Professional Documents
Culture Documents
CONVENTION
CENTER &
TOWER
PROJECT
Method Statement
For Installation of
Fan Coil Unit (FCU)
Table of Contents
SN DESCRIPTION PAGE
1 Front Page 1
2 Table of Contents 2
3 Purpose 3
4 Scope 3
5 Definition 3
6 Reference Documents 4
7 Tools & Equipments 4
8 Manpower 5
9 Responsibilities 5
10 Material Inspection / Storage 6
11 Construction Sequence and Methodology 6
12 Inspection / Testing (For Equipment Installation) 7
13 Health, Safety and Environment 8
14 QC Approval Report Requirements 9
15 Attachments
15.1 Risk Assessment
15.2 Inspection and Test Plan
15.3 Inspection Check List
The purpose of this Method Statement is to describe the details used and controls to
be carried out for the installation of Fan Coil Unit (FCU) Ceiling mounted and
accessories to ensure that it complies with Project requirements,Project
Specifications (Section 23-8101 ) and standards.
4.0 Scope :
This Method Statement is applicable to all Fan Coil Unit (FCU) Ceiling mounted and
accessories for at Doha Convention Center & Tower Project.
Manpower and Equipments shall be organized to meet the schedule as per approved
Construction program.
5.0 Definition :
5.1 “Abbreviation “
8.1 Staff :
8.2 Labour :
8.2.1 Foreman
8.2.2 Trade workers
8.2.3 Helpers / Labours
8.2.4 Drivers
9.0 Responsibilities :
9.1 The Project Manager shall be responsible for the overall construction,
site coordination, site activities and implementation this method statement.
9.2 The Construction Manager, Site Engineers, Supervisors and Foremen
shall implement and execute this Method Statement.
9.3 The Material Controller shall be responsible for receiving all materials on
site warehouse.
9.4 Site Engineer / Supervisor shall check all the materials as per approved
material submittal & manufacturer’s recommendation prior to installation
and shall be responsible for the execution as per approved shop drawings.
9.5 Safety Officer shall ensure that appropriate / necessary measures are in
Place at work location to avoid any unexpected accidents / events.
9.6 QAQC Engineer / Inspector shall be responsible for carrying out
inspections for the materials delivered on site. He shall document such
inspections.
11.1.1 Ensure that all Drawings for Installation are latest approved and
properly coordinated with other services
11.1.2 Check if work location / area are ready for the installation of Fan Coil
Unit Ceiling mounted and accessories.
11.1.3 Before starting the work, check that all Safety precautions are in place.
11.1.4 Ensure that all the provisions, openings, height levels required are
properly coordinated to Civil Construction and Electrical services
which shall be checked by Site Mechanical Engineer, Supervisor and
Foreman.
11.2.1 All Fan Coil Unit ( FCU) Ceiling mounted equipment shall be installed
as per approved shop drawing, Material submittal approval and
Manufacturer’s instruction.
11.2.2 Mark/ lay out the Fan Coil Unit (FCU) mounted on the ceiling as per
approved shop drawings.
11.2.3 Installed approved Supports, Anchor fastener as per Material
Submittal approval.
11.2.4 Installation should be as per manufacturer’s instruction.
11.2.5 All Fan Coil Unit ( FCU ) ceiling mounted units slope of the condensate
drain pan shall be in the direction of condensate drain pipe
connection. Ensure that the ceiling mounted units are levelled to
ensure the condensate drain pan slope flows sufficiently to
condensate drain pipe.
11.2.6 Completion of piping connection and valves packages as per approved
shop drawings and manufacturer’s instruction.
11.2.7 Ensure that all valves, strainers, drain cock are installed correctly as
per approved shop drawing shown direction of flow.
11.2.8 Permanent access doors with sufficient clearances to be provided for
servicing and maintenance as per approved shop drawing and
Manufacturer’s instruction.
11.2.9 Provide anti vibration mounts for Fan Coil Units ( FCU ) ceiling hung.
11.2.10 Provide flexible connection at all pipes,ducts,conduits etc. Connecting
to Fan coil units.
11.2.11 Ensure the provision for maintenance cleaning of U –trap / strainer.
11,2.12 Provide protection cover to all FCU equipment installed during the
remainder of construction period.
11.2.13 Prior to False ceiling closure, all equipment installed shall be
identified and as approved by the Consultant.
12.1 After completion of the work, The Site Engineer & Supervisor who perform an
activity are required to raise an RFIA with complete attachment &
information regarding the scope of inspection, including necessary drawings
12.2 After Site Engineer & Supervisor completed their inspection and testing , RFIA
shall be submitted to QAQC Department who shall check and process the
documents to have completed work inspected by Supervision Consultant for
their approval.
12.3 Testing / Run test of the equipment installed shall be as per manufacturer’s
instruction and / or witnessing by the consultant prior for final approval.
Safety of all personnel and equipment is the highest priority of ETA-Debbas JV during
the execution of the Works.
13.2.1 Safety Tool Box Talk / start shall be given by the Site supervisor /
Safety officer every week and/or as deemed necessary.
13.2.2 Safety tool Box Talk / start shall brief the task / subject and shall be
given in languages understandable by multinational workforce.
13.2.3 Safety Tool Box Talk / start attendance shall be recorded on a sheet
and signed by attendees.
Method Statement – Installation of Fan Coil Unit (FCU) Ceiling Mounted
DOCUMENT NUMBER: ED-M-M-M-A-GN-0018
Page 8
DOHA
CONVENTION
CENTER &
TOWER
PROJECT
13.3.1 All materials shall be identified and all MSDS should be read and
understood before use.
13.4 Housekeeping
13.5 Signage
13.5.1 All necessary safety warning and caution signs shall be displayed at
work locations.
13.6 Environment
13.6.1 All materials shall be kept by the storekeeper and a copy given to HSE
Dept. The MSDS shall be followed as per Qatar labour law. Waste
Disposal shall be segregated and disposed by a Certified
Subcontractor and send it to the municipality stockyard for COSH
material as per Qatar law.