Project Title: MASALLI-ASTARA MOTORWAY SECTİON B

INSPECTION & TEST PLAN


(POST TENSIONING WORKS)

Doc. No: MAAS-MS-015 Issue Date: Rev No.: 0

Inspection*
No Activity Description Stage/Frequency Records Acceptance Criteria Inspection/Test Procedure
NIPPON

For every different source


Source of Reinforcement and Independent Laboratory Certificates, Test
1 compliance with requirements tests with 6 month reports
Engineers approval Submit RFT to Engineer for approval H
intervals

Engineers acceptance
Approved Concrete Mix Mix design formula,
2 Design
For every concrete class
Test reports
strength quality and Submit RFT to Engineer for approval H
verification testing

Prior to fabrication of Compliance with Designers


Work Notification
3 (Commencement RFI)
precast post tensioning RFI, Survey Reports requirements and consented Submit RFI to Engineer for Approval H
beams drawings

Before formwork and Correct location as shown on


4 Survey and setting out
rebar installation
Survey Reports
designers drawings
Internal Check Lists S

The reinforcing cage shall be


prepared in line with drawings
*correct length and diameter
Production and installation of Certificates, Check *correct bending radius, no
5 reinforcement bars
After lean concrete placed
Lists cracks
Internal Check Lists S
* splicing length,
*cleanness of reinforcement
*Concrete spacers installed

Correct location as shown on


6 Formwork Installation Before Placing Concrete Check Lists designers drawings to form Internal Check Lists S
required section of concrete

7 Testing and sampling of Slump test – for every Test Reports *Slump of concrete for precast Internal Check Lists, Lab reports W
Concrete mixer beams preferred to be between
Temp Mea - for every 70 mm to 140 mm
mixer *Max Temperature 32 oC
*Inspection
R– Review : Record/
H - Hold Point: Engineer’s notification required. Contractor W – Witness Point : Engineer’s notification S - Surveillance : No notification required but
Documents review
may not proceed beyond this point without confirmation from required but Contractor may proceed if activity may be subjected to Engineer
the Engineer Engineer do not attend Surveillance/ Monitoring
Project Title: MASALLI-ASTARA MOTORWAY SECTİON B

INSPECTION & TEST PLAN


(POST TENSIONING WORKS)

Doc. No: Issue Date: Rev No.: 0

Inspection/Test Inspection*
No Activity Description Stage/Frequency Records Acceptance Criteria
Procedure
NIPPON

Cube samples – one set


up to 25 m3
*Max free fall of concrete is 2m
*Compaction o concrete shall
After satisfactory formwork
8 Placement of Concrete
and rebar inspection
Check Lists be done by vibrators Method Statement, Check Lists R
*Smooth surface finishing
required
Free from major cracks, big air
After transportation to holes D>10 mm, segregation,
9 Post Pour Inspection
stockyard
Check Lists
honeycombs and other
Check Lists R
concrete deficiencies

*Exposed aggregate
10 Forming Construction Joints Prior to installation Check Lists *Rough surface Visual inspection R
*No major cracks and big holes

RFT, RFI,
All Requests and checklists
11 Pre-Handover Prior to installation Lab reports,
completed and signed
Review H
Survey reports

Inspection*
W – Witness Point : Engineer’s notification R– Review : Record/
H - Hold Point: Engineer’s notification required. Contractor required but Contractor may proceed if
S - Surveillance : No notification required but
Documents review
may not proceed beyond this point without confirmation from activity may be subjected to Engineer
Engineer do not attend (to be actionized by
the Engineer (to be actionized by UAJV Representative) Surveillance/ Monitoring
UAJV Representative)