Inspection and Test Plan


For BlockWork Installation

Document reference CDP-RDC-AR-MAL-QAC-0001

Document produced by:

Road and Construction

Project No. 1456 WP number SC-0089


Baku, CRESCENT DEVELOPMENT PROJECT
Document tracking sheet
Revision Date Description Status QA signature
0 01/04/2022 Inspection and Test Plan Rejected R.S
1 07/04/2022 Inspection and Test Plan for Approved with R.S
Comments
BlockWork Installation
2 08/04/2022 Inspection and Test Plan for For Approval R.S
BlockWork Installation
INSPECTION AND TEST PLAN

CONCRETE WORK

PROJECT Name / (N0.)


CONTRACTOR ITP DOC./ Rev No. 02 INSPECTION POINTS AND
Crescent Development Project RESPONSIBILITY
NAME:
Road and Construction
ITP CONTRACTOR
QUALITY RELATED REFERENCE CHARACTERISTICS ACCEPTANCE VERIFYING SUB-
CODE PASHA
ACTIVITY DOCUMENT TO BE VERIFIED CRITERIA DOCUMENT CON Const. QA/QC
No


Physical Check for A1 W2 W1 M-R1
1 AAC Block Work Approved Shop Applicable Drawing Work Inspection Request
Joints size, Vertical
Drawing and horizontal
Criteria

During Mix
Inspection Report –
IM&T Calibration Design Approval.
Survey Equipment International / National General
2 Procedure Cal. Certificate TC R1 R1 R1
Calibration Standard & Calibration Agency
Review with
Certificate
Frequency Wise

Approved Drawing Physical Inspection Approved MAR with Field Material


3 Material Receiving
and Approved and Document Receiving Status Receiving Inspection A1 R1 W2 R1
Inspection
(MAR) Review Prior to Use Registration Sheet Report
Make Sure Smooth Reasonable Flat and
5.3.3.3 of ACI 301 Work Inspection Request
Surface Finish Finish By Trowel Smooth Surface A1 W2 W1 M-R1
4 Approved Drawing
and/or Proper Tools Condition.

Physical Check for Material


Approved Shop Work Inspection Request
Chemical Anchorage Depth, Cleaning Specification A1 W2 W1 M-R1
5 Drawing afterward

ABBREVIATION OF INSPECTION POINT AND RESPONSIBILITY


AR Approval Required A1, A2 Actual Inspection (A1:100%, A2:10%) W1, W2 Witness Inspection (W1:100%, W2:10%) H Hold Point
TC Test Certificate Required S Operation Surveillance R1, R2 Review of Documentation (R1:100%, R2:10%) M Monitoring

Physical Check to
Concrete Concrete Poured Max 32℃ Min 5℃ Work Inspection Request
6 8.4.2 of ACI 318, A1 A2 W2 M
Temperature Phase (each mix
truck)

Min 5℃
7 Ambient Check to Weather (Use heating, covering Work Inspection Request
5.3.1.6 of ACI 301 A1 A2 W2 M
Temperature Condition means to maintain
required temperature)
Physical Check for
Size, Surface
8 Approved Work Inspection Request
Formwork Cleanliness, Form
Applicable Drawing A W2 W1 W2
Installation Drawing Support, Embedded
1
Items & Box
Anchor etc.
Formwork Removal Concrete Review and Verify a) Vertical Forms
Pouring of Curing Status with Normal
9 Plan for Condition: Work Inspection Request A W2 W1 M-R1
Based on Pouring
Critical After 48hours 1
Date/Time and
Structure Compressive b) Horizontal Forms
Strength Verify for with Suspended
Critical Structure Condition: After
7-Days and
Verified
70% Design Comp.
Strength
Physical Check for
10 Rebar Size,
Reinforcement Approved Cleanliness Work Inspection Request
Applicable Drawing A W2 W1 W1
Rebar Installation Drawing Dimension, Overlap
Length and Spacer 1
Fasten & Distance
Document review of
Approved drawing
Manufacture Data (MAR)-Material Approval
11 Form Oil & Manufacturer Applicable Drawing AR W2 AR M-R1
Sheet and/or Sample Request for Construction
data sheet
check, if required

Physical Check for Applicable Drawing Work Inspection Request


Approved Shop AR W2 W1 M-R1
size, correct
12 Rockwool Drawing Placement

ABBREVIATION OF INSPECTION POINT AND RESPONSIBILITY


AR Approval Required A1, A2 Actual Inspection (A1:100%, A2:10%) W1, W2 Witness Inspection (W1:100%, W2:10%) H Hold Point
TC Test Certificate Required S Operation Surveillance R1, R2 Review of Documentation (R1:100%, R2:10%) M Monitoring
CRESENT DEVELOPMENT PROJECT

BLOCK MASONRY INSPECTION CHECKLIST/BLOK HÖRGÜ YOXLAMA VƏRƏQƏSİ


CLIENT / SİFARİŞÇİ PASHA CONSTRUCTION Site / Tikinti sahəsi Mall Building
PROJECT / LAYİHƏ CDP CRESENT DEVELOPMENT PROJECT Dwg No.
CONTRACTOR/ PODRATÇI ROAD AND CONSTRUCTION Area / Ərazi Zone 2
Project No. / Layihə N-si 1456 Structure/ Konstruksiya Blockwork
Report No. / Hesabatın N-si Inspection Date:
Description of Required inspection: Block masonry work

DATE OF DATE OF
Masonry Bloks / Hörgü Blokları N/A YES NO Masonry Bloks / Hörgü Blokları N/A YES NO
INSPECTION INSPECTION

1.Cleaned the entire floor before starting the line-out of masonry? 10.Has all the Vertical joints been 1/3?
Hörgü işinə başlamazdan əvvəl bütün mərtəbəni təmizlədinizmi? Bütün Şaquli birləşmələr 1/3 olub??

11.Galvanized L-shaped elements should be fixed to


2. Check if the Mortar mix (mixed as per specification) is uniform and of optimum the concrete floor and beam every 1.20 m on a
workability (Ease to work with)? supporting masonry?
Məhlul qarışığının (spesifikasiyaya uyğun olaraq qarışdırılır) vahid və optimal Sinklənmiş L- profil elementlər beton döşəməyə
işləmə qabiliyyətinə malik olub-olmadığını yoxlayın (işləmək asandırmı ?) bərkidilməli və dayaq hörgü üzərində hər 1,20 m-dən
bir şüa vurulmalıdır?
13.A mesh should be thrown in every 2 rows on the
3. Does the conformity of wall types and dimesions comply with the drawings?
masonry wall?
Divar tipi ve ölcüləri projeyə uygundurmu?
Hörgü divarına hər 2 cərgəyə bir mesh atılıbmı?
14.Are all door & window openings are as per the
4. Are dimensions of block as per drawings?
drawing provided? Bütün qapı və pəncərə açılışları
Blokun ölçüləri çertyojlara uyğundurmu?
təsvirə uyğundurmu?
5. Every max 3.00 meter stiffening columns and beams as frame work shall be
15. Are all courses are in plumb,line & level? Bütün
reinforced with reinforced concrete stiffening work ?
kurslar plumb, line və səviyyədədir?
Maksimum hər 3metrədən çərçivə kimi gücləndirici sütün və tir bərkidilməlidir.

6. Dimensions of reinforcement to be used in beams ø12 f for wall? 16. Has the entire floor been cleaned after the work?
Kirişlərdə istifadə olunacaq armaturun ölçüləri ø12 divar üçün? İşdən sonra bütün döşəmə təmizlənibmi?

7. The clamps must be spaced f10 200mm apart? Qısqaclar bir-birindən f10 200
mm məsafədə yerləşdirilməlidir?

8. Are Mechanical Devices & System checked?


Mexanik cihazlar ve sistem kontrolu yoxlanılıbmı?

9. Is firestopping works completion confirmed by Site Team?


Sahə rəhbəri yanğına qarşı işlərin bitməsini təsdiq edirmi?

ÖLÇME / SURVEY
AD & SOYAD / NAME & SURNAME Mirza Guliyev
Road AND Construction İMZA / SIGNATURE
TARİX / DATE
AD & SOYAD / NAME & SURNAME
PASHA CONSTRUCTION İMZA / SIGNATURE
TARİX / DATE
8 . Maddə Elektrik, Mexanik qrupları tərəfindən yoxlanılmalıdır. Qalanları tikinti qrupu tərəfindən yoxlanılmalıdır. Clause 8 is to be checked by Electrical and Mechanical teams respectively. Remaining ones are to be checked by Construction Team.

Remarks / Qeydlər:

CONTRACTOR / PODRATÇI CLIENT / SİFARİŞCİ

ROAD AND CONSTRUCTİON PASHA CONSTRUCTION


SİTE MANAGER SİTE ENGİNEER

Name/ Adı Ramin Suleymanov Ziya Majid


Signature/İmza
Date/Tarix