Project Name : Dubai Creek Harbour Development – Dubai Creek Residences

Client Project Manager Engineer Main Contractor

METHOD STATEMENT EXCAVATION & RETAINING WALL FOR TC3 TOWER


CRANE FOUNDATION AT NE2 TO AVOID SOIL EROSION

Dubai Creek Harbour Development - Dubai Creek Residences

Dubai Creek Residences: Main Contract Works

Table of contents

1. Scope/Objectives

2. Reference

3. Access/Egress and Location

4. Health & Safety

5. Definitions

6. Responsibilities/Supervision

7. Sequence/Method to be employed

8. Man-power requirement

9.Equipment requirement

10.Materials requirement

11.Q.C. Approvals & Other documentation

12.Supporting documentation

13.Distribution

14.Other Information

15.Attachments

1
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences

Client Project Manager Engineer Main Contractor

METHOD STATEMENT EXCAVATION & RETAINING WALL FOR TC3 TOWER


CRANE FOUNDATION AT NE2 TO AVOID SOIL EROSION

1. Scope/Objectives
This method statement is to detail & to establish sequence of activities to carryout excavation
& retaining wall for TC3 tower crane foundation at NE2 to avoid soil erosion
2. Reference
2.1 Contract Drawings
 5120544/GEN/S/0101, 105-REV00
 5120544/SPO/S/2001-REV: 00,
 5120544/SPO/S/2002-REV: 01,
 5120544/NPO/S/2002-REV: 01
 5120544/NPO/S/2002-REV: 01
 5120544/SPO/S/2002-REV: 01
2.2 specifications 5120544-D-2001-D-20
2.3 Project Quality Plan TS-ABM-CIV-PQP-0012 R.1
2.4 HSE Plan TS-ABM-CIV-HSE-0014 -R.1
3. Access/Egress and Location
Access to the work place will be through designated and exit pathway.
4. Health & Safety
4.1.Contractor will comply with all safety measures as applicable to project safety
requirement.
4.2.PPE will be worn at all times as required.
4.3.Proper and safe access and enough barricades to the work areas shall be installed &
maintained throughout the working period.
4.4.Proper communication should be ensured.
5. Definitions
ATK-ATK Engineering & Consultant
ABM-Al Basti & Muktha LLC
MS-Method Statements
QCP-Quality Control Procedures
6. Responsibilities/Supervision
2
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences

Client Project Manager Engineer Main Contractor

METHOD STATEMENT EXCAVATION & RETAINING WALL FOR TC3 TOWER


CRANE FOUNDATION AT NE2 TO AVOID SOIL EROSION

6.1 Project Engineer:


 Shall be responsible to organize required machinery, material, man power to engineers
/ supervisor & foreman for effectively executing the work in a safe manner.
 To clarify any discrepancies in the work.
6.2. Site Engineer / Foreman:
 To execute the work as per Project Engineers instructions with the right methodology &
in a safe manner.
 Make sure that all the works are completed prior to offering for inspections.
 To execute the works as per approved method statements.
 To attend all the comments made by Consultant at the time of inspection.
 Ensure the workers PPE, sufficient lighting.
6.3. QA / QC Engineer:
 To check the work is carried out as per the approved method statement.
 To ensure all approved materials are being used
 To raise the W.I.R. after co-ordination with Project Engineer.
7 Sequence/Method to be Employed
 The area near the NE2 raft will be excavated as Stage 1 as shown in the
attached drawing.
 The T12 steel bar will be bind vertically @ 150mm c/c with L-shaped at bottom of the
raft and horizontally @ 200mm c/c with the existing dowels bars which is at the top of
the raft as shown in the attached drawing.
 The Shuttering will be done and the concrete will be poured into the hanging retaining
wall .
 Then the stage 2 still be excavated as shown in the attached drawing.
 The Cement slurry will be applied to the vertical portion of the soil after making the
manual compaction for the temporary support.
 The L-shaped bars will be made straight and lapping will be done with T12 steel bar
vertically as shown in the attached drawing.
 The Shuttering will be done and the concrete will be poured into the hanging retaining
wall with the concrete chute as shown in the attached drawing.
3
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences

Client Project Manager Engineer Main Contractor

METHOD STATEMENT EXCAVATION & RETAINING WALL FOR TC3 TOWER


CRANE FOUNDATION AT NE2 TO AVOID SOIL EROSION

 Similarly stage 3 will be done as per the attached drawing.


 Then TC-03 foundation will be casted.
8. Man Power Requirement
 Site Engineer
 QA/QC Engineer
 Foreman
 Charge hand
 Mason
 Skilled and unskilled labor
9 Equipment required
 Excavator
 Shovel
 JCB
 concrete Truck
 Hand Shovel.
 Compactor
10 Materials required
 Hand Shovel.
 Plump bob
 spirit level
 Props (to provide side supports )
 Shuttering materials.
11. QC APPROVAL AND OTHER DOCUMENTRY REQUIREMENTS
Follow approved Method Statement, ITP, QCP, HSE Plan, and Material Approval.
12. SUPPORTING DOCUMENTATION
This MS to be read in conjunction with the below referenced documents
 Contract Drawings and specifications
 Project Quality Plan
 Project HSE Plan

4
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences

Client Project Manager Engineer Main Contractor

METHOD STATEMENT EXCAVATION & RETAINING WALL FOR TC3 TOWER


CRANE FOUNDATION AT NE2 TO AVOID SOIL EROSION

13. DISTRIBUTION
Copies of this MS will be circulated to the following for Information & action
 Project Manager
 Construction Manager
 Site Engineer
 QA/QC Engineer
 HSE Engineer
14. OTHER INFORMATION
Ensure that all the activities have been carried out to suit the site conditions and involved with
Site in Charge.

15. ATTACHMENTS
 Risk Assessment
 Section Drawings