Professional Documents
Culture Documents
CONVENTION
CENTER &
TOWER
PROJECT
Method Statement
For
Installation of HVAC Ducts and
Accessories
Table of Contents
SN. DESCRIPTION PAGE
1 Front Page 1
2 Table of Contents 2
3 Purpose 3
4 Scope 3
5 Definition 3
6 Reference Documents 4
7 Tools & Equipments 4
8 Manpower 5
9 Responsibilities 5
10 Material Inspection / Storage 6
11 Construction Sequence and Methodology 6
12 Inspection / Testing 8
13 Insulation 9
14 Health, Safety and Environment 11
15 QC Approval Report Requirements 12
16 Attachments
16.1 Risk Assessment for Installation of HVAC Ducts
16.2 Inspection and Test Plan of HVAC Ducts
16.3 Inspection Check List of HVAC Ducts
The purpose of this Method Statement is to describe the details used and controls to
be carried out for the installation of Ducts, fittings, insulation and accessories for
HVAC System to ensure that it complies with Project requirements, Project
Specifications (Section 23-3100 ) and standards.
4.0 Scope
This Method Statement is applicable to all Ducts, fittings, insulation and accessories
for HVAC System at Doha Convention Center & Tower Project.
Manpower and Equipments shall be organized to meet the schedule as per approved
Construction program.
5.0 Definition
5.1 “Abbreviation “
5.5 “Materials”
Materials means all items covering the materials or equipments delivered to site
that must be incorporated in the project.
8.0 Manpower
8.1 Staff :
Construction Manager
Site Engineers
Supervisors
QAQC Engineer / Inspector
Quantity Surveyor
Safety Officer
8.2 Labour :
Foreman
Trade workers
Helpers / Labours
Drivers
9.0 Responsibilities
9.1 The Project Manager shall be responsible for the overall construction,
coordination site activities and implementation this method statement.
9.3The Store Manager & Supervisor shall be responsible for receiving all materials
delivery from Manufacture / Supplier on site warehouse.
9.4 Site Engineer / Supervisor shall check all the materials as per approved material
submittal & manufacturer’s recommendation prior to installation and shall be
responsible for the execution as per approved shop drawings.
9.5 Safety Officer shall ensure that appropriate / necessary measures are in place at
work location to avoid any unexpected accidents / events.
Method Statement – Installation of HVAC Ducts and Accessories
DOCUMENT NUMBER: ED-M-M-M-A-GN-0001
Page 5
DOHA
CONVENTION
CENTER &
TOWER
PROJECT
9.6 QAQC Engineer / Inspector shall be responsible for carrying out inspections for
the materials delivered on site. He shall document such inspections.
9.7 QAQC Engineer / Inspector shall monitor the installation activities progressively
and shall record all deviation from specification in a form of snags list or non-
conformance notification.
10.1 All HVAC Ducts materials received or purchased shall be inspected and
approved by Supervision Consultant before using on site. Materials shall be
stored in a safe, secured and tidy manner in appropriate condition to prevent
deterioration or damage. All HVAC Ducts materials shall be appropriately
covered and protected from weathering ill effects, open sunshine, sand
storm, and other such vagaries peculiar to the region. Items shall be stored
for ease of access / handling / stock verification/ inspection/ checking by the
main contractor / supervision consultant representative if and when
required.
Note: Insulation adhesive, sealant and other chemicals shall be stored in Air
Conditioned (ACU) area as per manufacturer’s recommendation.
11.2.16 Prior to False ceiling closure, all insulated and exposed ductworks
shall be identified as per approved by the consultant.
12.1 After completion of the work, The Site Engineer & Supervisor who perform an
activity are required to raise an RFIA with complete attachment &
information regarding the scope of inspection, including necessary drawings
highlighted to show the scope of inspection. He shall systematically check
and inspect their work. The inspection shall be performed according to
typical checklist and approved Inspection and Test Plans (ITP) which shall also
be attached to the RFIA.
12.2 After Site Engineer & Supervisor completed their inspection and testing , RFIA
shall be submitted to QAQC Department who shall check and process the
documents to have completed work inspected by Supervision Consultant for
their approval.
12.3 Cleaning of installed ducts system use with Handy Air Blower high velocity
pressure to force out / remove accumulated dust and debris inside ducts.
12. 4 Specifying Air Leakage Testing for the HVAC Ducts. The installed Ducts having
Low Pressure and Medium Pressure Static differential ratings Class A & B, is
not mandatory ,shall be Untested, No Need to perform and verify leakage
control by field testing when adequate methods of assembly and sealing are
used. It is Not recommended that the HVAC ducts system constructed to 3”
(750 Pa) Wg class or lower to be tested because this is generally not cost
effective. ( Refer to the attached SMACNA Second Edition Leakage Test
Clause 1.7.1 page 1.10 and Table 1 & Table 17 Duct Classification Air Leakage
Limits and Rates )
Method Statement – Installation of HVAC Ducts and Accessories
DOCUMENT NUMBER: ED-M-M-M-A-GN-0001
Page 8
DOHA
CONVENTION
CENTER &
TOWER
PROJECT
Note: RFIA must be processed and submitted to Supervision Consultant 24 hours
before the actual inspection and/or witnessing.
13.4 Start from edge of board and measure first outside duct dimension plus
add on allowance:
13.5 From there, measure second outside duct dimension plus add on
allowance as per above. Draw second corner centreline.
13.6 From there, measure same as first outside dimension plus add on
allowance as per table above. Draw third corner centreline.
13.7 From there, measure same as second outside dimension plus add on
allowance as per table below.
13.23 After completion of insulation work, RFIA must be raised and submitted to
Supervision Consultant 24 hours before the actual inspection and final
approval.
Safety of all personnel and equipment is the highest priority of ETA-Debbas JV during
the execution of the Works.
14.2.1 Safety Tool Box Talk shall be given by the Site supervisor / Safety
officer every week and/or as deemed necessary.
14.2.2 Safety tool Box Talk shall brief the task / subject and shall be given in
languages understandable by multinational workforce.
14.2.3 Safety Tool Box Talk attendance shall be recorded on a sheet and
signed by attendees.
12.3.1 All materials shall be identified and all MSDS should be read and
understood before use.
14.5 Signage
12.5.1 All necessary safety warning and caution signs shall be displayed at
work locations.
14.6 Environment
14.6.1 MSDS for COSHH materials shall be kept by the storekeeper and a
copy given to HSE Dept. The MSDS shall be followed as per Qatar
labour law. Waste Disposal shall be segregated and disposed by a
Certified Subcontractor and send it to the municipality stockyard for
COSH material as per Qatar labour law.