communications. As we gather insights, we’ll need to
Emerging vehicular technology promises to decide what capital programs will be needed to make Publisher
change human habits in ways that will directly affect the transportation system of the future work. Now is a Precast/Prestressed Concrete Institute
transportation solutions, including fundamental aspects great time for bridge engineers to get engaged so we Bob Risser, President
of bridge design such as lane geometry and access can understand how new technologies will influence Postmaster: Send address changes to ASPIRE, 200 W. Adams St.,
Suite 2100, Chicago, IL 60606. Standard postage paid at Chicago, IL,
points. For example, commuters may not care so much our roadways, bridges, and interchanges. This is also and additional mailing offices.
ASPIRE (Vol. 13, No. 2), ISSN 1935-2093 is published quarterly by the
about personal time spent in traffic if they can relax the time to start reviewing the design assumptions Precast/Prestressed Concrete Institute.
while their autonomous cars drive them home. Their underlying our bridge codes. Will our investment in Copyright 2019, Precast/Prestressed Concrete Institute.
incentive to pay tolls for express lanes or to use managed variable toll rate commuter lanes with bridge assets If you have a suggestion for a project or topic to be considered for
ASPIRE, please send an email to info@aspirebridge.org
lanes restricted to passenger vehicles may therefore become a feature whose use will need to be redefined
decline. But parcel delivery businesses might be willing to carry heavier trucks or platoons of trucks? With
to pay a premium to access faster lanes and bridges and connected vehicles, like a platoon of trucks, what bridge
shorten the time that their vehicles spend in traffic. code design assumptions will need to be revisited and
Reference
I also wonder whether we will soon be designing how will these new load effects be reconciled with the 1. SP Global. 2018. The Road Ahead for Autonomous
bridges for mass-transit, fixed-guide systems with ride- inherent capacity of our existing inventory? I certainly Vehicles. International Bridge, Tunnel and
share and autonomous-vehicle technologies. If so, we hope our bridge colleagues in leadership roles are Turnpike Association. https://www.ibtta.org/studies-
may need to revisit older transportation solutions. For helping to identify consistent and prudent strategies. and-reports.
American Segmental Bridge Institute Epoxy Interest Group Expanded Shale Clay and Slate Institute
Portland Cement Association Precast/Prestressed Concrete Institute Post-Tensioning Institute Wire Reinforcement Institute
4 |4ASPIRE
| ASPIRE
Spring
Spring
2019
2019
www.dsiamerica.com
FOLLOW US ON
For information on the benefits of segmental bridge construction and ASBI membership visit: www.asbi-assoc.org
Changing Perceptions
DYWIDAG-Systems International’s new high-tech inspection and monitoring tools
add to its selection of post-tensioning products and services, enhancing its role as a
specialty contractor.
by Craig A. Shutt
Quantitative Assessment of
Resilience and Sustainability
by Dr. Jeremy Gregory, Massachusetts Institute of Technology
Sustainability is a word that is conditions is a measure of resilience that quake shattered roads and bridges,
ubiquitous, yet often vague. At the is vital to understanding sustainability, destroyed neighborhoods, disrupted
Massachusetts Institute of Technology particularly in regions where climate- livelihoods, and killed an estimated 139
Concrete Sustainability Hub (CSHub), related events are becoming increasingly people.3 In response to the earthquake,
we have a concise mantra: “We want frequent and destructive. authorities established more rigorous
our world to last.” This saying helps us building codes intended to protect
clarify what we mean by sustainability Resilience, an important element of buildings from future seismic activity.
with regard to the structures we build, sustainability, can be quantifiably Alaska’s successful response to the 2018
including bridges. Such structures measured in two stages, response earthquake is due, in large part, to the
will remain sustainable only if civil and recovery (Fig. 1). First, we assess changes implemented in building and
engineers are farsighted. Many aspects the system’s immediate response to bridge design codes.1
of a structure, including its future an event. For example, let’s imagine
economic impact and the environmental that a city experiences a hurricane. Alaska’s rapid recovery demonstrates
conequences of construction, repairs, Before the storm arrives, the city how efforts to improve resilience can
or replacement, affect its sustainability. operates at peak performance, as deliver a return on investment (ROI).
Our research finds that quantitative indicated by parameters like economic If stakeholders remain unaware of
assessment of these factors can lead to productivity, transportation efficiency, the ROI of resilience, success stories
alternatives that improve a structure’s and so on. As the storm ensues, the like that of Alaska in 2018 will occur
sustainability (see http://cshub.mit.edu/ city’s performance will drop because less frequently. Calculating this ROI
news/lca-research-brief-quantifying- o f e c o n o m i c i n a c t i v i t y, d i s a b l e d is therefore a key aspect of CSHub’s
hazard-life-cycle-cost for more infrastructure, and other damages. work, and, to do it, a probabilistic
information). The extent of the drop in performance hazard repair estimation model has
is the first measure of resilience—a been developed.
Sustainability analyses are usually smaller reduction in performance
conducted by considering a structure’s indicates greater resilience. The second The crux of this model is the probability
typical loading conditions throughout measure of resilience is the time to curve, which allows us to analyze the
its life. An additional important recovery to a performance level that uncertainties of disaster and predict
consideration is the structure’s response may be lower than, the same as, or outcomes. Using government and
to atypical loading conditions, such as higher than the performance level other scientific data, we can generate
those caused by natural or human-made before the disaster. A rapid and strong a probability curve that estimates
disasters. A structure’s response to such recovery signifies effective resilience. the likelihood of a hazard in a given
location. We refer to this as a hazard
A recent example of resilience can curve (Fig. 2).
be seen in the aftermath of Alaska’s
November 2018 7.0-magnitude The hazard curve’s counterpart in
earthquake. While the photos of resilience analyses is the fragility curve
crumbled highways were dramatic, the (Fig. 3), which estimates the damage
actual devastation was not extensive. a hazard will inflict on a structure. To
Authorities reported no fatalities and generate fragility curves, we employ
no collapsed buildings, and seriously a technique inspired by molecular
damaged roadways were repaired dynamics. We model the integrity of a
within days. 1,2 Pundits therefore structure’s components like we would
declared the state’s response to the the bonds of atoms. This methodology
disaster a success. allows us to efficiently estimate the
effects of hazard-induced loads on
Figure 1. Resilience has two parts—initial Alaska has not always enjoyed these components. What makes this
response to a damaging event (the drop such resilience. In 1964, the state technique unique is its versatility
in performance) and recovery time. All experienced the largest earthquake and precision. Whereas conventional
Figures: Dr. Jeremy Gregory. in U.S. history. This 9.2-magnitude models of building fragility approximate
REHABILITATING
MARYLAND ROUTE 195
(CARROLL AVENUE) BRIDGE OVER SLIGO CREEK
by Fred Braerman, Johnson, Mirmiran & Thompson, and Maurice Agostino,
Maryland Department of Transportation, State Highway Administration
The Maryland Route 195 (Carroll Avenue) Sligo Creek, and a county-owned trail access to all four approaches to the
Bridge over Sligo Creek, located in the for hiking and biking. In 2011, the bridge.
Washington, D.C., suburb of Takoma MDOT State Highway Administration
Park, Md., is a nonredundant, open- (SHA) Office of Structures contracted During the planning stage, several
spandrel, reinforced concrete arch bridge the bridge design engineer to project-specific challenges were noted.
that carries one lane of traffic in each perform an in-depth field inspection, The bridge’s location, 50 ft over a ravine
direction, with sidewalks on both sides. structural analysis, and assessment of within the floodplain of Sligo Creek,
Nearly 80 years after being constructed the bridge. Because the bridge was constrained the project site. Existing
in 1932, the bridge became rated eligible for inclusion on the Historic utilities on the bridge and adjacent
structurally deficient in 2011, when Register and on MDOT SHA’s Priority 1 overhead utilities on the west side of
routine inspections found extensive and list for preservation, the bridge design bridge would have to be temporarily
worsening deterioration of the bridge engineer focused on rehabilitation relocated to allow for construction.
deck. While evaluating options for this strategies. Sligo Creek Parkway, located beneath
aging structure, Maryland Department of the southernmost span, was a major
Transportation (MDOT) officials recognized The bridge design engineer’s findings commuter route within this congested
the functional and historic significance of indicated that replacement of all suburb, and a heavily used hiker-biker
the bridge and concluded that replacing it portions of the bridge above the arch trail located beneath the northernmost
with a girder-type structure would not be ribs would be required to address the span would need to remain open
the right solution. Instead, MDOT decided extensive deterioration of the deck, floor during rehabilitation.
that rehabilitation was the appropriate beams, columns, and spandrel arches.
strategy, a decision that was well received The plan was to repair and preserve the Project leaders conducted extensive
by the community. A construction existing substructure units and arches public outreach to gain input and
contract was awarded to the prime while reconstructing the remainder of support from the community. For
contractor for $9.3 million in October the bridge from the arch ribs up. The example, they held multiple public
2015, and the project was completed less complete reconstruction of the bridge meetings and coordinated plans with
than one year after the bridge was closed above the arch ribs would allow for the Washington Adventist Hospital on the
to traffic. The bridge was reopened ahead structure to be widened curb-to-curb by north side of the bridge, the Takoma
of schedule in June 2017. 2 ft, creating 11-ft-wide travel lanes. The Park City Council, the Montgomery
community wanted wide shoulders to County Transit bus system, Montgomery
Planning and the make biking safer in this residential area. County Parks, and local emergency
Decision Process responders.
Originally built with non-air-entrained Additionally, the rehabilitation would
concrete and black reinforcing steel, include new sidewalks on both sides Design Challenges
the 220-ft-long Carroll Avenue Bridge of the bridge, with new sections of When a bridge is rehabilitated, its
has span lengths of 65, 90, and 65 sidewalk extending past the ends of the geometry must be maintained. The
ft and traverses Sligo Creek Parkway, bridge to provide improved pedestrian existing Carroll Avenue Bridge was
profile MARYLAND ROUTE 195 (CARROLL AVENUE) BRIDGE OVER SLIGO CREEK /
TAKOMA PARK, MARYLAND
BRIDGE DESIGN ENGINEER FOR REHABILITATION: Johnson, Mirmiran & Thompson, Hunt Valley, Md.
PRIME CONTRACTOR: Kiewit Infrastructure South, Omaha, Neb.
REINFORCING STEEL SUPPLIER: Gerdau, York, Pa.
OTHER CONSULTANTS (ROADWAY AND TRAFFIC DESIGN): Mercado Consultants Inc., Ashton, Md.; Sabra
and Associates Inc., Columbia, Md.
View of completed
Carroll Avenue
Bridge from Sligo
Creek trail.
PCI Offers FREE Bridge Geometry Manual and Training
A Bridge Geometry Manual has been developed as a FREE resource that presents the basics of roadway geometry and many
of the calculations required to define the geometry and associated dimensions of bridges. Four FREE instructor-led training
(ILT) courses have been developed to facilitate the use of the Bridge Geometry Manual. The target audience for the Bridge
Geometry Manual and instructor-led training courses is bridge engineers with two or less years of experience and CAD tech-
nicians who have not had previous training in roadway and bridge geometry. Again, there is no cost to enroll in and complete
any of these courses being taught by the contracted primary author Corven Engineering Inc. or to download the new manual.
Corridor
existing Interstate 75
southbound lanes and is
over 1 mile long. Photo:
Aerial Innovations of
Express Lanes
Georgia Inc.
construction tolerance and to position the bridge, three types of intermediate design strength) before tensioning.
the precast concrete cap. The cap- piers were used: conventional The “U” shape also minimized the
column connection was established hammerhead on a single column, lifting weight (210 kip) and provided
using a filleted rectangular blockout inverted-tee hammerhead on a single part of the formwork for the cast-
(with 7.375 in. chamfers at each column, and inverted-tee straddle in-place concrete after the precast
corner) in the precast concrete cap. bent on two columns. The inverted- concrete member was erected on the
Headed dowels, confined by heavy tee hammerhead pier caps were used columns. The prestressed beam seats
transverse reinforcement, reinforced the in two of the intermediate bents to were constructed as part of the precast
connection zone. mitigate the limitations on the available concrete section, with 2-ft 2-in.-wide
vertical clearance under the bridge. ledges on each side of the 5-ft-wide
The precast concrete cap reinforcement core precast concrete section. During
was detailed to avoid conflict with A straddle bent was selected primarily a temporary nighttime (11:00 p.m. to
the headed dowels. The size and because of the sharp skew angle and to 4:00 a.m.) shutdown of the existing
re i n f o rc e m e n t d e t a i l i n g o f t h e keep the maximum span lengths around southbound I-75, traffic was detoured
connection were designed to utilize 150 ft, which would make the best use to adjacent roadways and I-285. During
standard strength concrete (f’ c = 4.5 of precast concrete girders. The location this time, two 300-metric-ton mobile
ksi). Constructing the pier column from of the straddle bent was chosen to hydraulic cranes were used to lift the
the I-75 shoulder and using precast minimize its length and to balance loads cap and place it on top of the columns.
concrete elements efficiently minimized from the adjacent spans. The formwork for the cast-in-place
both traffic disruptions and the portion of the bent cap was then lifted
environmental impact of the project. To make the straddle bent, a fill and connected to the precast concrete
embankment with the same slope as section. The cast-in-place concrete was
Precast, Post-Tensioned the final slope of the precast concrete placed later with protection measures
Straddle Bent Caps bent cap was constructed; this in place while traffic was maintained
At a second site, an 806.5-ft-long, facilitated geometric control of the below.
six-span bridge carries the I-75 formwork and the post-tensioning
express roadway over the existing ducts. The precast concrete bent cap The cast-in-place portion of the bent cap
I-75 southbound lanes. The roadway’s was cast on site, adjacent to the final reached a minimum strength of 5 ksi
horizontal alignment at the bridge bent location, and post-tensioned and before the prestressed concrete girders
is highly skewed with respect to the grouted while on the ground. The were erected. To maintain structural
roadway below and consists of two precast concrete cross section was a stability of the precast concrete section
reverse curves with a short tangent “U” shape to allow for seven ducts, after erection on the columns, the top of
between the curves. The overall width each with nineteen 0.6-in.-diameter the 5-ft-wide column was flared to 8 ft 6
of the bridge varies from 29 ft 3 in. to strands tensioned in a single-stage post- in. wide in the longitudinal direction. The
35 ft 3 in. tensioning operation. The concrete for precast concrete cap width was similarly
the cap was at least 14 days old and flared to 8 ft 6 in. to accommodate two
Given these geometric constraints and had reached a compressive strength bearings at each column.
the presence of existing roadways under of 7 ksi (which was also the 28-day
WATER RESOURCES
Concrete I Roller Compacted Concrete I Soil-Cement
DAMS
OVERTOPPING PROTECTION
FLOOD CONTROL
EMBANKMENT PROTECTION
WATER SUPPLY
LINERS
www.cement.org/water
The Brotherhood Bridge (also known as girder structure, was built and named the requirements became more stringent,
the Mendenhall River Bridge) is located “Brotherhood Bridge” to commemorate the need for a replacement bridge
near Juneau, Alaska, about five miles the 50th anniversary of the Alaska Native became apparent. Construction of the
downstream of the Mendenhall Glacier. Brotherhood (ANB). replacement bridge began in April 2014.
The project, which has interesting The new bridge, which was rededicated
historical connections to the region’s Roy Peratrovich Jr. was an engineer for in October 2015, retains the name and
Native Alaska community, faced several the Alaska Department of Highways decorative bronze medallions that are a
unique design challenges not often team that designed the 1965 key part of the Brotherhood spirit.
encountered outside of Alaska and structure. He is a Tlingit of the Raven
incorporates many features commonly Lukaax.ádi clan, the first Alaska Native Geological and
used by the Alaska Department of person registered as a professional Hydrological Considerations
Transportation and Public Facilities civil engineer in Alaska, and the son The Mendenhall Glacier is viewed
(AKDOT&PF). of prominent Alaska Native civil rights by more than 500,000 tourists every
leaders Elizabeth and Roy Peratrovich year. Currently, the face of the glacier
History Sr. In honor of the ANB anniversary, is located about 1.5 miles from the
Five bridges have been built to cross the Peratrovich Jr. sculpted 10 bronze Mendenhall Glacier Visitor Center;
Mendenhall River at this location. The first medallions with the ANB crest and however, several hundred years ago, the
road crossing at the river, a timber trestle, imagery, which were incorporated into face of the glacier was located near the
was constructed in 1903 for a total the bridge rail of the 1965 structure. bridge site. As the glacier has retreated,
cost of $1700. The timber trestle was the surrounding ground surface has
reconstructed in 1919 and then replaced The bridge served the community risen due to isostatic glacial rebound. At
with a single-lane, two-span steel truss well for about five decades. But, as the bridge’s location, the ground surface
in 1931. In 1965, the fourth bridge, a the weight of trucks increased, traffic is rising at a rate of about 1 in. per year.
two-lane, three-span continuous steel demands grew, and design code Consequently, the river is incising and
Built in 1940, the original Maine– design would have made her proud. for vehicles, rail lines, and maritime
New Hampshire Bridge spanning the The previous structure had five main vessels. With the new bridge, maritime
Piscataqua River between Portsmouth, truss spans, including the vertical lift vessels can navigate the Piscataqua
N.H., and Kittery, Me., served as the span, along with 15 roadway spans on River while the upper segmental-
critical backup route between Maine the Portsmouth side and seven on the approach superstructure carries U.S.
and New Hampshire if traffic were Kittery side. The new Sarah Mildred Route 1A (Bypass) and the lower
disrupted on the Interstate 95 Bridge Long Bridge has twin segmental- segmental superstructure connects
upstream. In 1987, the Maine–New concrete approach spans in a stacked Pan Am Railways, a railroad system for
Hampshire Bridge was renamed to configuration leading to a single-deck the Northeastern United States, to the
honor Sarah Mildred Long, an employee hybrid movable span at its center. Portsmouth Naval Shipyard. The movable
of the Maine–New Hampshire Interstate hybrid span rises to allow passage of
Bridge Authority for 50 years. The new structure’s design, which tall vessels and lowers to railroad-track
provides a unique concept for a level for trains to cross, remaining at
Three decades later, on March 30, segmental bridge, improves the skew the vehicle level in its resting position.
2018, a replacement bridge, also angle and width of the navigation The Portsmouth, Me., approach spans
named for Long, opened. Its innovative span as well as safety and efficiency extend over Market Street and the Pan
The new Sarah Mildred Long Bridge between Maine and New Hampshire over the Piscataqua River features twin segmental-
concrete approach spans in a stacked configuration leading to a single-deck, hybrid movable span at the bridge’s center. Photo: FIGG
Engineering Group.
profile SARAH MILDRED LONG BRIDGE / PORTSMOUTH, NEW HAMPSHIRE, AND KITTERY,
MAINE
BRIDGE DESIGN ENGINEERS: FIGG Bridge Engineers, Tallahassee, Fla., and Hardesty & Hanover, New York, N.Y., a
joint venture
PRIME CONTRACTOR: Cianbro, Pittsfield, Me.
POST-TENSIONING CONTRACTORS: GZA GeoEnvironmental, Boston, Mass.; Sebago Technics, Portland, Me.
span)-200-320-200 ft. The lower railway lengths. As a result, 11 fewer piers 5-ft 7-in.-wide median that contains the
level consists of 16 spans: 60-100-160- were needed in the waterway, and railroad tracks.
160-160-160-135-65-35 (tower span)- an existing median pier on Market
300 (lift span)-35 (tower span)-65-135- Street was eliminated, improving the Modified Tower
160-160-100 ft. Many of the railway gateway span leading into downtown Drive System
level’s span lengths are approximately Portsmouth. Several options were considered for
half the length of the vehicle level to the drive system to operate the
accommodate the heavier (Cooper The upper vehicular spans feature central 300-ft-long streamlined box-
E80) required live load. The goal was precast concrete segmental box girders girder lift span. Typically, two options
to maximize span lengths on each level with depths varying between 8 and are available. With a span drive, the
to reduce the number of piers in the 13.5 ft and base widths varying from machinery is located on the span,
waterway. 15 to 16.75 ft. The lower railway spans raising and lowering itself with
consist of precast concrete segmental the span. With a tower drive, the
The 160 ft length for the railway spans girders varying in height from 9 to 11 machinery, located at the tops of the
is significant for a segmental bridge ft, with top flanges of 19 ft and base towers, raises or lowers the span. For
and allowed for only an intermediate widths varying from 11.33 to 12 ft. The this project, a hybrid design provided
monoshaft pier to be used at the single-level lift-span deck is 42 ft 7 in. the best of both worlds.
midspans of the upper level’s 320 ft wide, with two lanes separated by a
The operating equipment is located at
the base of the four 200-ft-tall precast
concrete towers, on each corner of
the span. The machinery was placed
at the bases, providing easy access for
maintenance and inspection. Similar to
a span drive, the equipment uses uphaul
and downhaul ropes to physically pull the
span up and down and does not rely on
the friction of the counterweight sheave
to move the span. As with a tower drive,
the equipment is enclosed within the
towers, including mechanicals, wiring,
and even the maintenance stairway.
The counterweights were built with
steel plates inside a steel box. Steel was
selected after evaluating it against other
options, such as lead, to determine the
cost-benefit ratios and compare densities
to the total heights of the materials that
would be needed. The towers feature
glass windows that provide ambient
lighting for maintenance crews and also
allow drivers to see the counterweights
moving when the span is raised and
Each lift tower consists of 21 precast concrete segments cast at the project site using lowered.
match-casting procedures. Photo: Maine Department of Transportation.
The lift span features guide rollers that
57
correct starting geometry, the segments
Cost Efficiency of Precast were erected on temporary supports and
Concrete Towers properly adjusted, with a short closure
Precast concrete was chosen for the pour between the precast concrete tower
towers after all possibilities were segments and the cast-in-place footing.
evaluated. This option was most
efficient and cost effective because all
the equipment and setup needed for
Erection geometry was monitored
and adjusted as necessary to maintain
erection tolerances. The towers were
The
erection, post-tensioning, and epoxy capped with a precast concrete tower cap
joining for the tower segments were with cast-in-place concrete topping.
already on site for the precast concrete _____________
segmental superstructure.
Jeffrey S. Folsom, P.E., is assistant
th
bridge program manager with the
Each tower consists of 21 precast
Maine Department of Transportation in
concrete match-cast segments. Tower
Augusta.
AnnuAl
PCI DesIgn
The Sarah Mildred Long Bridge is an impressive eliminated the usual cross bracing and concealed
AwArDs
bridge that meets a set of complex functional re- the lifting equipment. At the same time, the
quirements while achieving a high level of visual haunched girders, which are deeper at the piers The 57th Annual PCI Design
quality suitable for its location within an area that where the forces are the greatest, and the solid Awards will open for entries
encompasses two historic cities and an attractive towers, rising from a massive base, provide an on May 20, 2019. Join us in our
natural setting. Meeting both the functional and impression of great strength. This impression is
aesthetic requirements of the project within a reinforced by the simple but robust modulation search for excellence and submit
reasonable budget required innovation in layout, of the concrete piers. your projects electronically
design, contracting arrangements, and construc- by August 19, 2019.
tion. That the design, construction, and client There is also a kind of delicacy at the tops of the
team was able to meet all of these requirements towers, which taper to reveal the counterweight
so successfully is a credit to all involved. sheaves. Because the sheaves are a visual feature,
the design conveys that the bridge is meant to
Visit PCi.org
Projects with this kind of functional complexity move. The sheaves are round, and things that are
often have a corresponding and unattractive round rotate. Why else would they rotate but to
visual complexity. The old bridge was an lift the center span? Finally, the vertical strips of
for more InformAtIon
example of that type of design. On the new tower windows that show the counterweights
AnD submIssIon DetAIls.
bridge, concrete segmental construction offered moving are visual compensation to drivers stuck in
a solution to the aesthetic challenges. On the the traffic backup as a ship or train passes through
spans, it allowed for fewer piers and simplified the crossing. Sarah Mildred Long would indeed be
the appearance of the girders. On the towers, it proud of the bridge bearing her name.
CONCRETE BRIDGE TECHNOLOGY
Observations from
30 Years of Inspecting
Post-Tensioned Structures
by Bruce Osborn, Structural Technologies LLC/VSL
The following article shares the author’s Unforeseen Challenges caused excessive bleeding in the tendons.
firsthand accounts of inspections of over
In the early years of post-tensioning, The presence of bleed water increased the
70 bridges and approximately 18,500
stressing was regarded to be the most risk of voids during the grouting process,
tendons. The author has inspected PT
impor tant aspect of the operation, thereby making the strands vulnerable to
structures in some of the most benign
and other details were believed to not corrosion. Voids discovered in this time
and harshest environments from Alaska
be as structurally significant. Even period were typically credited to excessive
to Puerto Rico, and in many locations
though grouting served as another layer bleed water, improper venting, poor
in between. The condition of each PT
of protection against corrosion of the grouting practices, or inadequate grout
bridge was determined through analysis
PT strands, it was often treated as an materials.
of data gathered from destructive and
afterthought and performed with limited
nondestructive investigations performed
supervision or inspection from an outside Notably, when inspections identified voids
on external and internal post-tensioning
party. Because the construction and in the grout within tendons, those voids
systems. In the former type of system,
inspection standards of past decades do were not always associated with significant
tendons run within the void in box
not meet today’s requirements, inspection corrosion. In most cases, voided areas
girders or cable-stayed bridges; in the
of older PT structures is important. could be regrouted to extend the service
latter type, ducts for tendons are cast
life of the structure and the PT system
within the structural concrete section.
Prior to 2000, grout used for tendons was within it. Figure 1 shows a borescope
The findings illustrate the evolution of
a simple mixture of Type I or II cement picture taken from the inside of a voided
PT structures since the 1970s, common
and water. In some cases, additives were tendon in a structure whose exterior
types of deficiencies, and how shifts
used to try to improve the protective condition was well maintained. The void is
in quality-control procedures have
characteristics of the grout. In later located at the top of the duct, and the steel
improved installation and extended the
years, it was proven that this combination within the tendon has not undergone any
life of PT structures.
of materials had segregation issues that major corrosion. This type of void is most
NEW! DC 45.1-18:
Recommendations for Stay Cable
Design, Testing, & Installation
References
1. Gonzalez, L., M.J. Kowalsky, J.M.
Nau, and T. Hassan. 2008. Reversed
Cyclic Testing of Full Scale Pipe
Piles . Repor t to Skyline Steel
Corporation. Report IS 08-13. 52
pages.
2. Gonzalez, L., M.J. Kowalsky, J.M.
Nau, and T. Hassan. 2009. Reversed
Cyclic Testing of Small Scale Pipe
Piles . Repor t to Skyline Steel
Corporation. Report IS 09-12. 53
pages.
3. Brown, N.R, M.J. Kowalsky, and J.M.
Nau. 2013. Strain Limits for Concrete
Filled Steel Tubes in AASHTO
Provisions . Final report to Alaska
University Transportation Center/
Alaska Department of Transportation
and Public Facilities. http://dot.
alaska.gov/stwddes/research/assets/
pdf/fhwa_ak_rd_13_05.pdf.
4. Brown, N.R, M.J. Kowalsky, and
J. Nau. 2015. “Impact of D/t on
Seismic Behavior of Reinforced
Concrete Filled Steel Tubes.” Journal
of Constructional Steel Research.
107: 111–123. DOI: 10.1016/j
Test setup to model reinforced-concrete-filled steel tubes in soil. Figure: Diego Aguirre.
.jcsr.2015.01.013.
RCFST piers were located within areas experienced any damage or signs of 5. Aguirre-Realpe, D.A., M.J. Kowalsky,
having a peak ground acceleration greater significant movement. J.M. Nau, and M. Gabr. 2017.
than 0.25 g during the 7.0-magnitude Seismic Performance of Reinforced
earthquake event on November 30, In summary, based on research over a Concrete Filled Steel Tubes in Soil.
2018. Even though many of these bridges 10-year period that indicated good Final report to Alaska Department of
were located in liquefiable soils, none performance of these systems, design Transportation and Public Facilities.
h t t p : / / d o t . a l a s k a . g ov / s t w d d e s /
Deformation of reinforced-concrete-filled steel tube during test in soil. Photo: Diego Aguirre. research/assets/pdf/4000-127.pdf.
6. Aguirre-Realpe, D.A, M.J. Kowalsky,
J.M. Nau, M. Gabr, and G.W. Lucier.
2017. “Seismic Performance of
Reinforced Concrete Filled Steel Tube
Drilled Shafts with Inground Plastic
Hinges.” Engineering Structures .
165: 106–119. DOI: 10.1016/j
.engstruct.2018.03.034.
7. Montejo, L.A., L.R. Gonzalez-Roman,
and M.J. Kowalsky. 2012. “Seismic
Performance Evaluation of Reinforced
Concrete-Filled Steel Tube Pile/Column
Bridge Bents.” Journal of Earthquake
Engineering . 16(3): 401–424. DOI:
10.1080/13632469.2011.614678.
_____________
The new Sarah Mildred Long Bridge, of Cianbro, see the Spring 2017 issue Others have approached the construction
which spans the Piscataqua River from of ASPIRE ®). FIGG Bridge Engineers of these types of foundations using the
Portsmouth, N.H., to Kittery, Me., opened designed the approach spans, and following methods:
on March 30, 2018. The structure has Hardesty & Hanover designed the lift • Casting a complete tub and setting it
two-level precast concrete segmental box- span and towers as a joint venture. on drilled shafts using a large capacity
girder approach spans with a 300-ft-long crane
lift span. Additionally, the 200-ft-tall towers Tower Foundation Design • Casting and launching a complete tub,
of the lift span are vertically post-tensioned Challenges floating it over the drilled shafts, and
segmental towers, a first in the United The Piscataqua River is a deep and fast- then submerging it into place
States. The foundations for the lift span flowing tidal river, one of the fastest • Suspending a precas t concrete
towers are 125 ft long, 65 ft wide, and in the United States. This factor and segmental soffit above high water,
15 ft thick. The design of the foundation others presented many challenges to the building a traditional cofferdam on the
includes a precast concrete tub used as a construction of the tower foundations. soffit, and using synchronous jacks to
cofferdam and form. An allowance of 18 The following were among the primary lower the system into place
in. for the tub-wall thickness and 3 ft for considerations that influenced the
the bottom thickness was included in the u l t im a t e m e t h o d o f fo u n d a t io n Cianbro analyzed these options and
design. Eight 10-ft-diameter drilled shafts construction: ruled them out because it did not have
socketed 35 ft into competent rock support • The tidal current could exceed 4 knots. sufficient crane capacity to lift 1100 tons,
each foundation. The top of the foundation • The maximum crane capacity at and a dry dock or launching system was
is at elevation 8 ft, about 2 ft above the working radius using a Manitowoc not available to fabricate and launch
highest astronomical tide expected during MLC300 Lattice Boom Crawler, which such a large floating tub. Additionally,
construction. Each of the structural was the largest crane the contractor the Piscataqua River’s extreme current
footings contains 3200 yd3 of cast-in-place had in its fleet, on a 72 ft by 200 ft and a slack tide of only 30 minutes made
concrete and 500,000 lb of reinforcement deck barge was 180 tons. the prospect of floating and accurately
along with 14 post-tensioning ducts for the • The foundation had to be submerged positioning a large tub over the drilled
segmental towers. 13 ft at the highest astronomical tide. shafts too risky. Similarly, slowly jacking
• The water was 65 ft deep, with little a tub down into the current was not ideal.
The project was jointly sponsored by the overburden on the river bottom.
Maine and New Hampshire departments • There were significant construction Cianbro Solution
of transportation. The project delivery and environmental loads, such as A precast, sand-lightweight concrete,
method was the construction manager/ water pressure due to the tidal current segmental post-tensioned tub addressed
general contractor method, and the alternating in direction. the design challenges. The MLC300
Cianbro Corporation of Pittsfield, Me., • Worker and diver safety had to be crane could quickly erect the tub. The
was the general contractor (for a profile ensured. combination of strength and density of
the sand-lightweight concrete was critical
Sarah Mildred Long Bridge approaches, lift span, towers, to the success of the design because loads
and tower footings. Photo: Cianbro/Richard Hopley. were close to crane capacity. Additionally,
each piece could be set quickly to the
design elevation and secured during slack
tide. The tubs were free draining, which
gave workers two hours to work inside the
tubs at low water. Workers grouted and
bolted the tubs from the top. There was
no need for divers to go beneath the tubs,
thereby improving safety.
units were placed between the drilled- piece) to be transferred to the drilled-shaft
shaft units and were supported by an unit through shear friction. An extensive
integral ledge cast into the drilled-shaft finite element model was developed of the
units. The drilled-shaft segments could tub using RISA-3D software to determine
be precisely located in elevation and the structural behavior of the tub.
plan by using threaded hangers and
horizontal alignment fixtures cast into the The success of the system depended on
concrete around the penetrations for the the connection of the tub to the drilled
drilled shafts. The horizontal alignment shafts. The connection was required
fixtures also stabilized the segments from to transfer large uplift forces from
the pressure of the water current. A ¾ the dewatered tub as well as the loads
in. space between segments provided imposed from concrete placement. The
The dewatered tub with the drilled shafts visible.
erection tolerance and space to grout and design shear load transferred to each
The work platform has been attached to the top
seal between segments. Grade 75, 1-in.- drilled shaft was 850 kip. A grouted shear
of the tub. Photo: Cianbro.
diameter sleeved all-thread bolts were key design, typically used in the offshore
spaced at 18 in. along the entire length oil industry, provided the necessary before a segment was set allowed the
of the joint between segments. Each all- capacity. The connection was designed divers to grout the connection from the
thread bolt was post-tensioned to 30 kip using grouted pile-to-structure connection top. High-strength (8 ksi), structural
after the joints were grouted, allowing the criteria from the American Petroleum underwater concrete, with washout
entire load of the fill unit (weight of first Ins titu te's Recommended Prac tice additives, provided the required strength
lift of concrete plus dead load of the fill 2A-WSD.1 Installing forms for grouting in a timely manner in the cold river water.
Conclusion
The precast concrete, post-tensioned
segmental tub provided a cofferdam/
form system that was constructed using
readily available erection equipment.
Tub erection, grouting, and dewatering
took only 30 days, which helped meet
an aggressive project schedule. Exposure
to the harsh environmental conditions
was minimized, thereby reducing risk. The
use of sand-lightweight concrete was also
critical to the success of the design.
Reference
1. American Petroleum Institute (API).
The precast concrete segmental tub. The use of sand-lightweight concrete for the segments allowed the 2014. API Recommended Practice
tub to be installed using readily available equipment. Figure: Cianbro. 2A-WSD: Planning, Designing,
and Constructing Fixed Offshore
DRILLED SHAFT DRILLED SHAFT UNIT
Platforms—Working Stress Design.
22nd ed. Washington, DC: API.
3" 14'–10 1 3"
4 2" 4 _____________
EL -4.50
Joseph Orlando is senior structural engineer
with Cianbro Corporation in Portland, Me.
4'
EDITOR’S NOTE
FILL UNIT
Implementation of an Electrically
Isolated Tendon Post-Tensioning
System in the United States
by Dr. Clay Naito, Lehigh University, and Dr. Christina Cercone, Manhattan College
Post-tensioned concrete bridges represent The tendon system uses a plastic duct, resistance (LCR) meters to measure
an important component of the current with plastic duct couplers and plastic the AC resistance, capacitance, and loss
U.S. bridge inventory. These systems, half shells to protect the integrity of the factor between the isolated PT strands
whether cast-in-place or precast concrete corrosion protection system along the and the reinforcing steel located in the
construction, can be used to create long- length of the tendon. The plastic half surrounding bridge structure. These
span continuous bridge superstructures shells are used between the plastic duct readings can be compared to limiting
with long service lives. However, ensuring and the transverse reinforcement to acceptance criteria values 1 to provide
the quality of the post-tensioning duct provide additional protection to the duct owners with an assessment of the quality
system and grout material used to during member fabrication and tensioning. of the encapsulation and any unexpected
encapsulate the strands has been a corrosion initiation. These measurements
concern. The post-tensioning ducts are Several companies commercially produce are often taken at key s tages of
conventionally located within the web of the required components of the EIT construction, such as during tensioning or
the concrete girders, and critical sections— system for the European market, making tendon installation, before and after grout
such as splices and anchorages—are this an off-the-shelf technology. For the installation, during deck placement, and
heavily reinforced to provide adequate past 20 years, EIT systems have been during service. The EIT system has the
transfer of forces into the members. These used in various post-tensioned concrete potential to provide long-term condition
practical requirements of post-tensioning bridges in Europe, including the Piacenza assessment of the tendon system over the
(PT) make visual and nondestructive Viaduct and Marchiazza Viaduct in life of the bridge.
inspection techniques difficult to implement Italy and the P.S. du Milieu and the
during construction and throughout the Wiesebrücke Basel in Switzerland. First U.S. Demonstration
life of the bridge. Quality control methods Project
are well established for PT installation With the EIT system, the encapsulation The many benefits of the EIT system
and grouting, but traditional inspection sys tem is ass ess ed from time of and its successful use in Europe have
methods are not easy to implement during construction through the service life prompted research and development
regular service-life inspections of internal of the bridge by using commercially efforts geared toward implementation in
tendons. a va il a bl e in d u c t a n c e / c a p a ci t a n c e / the United States, including a series of
System Components
The EIT system is composed of an
enhanced tendon and anchorage system.
The anchorage includes an isolation
The main unit of the Coplay-Northampton Bridge consists of a 540-ft-long, three-span section over
plate, a plastic trumpet, and proper
the Lehigh River. The superstructure consists of five prestressed concrete PA bulb tees, which were
encapsulation of the anchorage head.
spliced and post-tensioned. All Photos: Dr. Clay Naito.
demonstration bridge projects sponsored each beam. Electrical continuity along a viable approach for providing additional
by the Federal Highway Administration the entire span is important because the quality assurance of the PT system.
(FHWA). The firs t demons tration measurements are taken at one end of
project integrates the EIT system into the bridge. Failure to maintain electrical References
the Lehigh County–owned Coplay- continuity of some spans would limit 1. Angst, U., and M. Büchler. 2015.
Northampton Bridge between Coplay and the effectiveness of the EIT system. Monitorable Post-Tensioning Systems
Northampton boroughs in Pennsylvania. The continuity strands were tied to the Sub Task 2: State of the Art Report.
This construction project is currently uncoated steel shear reinforcement within Zurich, Switzerland: Swiss Society for
underway. Deck placement is expected in each beam during precasting and were Corrosion Protection.
spring 2019, and the bridge is scheduled tied together at each splice after erection. 2. Post-Tensioning Institute (PTI) and
to open in fall 2019. The two electrical continuity strands were American Segmental Bridge Institute
located at the bottom of the beams. (ASBI). 2012. PTI/ASBI M50.3-
The primary portion of the Coplay- 12: Guide Specification for Grouted
Northampton Bridge consists of a three- The EIT system was monitored during Post-Tensioning. Farmington Hills, MI:
span, 540-ft-long unit over the Lehigh selected stages of the construction PTI.
River. The superstructure consists of project (following tensioning of the _____________
prestressed concrete PA bulb tees, tendons, prior to and following grouting,
Dr. Clay Naito is a professor in the
which were spliced and post-tensioned and 28 days after grou ting), and
Department of Civil and Environmental
in the field. The beams were precast at monitoring will continue to evaluate the
Engin eering at Lehigh University in
Nor theast Prestressed Products in long-term performance of the PT system.
Bethlehem, Pa., and Dr. Christina Cercone
Cressona, Pa. The bridge was designed Measurements are taken by connecting
is a faculty member in the Civil and
by AECOM and constructed by Trumbull the LCR meter to one of the exposed
Environmental Engineering Department at
Corporation, with project management continuity strands located at the bottom
Manhattan College in Riverdale, N.Y.
provided by Pennoni. Each beam has of the flange and to the PT strands of
four PT ducts. As a demonstration, the EIT system, using an exposed wire
only the top PT duct in each beam line connection. These measurements are
has the EIT system, which was provided compared to the threshold performance
by DYWIDAG-Systems International limits and indicate the level of electrical
(see the Focus article in this issue of isolation of the tendons.
ASPIRE® on page 6).
Initial measurements indicate that the
As mentioned previously, the EIT system EIT system meets the current isolation
requires the use of a plastic duct with requirements needed to achieve the highest
plastic duct couplers and plastic half level of corrosion protection, PL3, as
shells. In the demonstration project, defined in PTI/ASBI M50.3-12: Guide
the addition of the required isolation Specification for Grouted Post-Tensioning 2
plate and plastic trumpet in the EIT and additional recommendations developed
anchorage was not a significant change by Angst and Büchler for FHWA.1
to a traditional PT system. All the PT
ducts, including the single EIT duct, were According to discussions with the
spliced in the field using plastic couplers precast concrete producer, project Measurement of the electrically isolated tendon
combined with heat-shrink tubing. To manager, contractor, and Pennsylvania (EIT) system after grouting. The inductance/
ensure electrical continuity of the beam Department of Transportation, the use of capacitance/resistance meter is connected to the
reinforcement located outside of the PT the EIT system required minimal added exposed steel located at the bottom flange and
ducts, two uncoated pretensioning strands construction effort, has had nominal to the post-tensioning strands using the wire
were left protruding from each end of impact on project costs, and appears to be connection to the top EIT anchorage.
Sweep is defined in the Manual for Quality and owners may be understandably would be preferable). The measurement(s)
Control for Plants and Production of concerned about how sweep could occur should be recorded even if zero.
Structural Precast Concrete Products in production, and what corrective actions
(PCI MNL-116) 1 as “a variation in can, or should be taken. Regardless the Alternatively, it may be easier to measure
horizontal alignment from a straight amount of sweep, the truth is this: most the sweep at approximately 20 ft
line parallel to centerline of member prestressed concrete bridge girders, once increments. In this case, measurements
(horizontal bowing).” A generalized they are in place with composite concrete should be made accurate to ±1⁄16 in. A
representation for sweep is shown in Fig. 1. decks cast upon them, will function sweep measurement made at the center of
effectively for the design life of the bridge a 20.0-ft length, or the average of several
Decades of industry experience inform us without concern for limits on strength, such measurements, can be converted to
that very few girders are produced with durability, or serviceability. an overall sweep by the following:
noticeable or out-of-tolerance sweep.
2
However, when sweep is large enough to Prestressed concrete bridge girders that ⎛ L ⎞
be noticed—or when the amount of sweep are built in accordance with our design f = f20 ⎜ ⎟
⎝ 20.0 ft ⎠
exceeds tolerance—producers, contractors, standards, and are made from conforming
materials (concrete and steel) within a where
geometry described by the contract f = sweep projected over the
documents, will support the intended entire girder length L
design loads for millions of cycles, in all f20 = sweep measured over a
kinds of climates, for the design service 20.0 ft length
life of the structure. This article focuses
on the sweep of bridge girders that may Tolerances for precast, prestressed concrete
occur during initial fabrication, lifting, or members have been established to allow
storage in the yard. One probable cause for production and erection variances, as
is explored with a hypothetical example well as the interface of the member with
and corrective actions that can be taken the overall construction of the structure.
L Sweep
while the girder is still in the precast Tolerances are to be used for guidelines
producer’s yard. Subsequent articles and not as reasons for rejection. If the
will cover transportation, erection, and girder can be brought within tolerance in
construction issues and discuss whether an acceptable manner, or if exceeding the
permanent sweep in girders should cause tolerance does not affect the integrity or
concern for long-term stresses, strength, performance of the girder, the girder should
or performance. be accepted. Later articles will show that
girders with sweep in excess of tolerances
Measurements and Tolerances can function without compromising the
The initial measurement of sweep is completed bridge system.
made after the side forms are removed
and prestressing force is transferred, or The tolerance for sweep for bridge girders
after the girder is removed from the forms given in MNL 116-991 is 1⁄8 in. per 10
and is placed on dunnage in the precast ft. For example, a bridge girder with a
producer’s yard. When measuring sweep, it length of 130.5 ft would have a sweep
is important that the girder is level, the sun tolerance of 1.63 in. The calculation for
is not shining on one side, and the actual sweep tolerance follows:
flange widths have been verified at the ends ⎛1 ⎞
and middle. Commonly, sweep is measured ⎜ in. ⎟
CL Sweep Tolerance = 130.5 ft ⎜ 8 ⎟
at the midspan of the girder. Admittedly,
⎜⎜ 10 ft ⎟⎟
accurate measurement may be difficult for ⎝ ⎠
Figure 1. A generalized representation for sweep
long girders. However, a measurement to
in a girder. Figure: Dr. Bruce Russell.
¼ in. precision should be sufficient (1⁄8 in. = 1.63 in.
of sweep is normal for a particular girder stored out of plumb can develop sweep. = 2.088 ×10−6 rad/in.
type. When the initial measured sweep • Exposure to sun—thermal differences
is larger than this “experience” value, between the sides of the girder in
φ y L2
f=
or if measured sweep exceeds tolerance storage can cause sweep. 8
or is projected to exceed tolerance, then • Curing temperatures—if heat is 2⎛ in.2 ⎞
an investigation should be undertaken applied, ensure uniform application of (2.088 ×10 −6
)
rad/in. (130.5 ft ) ⎜144 2 ⎟
⎝ ft ⎠
immediately by the precaster and sweep elevated temperatures. =
8
should be monitored on a regular basis • Quality control records—search for
while the girder is stored. The investigation differences in concrete batches. = 0.640 in.
might uncover a problem that can be • The design—strand pattern and From these calculations, one can see that a
corrected before subsequent girders are items such as blockouts in a flange or strand pattern that is placed eccentrically
produced or, if mitigating or corrective localized changes in the web. by ¼ in. can produce an estimated sweep
action on the existing girder is required, of 0.64 in. immediately after transfer. This
lead to a preferred course of action. As In many cases, the cause of sweep is sweep is less than the sweep tolerance of
time goes by, measured sweep may worsen not easily identified. It could involve a 1.63 in. for a 130.5 ft girder, which was
because of creep and concrete maturity, combination of two or more of the listed calculated earlier in this article.
with fewer opportunities for corrective items.
The sweep created by the eccentric
Table 1. Girder Design Details for Example Calculating Sweep for prestressing force creates a theoretically
Bridge: SH 99 over Deep Fork River, Eccentrically Located Strands uniform minor-axis curvature φ y over
Lincoln Co., Okla. For the purposes of this discussion, one the length of the bridge girder. As can
Design Engineer: Bruce W. Russell possible cause of sweep is explored. The be seen in the calculations, sweep is
example is based on a PCI-AASHTO proportional to the square of the girder
Span: 130.5 ft
bulb-tee BT-72 girder2 designed for State length. Therefore, in the author’s opinion,
Type of Girder: PCI-AASHTO BT-72 Highway 99 (SH 99) over the Deep for longer girders, it may be more
Spacing, s = 7.17 ft Fork River in Lincoln County, Okla. The appropriate to set a larger tolerance for
original designs were performed by the sweep than the 1⁄8 in. in 10 ft provided
A= 767 in.2
author. Spans for this bridge were 130 in MNL 116-99. For example, the
h= 72.0 in. ft 6 in., measured from center-to-center same strand eccentricity that creates a
cb = 36.60 in. of bearings. Girders were spaced at 7 ft ¾ in. sweep for a 100 ft girder (which
Ixx = 545,113 in.4 2 in. Each BT-72 girder was made with exceeds the tolerance of 1.25 in.) also
thirty-eight 0.6-in.-diameter Grade 270 produces a 3.0 in. sweep for a 200 ft
Iyy = 37,543 in.4
prestressing strands conforming to ASTM girder, which exceeds the tolerance of
wb = 0.799 kip/ft A416. Design details are listed in Table 2.50 in. The point is that longer girders
f’c = 10.0 ksi 1. Please note that the example used for are more susceptible to noticeable or
f’ci = 7.0 ksi this article is hypothetical and created out-of-tolerance sweep simply because
only for purposes of illustration. During they are longer, and the effect that may
Eci = 4821 ksi
fabrication of the actual girders for the have caused sweep in the first place is
Width of SH 99 Bridge, there were no reports of squared in proportion to length.
26 in.
bottom flange sweep in the bridge girders.
Width of
42 in.
Stresses Caused by Sweep
top flange For purposes of illustration, let us Generally, if sweep exists, it is most often
Strand type: 0.6-in.-diameter Gr. 270 compute the sweep as if all strands in small, and its effects on stresses can
ASTM A416, low relaxation the girder were located ¼ in. off center, be ignored. Also when considering the
N= 38 strands or with a lateral eccentricity ex of ¼ magnitude of the stresses, readers should
in., which is the tolerance in PCI MNL- be aware that the stresses computed in
e= 29.02 in.
116 for strand placement. The following this manner are temporary stresses and,
www.WireReinforcementInstitute.org
Photograph of map cracking on concrete Ultraviolet light photograph of polished slab from a concrete core affected by alkali-silica reaction.
pavement affected by alkali-silica reaction. All The core was impregnated with a fluorescent epoxy. The yellow-green areas are filled with the epoxy.
Photos and Figures: Dr. David Rothstein. The white arrows indicate examples of cracks.
under controlled conditions.4 Measuring of lithium-based compounds have been Application and Demonstration
the water-soluble alkali content of the used with mixed results to arrest the Projects Volume I: Summary of
concrete can show whether alkali in progression of ASR. A major concern Findings and Recommendations.
the system is sufficient to sustain ASR. with such materials is the depth of Federal Highway Administration
Remember that in cases where concrete penetration, which may be negligible in HIF-14-0002. https://www.fhwa.
is exposed to deicing salts, the alkali some cases. dot.gov/pavement/pub_details.
content of the concrete can increase over cfm?id=925.
time because of the ingress of the salts.5 Other measures to prolong the 2. Sanchez, L.F.M., B. Fournier, M.
serviceability of structures affected by Jolin, M.A.B. Bedoya, J. Bastien,
Managing the Structure ASR may include structural repairs and J. Duchesne. 2016. “Use of
Once ASR is identified as a concern, such as external post-tensioning, use of Damage Rating Index to Quantify
the appropriate approach to manage carbon- or glass-fiber wraps, or other Alkali-Silica Reaction Damage
it depends on the severity of the ASR methods to provide physical restraint. in Concrete: Fine Versus Coarse
and the potential for future expansion. In cases where there is significant Aggregate.” ACI Materials Journal
The first option is to simply monitor damage, cutting expansion joints or 113: 395–407.
the structure by conducting field removing areas around damaged joints 3. Katayama, T. 1998. “Petrographic
inspections at regular intervals. Crack may reduce stress. However, such Diagnosis of Alkali-Aggregate
index maps and strain gauges can be measures are only temporary, and they Reaction in Concrete Based on
used to determine if cracks are growing. do not mitigate future expansion. Quantitative EPMA Analysis.”
Also, additional cores can be extracted Proceedings of the 4th International
to be examined petrographically (DRI Conclusion Conference on Recent Advances in
works well for this) and compared to The diagnosis of ASR or DEF in a Concrete Technology, Tokushima,
cores evaluated previously. structure does not necessarily mean that Japan.
immediate removal, replacement, or 4. Merz, C., and A. Leeman. 2013.
If remediation is needed, several even repair is required. It is essential to “Assessment of the Residual
approaches are available. The most conduct careful field and petrographic Expansion Potential of Concrete
viable strategy for slowing or stopping investigations of the structure to obtain from Structures Damaged by
the progression of ASR is to cut off the an understanding of the severity of the AAR.” Cement and Concrete
water that feeds it. Studies have shown problem. In most cases, it is prudent Research 52: 182–189.
that an internal relative humidity (RH) to implement field-based programs 5. Katayama, T. 2004. “Alkali-
of 80% to 85% is essential to sustain to monitor and evaluate the behavior Aggregate Reaction Under the
ASR in concrete.6 Often, the first step of the structure over time. Preventing Influence of Deicing Salts in the
in keeping concrete elements below the ingress of water remains the most Hokuriku District, Japan.” Materials
this RH threshold involves repairing or effective method to mitigate ASR in Characterization 53: 105–122.
modifying drainage systems to redirect structures. In cases where damage is 6. Farny, J.A., and Kerkhoff, B.
water flows away from and out of significant, structural repairs may be 2007. Diagnosis and Control
structures. Waterproofing membranes, necessary. In all cases, experienced of Alkali-Aggregate Reactions in
filling cracks and construction joints engineers, petrographers, and Concrete. PCA R&D Serial No.
with appropriate materials, and contractors should be engaged to ensure 2071b. https://www.cement.org/
applying sealers or other surface that the proper strategies and methods docs/default-source/fc_concrete_
treatments may be adequate. Coatings for this work are deployed. technology/is413-diagnosis-
that permit water vapor to escape are and-control-of-alkali-aggregate-
preferred because they will facilitate the References reactions-in-concrete.pdf.
drying of the structure. In some cases, 1. Thomas, M.D.A., K.J. Folliard, _____________
sealers that do not allow the structure B. Fournier, P. Rivard, and T.
to breathe can make ASR worse because Drimalis. 2013. Methods for Dr. David Rothstein is the president and
they trap moisture entering from Evaluating and Treating ASR- principal petrographer of DRP, a Twining
untreated surfaces. Topical applications Affected Structures: Results of Field Company, in Boulder, Colo.
COST SAVINGS
The TwinTier’s Wire Pull-Back Mechanism dispenses the precise
amount of wire needed to form a tie, reducing wire usage.
WWW.MAXUSACORP.COM
CALL TO SCHEDULE A JOBSITE DEMO
800.223.4293
Reinforcing Steel
COST-EFFECTIVE
CORROSION
PROTECTION
Follow us on
Ultra-high-performance concrete (UHPC) States, nearly 200 bridges in 27 states and the repaired or rehabilitated using UHPC-class
is an advanced, fiber-reinforced, cementitious District of Columbia have been constructed us- materials, and, for the most part, each appli-
composite material that has gained significant ing UHPC materials, and 93% of these projects cation has had unique aspects. (Refer to the
attention from bridge owners and designers used UHPC for PBE connections. FHWA Interactive UHPC Bridge Map for ad-
because of its excellent mechanical and dura- ditional details.2)
bility properties. The rapid growth in UHPC’s Moving Beyond Four of these projects (in Colorado, Califor-
popularity in the U.S. bridge market has been PBE Connections nia, Florida, and Rhode Island) marked the first
spurred in part by its ability to provide a much- As UHPC-class materials become more prev- use of UHPC on state-owned highway bridges.
needed, robust solution for closure pours in alent, new and innovative applications for these Each of these projects used relatively small vol-
prefabricated bridge element (PBE) connec- materials in bridge design and construction will umes of UHPC material and were viewed as
tions.1 This application has also been a com- continue to emerge. One emerging application relatively low risk by the bridge owners. As such,
mon entry point for owners interested in the for UHPC in the U.S. highway bridge sector repair applications are becoming an alternative
opportunities UHPC provides for bridge de- is for bridge repair, retrofit, and rehabilitation. entry point for bridge owners looking to gener-
sign and construction. To date, in the United Since 2016, at least 10 U.S. bridges have been ate institutional knowledge and familiarize local
A simple log-in
to the PCI website
is all that is needed
to
download these fre
e
resources.
Re p or t
Prep a re d by t h e
P C I Co m m it tee o n B r i d ges
and the PCI Bridge Producers
Com m it tee
The PCI State-of-the-Art Report on Full-Depth Precast Concrete Bridge Deck Panels (SOA-
U n d er t h e d irec t io n o f t h e
Alabama
by William (Tim) Colquett, Alabama Department of Transportation
Construction of one of the new twin bridges on the Ross Clark Circle (U.S. Route 231) over Beaver Creek culvert in Dothan, Ala. The rollers and steel tracks shown in the
photo on the right were used with hydraulic jacks to slide the new bridge into place. Photos: ALDOT.
short-span precast concrete bridges and quickly as possible to minimize traffic These designs usually provide the best
substructures have been a common feature disruptions in an area with high ADT. economy, aesthetics, durability, and speed of
of Alabama’s off-system roadways for years. In lieu of constructing a new culvert, construction for the state.
ALDOT’s solution was to retain the existing
In some ways, the culvert, partially remove the fill from the Emerging Delivery and
culvert’s top, and span over it with parallel Design Methods
state was advancing 120-ft-long bulb-tee girder spans, 54 ft and Design options for bridges may expand as
63 ft wide, each supported by steel piles and ALDOT ventures into new delivery methods.
ABC methods before cast-in-place concrete abutments. For example, for the Interstate 10 (I-10)
The contractor constr ucted the Mobile River Bridge, a planned six-lane
ABC became an industry abutments beneath live traffic by using structure that will be the state’s second
steel trench boxes with removable lids that cable-stayed bridge, three prequalified
buzzword. accommodated traffic during peak hours teams now are putting together design,
and then could be removed in off-peak cost, and schedule proposals for the project,
Perhaps the most prominent use times to allow piles to be driven. Once the which is being financed through a public-
of ABC on state highways came in 2002 piles were driven, the lids were put back private partnership. This approach offers
and 2004, when two different structures in place while workers beneath completed the only way that the state can afford the
in the Interstate 59/20 interchange were construction of the abutment caps. project, which will cost between $800
damaged beyond repair after tractor The superstructure was constructed on million and $1 billion.
trailers wrecked under the bridges and roller bearings, so it could be rolled into
their fuel loads were ignited. These bridges,
located in what is sometimes called the place during specific windows of closure Design options
times. When the slide was ready, traffic was
“Malfunction Junction” due to the heavy
traffic and diverging-diamond geometry, shut down, the trench boxes were removed, for bridges may expand
and the spans were rolled into place.
had to be replaced as rapidly as possible to
minimize travel disruptions on an already The first bridge was rolled into place and as ALDOT ventures into
completed in three days, while the second
difficult route. Steel spans were replaced
with prestressed concrete bulb-tee girders was completed in two. new delivery methods.
Successfully completing this project
on an accelerated schedule. One span was required ALDOT to take a proactive The I-10 Mobile River Bridge will also be
replaced in 36 days, and the other was back approach with the contractor. This close the state’s first design-build project, which
in service in 38 days. Prefabrication of span relationship allowed dialogue and became possible when legislation was passed
components while the site was prepared was suggestions to flow easily, facilitating the to allow the use of that delivery method on
a key to that speed. ALDOT has incorporated quick processing of issues and creating a projects costing more than $100 million.
similar techniques into other projects to pattern that can be used on future projects Clearly, many new concepts will emerge
help reduce user costs and keep traffic where such ABC techniques may be from this process, and ALDOT is watching
moving smoothly. appropriate. closely to determine what benefits these
Recently, another ABC technique was Although these projects demonstrate approaches can provide for future projects.
successfully deployed for the bridge slide ALDOT’s willingness to use new techniques
in the $2.43 million culvert replacement
on Ross Clark Circle (U.S. Route 231) in when needed, Alabama’s bridge projects Bridge Aesthetics
typically use conventional construction New design ideas will also aid in creating
Dothan, Ala. (see the article on this project methods. Most bridges are built with more aesthetically pleasing bridges, which
in the Fall 2016 issue of ASPIRE®). The traditional concrete designs, typically has become a higher priority. The range of
objective was to widen the structure from using AASHTO-type and bulb-tee girders. aesthetic options available with concrete has
two to three lanes in each direction as
Williams System
williamsform.com
52 | ASPIRE Spring 2019
Chris Ritter,
Superintendent
Granite Construction Company:
“It was a pleasure to use the
PERI RCS system. We easily
trained the crews on how to
use it. Assembly and
disassembly was a breeze.
Can’t wait to use it again.”