Professional Documents
Culture Documents
1. TITLE
2. SCOPE OF WORK
2.1 General Description
2.2 Plant and Equipment
2.3 Materials
2.4 Site Planning & Preparation
2.5 Work Methodology
2.6 Organization, Responsibilities, & Supervision
2.7 Work Force
4. ENVIRONMENTAL ISSUES
4.1 Environmental Impact Assessment
4.2 ES & H main contractor requirements
4.3 Contractual Requirements
4.4 Emergency Procedures
5. QUALITY ASSURANCE
5.1 Contractual Requirements
5.2 Critical Works
5.3 Inspection & Testing
5.4 Follow up & Evaluation
1. TITLE
Method of Statement for HVAC Variable Refrigerant Flow ( VRF )
units & Refrigerant pipes installation.
2. SCOPE OF WORK
The scope of this method statement is to describe the various activities involved in
installation of Variable Refrigerant Flow System ( VRF ) Cealing Concealed Ducted
split type Air conditioning unit and Refrigerant piping to ensure that the works are
performed in a safe, professional and controlled manner as per manufacturer’s
recommendation and project specification requirements.
The following equipment will be used during the operation identified by this method
of statement.
The equipment supplied will be packed for protection against damage during
handling, transport, warehousing & installation. The efficiency of the packing
shall be responsibility of the supplier.
Deliver Variable Refrigerant Flor ( VRF ) as factory – assembled module with
protective crating and covering.
Lift and support units with manufacturer’s designated lifting or supporting
points.
1. Equipment and Tools required for the installation of Refrigerant pipes shall be
planned and arranged for delivery.
2. Site Safety and personal safety equipment shall be planned and arranged in
advance.
3. After the routes for the delivery of equipment are determined, M/S Al
Sulaithi Air Conditioning Ref. & Trad .Est will notify and coordinate with other
contractors affected by the traffic route to avoid any disturbance of other
contractor in the area.
4. M/S Al Sulaithi Air Conditioning Ref. & Trad .Est Site Engineer shall draw up a
traffic flow plan in coordination with M/S Al Sulaithi Air Conditioning Ref. &
Trad .Est ES&H staff and Hamad Al Atiiyah Group ES&H Representative.
M/S M/S Al Sulaithi Air Conditioning Ref. & Trad .Est truck drivers shall follow
the agreed traffic flow plan at all times.
5. The and Hamad Al Atiiyah Group Engineer shall be responsible to control
all the activities related to installation of Refrigerant Piping.
1. M/S Al Sulaithi Air Conditioning Ref. & Trad .Est Interface Coordinator
shall be responsible for coordination of work with other facility
contractor’s.
2. Prior to commencement of the work, if there is any interface with other facility
contractor, they shall be notified in advance for precaution to be taken care of.
Separately marked and Barricade lay down areas to restrict the access shall
be made for the following :
1. VRF Indoor and Outdoor units, Refrigerant pipes and its accessories/
2. Equipment and Vehicles
3. Lifting Tools and Tackles
4. Scaffolding Materials
2.4.5 Communication
The installation of Variable Refrigerant Flow System ( VRF ) and Refrigerant Piping
will be carried out as per AEB‐Arab Engineering Bureau approved drawings and
project specification.
Care must be taken to ensure the Variable Refrigerant Flow ( VRF ) units are
undamaged during transportation. The units will be delivered in containers to
prevent from being damaged.
Inspection of materials deliveries will be conducted and material receiving
report (MRR‐Material Received Report) will be prepared. Prepare a report
and mention if there are incomplete or damaged items and keep such
materials separately to invite responsible person from supplier.
Upon received of materials on site these will have to be inspected by QA/QC
Engineer / Inspector as per the AEB‐Arab Engineering Bureau approved
material submittal to ensure correctness of materials and quantities. Ensure
the insulation is protected from weather elements during the transportation.
A materials Inspection Report (MRR‐Material Received Report) shall be
preapared by QA/QC Engineer / Inspector and the same shall be submitted
to AEB‐Arab Engineering Bureau for their review and acceptance.
2.5.2 Pre – Installation Checks
Before any materials are installed ensure that these have been inspected at
site and have been approved as per the relevant MIR‐materials inspection
report form.
Ensure that all drawings are current and marked ISSUE FOR CONSTRUCTION
Check for space clearance for transportation and installation of the Variable
Refrigerant Flow System (VRF) units.
Check for the correctness of the markings and identification of all the section
prior to carrying out the installation.
Work will be carried out only when all associated work’s have been verified,
completed and access to the plant rooms is provided.
The Variable Refrigerant Flow System (VRF) units will be installed once all
housekeeping plinths and other builder’s works are completed.
Opening on the side of the building must be provided for moving the
equipment into place.
Install the Variable Refrigerant Flow System (VRF) unit level and plumb.
To ensure the equipment to install as per manufacturer recommendation.
To ensure the unit should sit on top of accessible elevated flooring.
To ensure separate floor stand for the unit may be used as support,
independent of the elevated floor and installed prior to the flooring system.
To ensure the unit to install to facilitate service, maintenance, and repair or
replacement of components, Correct equipment for ease of disconnecting,
without interference to the other installations.
To ensure the service clearance on front of the unit as per manufacturer’s
standard.
To install the refrigerant piping to allow the service and maintenance.
The manual electrical disconnect switch shall be installed within 5 Feet from
the unit accordance with codes, or a factory supplied disconnect switch
factory mounted within the unit accessible from the exterior.
Condensate drain pipe shall be extended from the unit to connect
nearest floor drain with ventilation.
Condensing units shall be lifted by means of crane with certified rigging
specialist
To ensure mounting of condensing units or rubber pads with a minimum
deflection of 6.35mm. Vibration isolation devices and installation
requirement are as per the mechanical vibration and Seismic Controls.
To ensure the condensing unit surroundings clearance 450mm from the wall,
obstruction or adjacent unit.
All Refrigerant piping shall be installed with high temperature brazed joints.
The brazing work shall be carried out as per the approved brazing procedure.
The refrigeration piping should isolate from the building by the use of
vibration isolating support ( Clamp )
Tube benders shall be used for all bends before making connection to either
end.
Install horizontal hot‐gas discharge piping with uniform slope downward
away from the compressor.
Install horizontal suction lines with a uniform slope downward to
compressor.
Install traps and double risers to entrain oil in vertical runs.
Liquid lines may be installed level.
Install the filter drier, sight glass in liquid line.
To ensure electrical service to conform to national and local electrical codes
refer to equipment regarding wire size and circuit protection requirements.
Ensure the installation of hangers for copper tubing.
Ensure the piping work is complete, check for leaks and dehydrate the field
piping.
Pressurize the field piping to 150 psig (1035kpa) using nitrogen with a trace
of refrigerant.
Ensure the system for leaks with suitable leak detector.
After completion of leak testing, release the test pressure (per local code)
and pull a deep vacuum on the field piping with a suitable pump.
Insulate the refrigerant pipe between the evaporator and the condensing
unit (suction line and discharged line).
After 30 minutes, check the pressure readings and, if they have not changed,
break vacuum with nitrogen.
Pull a second vacuum to 250 microns or less. Recheck the pressure after 30
minutes.
Verify the Variable Refrigerant Flow System(VRF) units are installed and
connected according to manufacturer’s written instruction.
After installing Variable Refrigerant Flow System(VRF) units and after
electrical circuit has been energized, test for compliance with requirements.
Operational test, after electrical circuit has been energized, start units to
confirm proper motor rotation and unit operation.
Test and adjust control and safeties.
Replace damaged and malfunctioning controls and equipment.
2.6 Organization, Responsibilities & Supervision
Construction Manager
HVAC Engineer
HVAC Supervisor
HVAC
Installation Team
2.6.2 The execution supervision shall be as follows :
Additional protective equipment will be issued when and as required by the risk
Assessment.
All pertinent requirements of this method of statement will be discussed with the
concerned personnel.
M/S Al Sulaithi Air Conditioning Ref. & Trad. Est shall provide first aid kit on site
for the light injuries. In the event of an emergency, all workers will be asked to
evacuate and assemble at the designated assembly area and wait for further
instruction from supervisors.
Evacuation plans shall be posted at the workplace.
Prior to commencement of the work, M/S Al Sulaithi Air Conditioning Ref. & Trad.
Est will secure from and Hamad Al Atiiyah Group Site identification for its workers
and vehicle entry passes for vehicles to be used on site.
Hot work permit and lifting permit shall be obtained prior to commencement of the
works and shall be made available at the work site.
4. ENVIRONMENTAL ISSUES
Appendix 6.2 – Risk Assessment provides the action and/or procedure taken to
minimize the identified risks.
5. QUALITY ASSURANCE
1. Lifting work
2. Working at Height
5.3 Inspection & Testing
Inspection and Testing shall be carried out as per the approved ITP –
Inspection Test Plan, Installation of VRF Units and Refrigerant pipes.
The following documents shall be used to assess and evaluate the progress of
the works :
1. Construction Schedule
2. Inspection Report
3. Weekly Construction Statu