Professional Documents
Culture Documents
-Approved Drawings
1.1 -Approved Method Statement Project Specs. R03-C02D02-ZFP-SPC-Ar-0001 Project specification required H RH/H RH/H RH
-Approved Material Submittal Sec.042000
-Approved Mix Design
2.0 Material Receiving
2.1
Masonry Reference standards -Concrete Masonry Units: ASTM C129 H H H
Unit & Related - Provide units with minimum average net area
Masonry Compressive
Accessories etc. strength of 4.14 MPa
. Samples for Concrete Unit Masonry
Project Specs. R03-C02D02-ZFP-SPC-Ar-0001 Reference standards
Handling, Storage and Preservation Sec.042000
Inspection of Block work Materials
3.0 Mock Up
3.1 Mock up preparation and approval Block work method Statement - Mock up to be prepared and approved by W S S
Supervision Consultant as per the following
wall types
.
A A. block masonry walls for plaster finish.
B Cavity wall.
-
4.0 Installation
4.1 Block work mortar mixing Approved Method Statement Reference Standard W W W W
1|Page
3.4 Concrete:
Base coat for two-coat plasterwork as
follows: 1. Portland
Cement Mix: 1 part
Portland cement and 2- 1/2 to 4 parts
sand
Aggregate. 2. Fiber Reinforcement
Base-Coat Mixes for Use over.
Concrete
Masonry: Base coat for two- coat
plasterwork
as follows: 1. Base Coat: 1 part
Portland
cement, 5 parts aggregate, lime
replacing plasticizer as per
manufacturer’s
Recommendation. 2. Fiber
Reinforcement:
Comply with manufacturer’s printed
Instructions.
CMU Block works / Installation of Reference Standard Ensure that the Installation of Concrete W H H H
Blocks Masonry Blocks (i.e. Mortar bedding &
Jointing, Horizontal Joint Reinforcement,
Control Joints, Repair, Pointing &
Cleaning, Curing Install according to ASTM C
1063 and at
locations indicated on Drawings.
Masonry Accessories At distances between control joints of not
greater than 5.5 m
1- As required to delineate plasterwork intoareas
(panels) with length-to-width ratios of not
greater than 2- 1/2:1.
2- Where control joints occur in
surface of construction directly behind plaster
Plumpness/Vertically Check Reference Standard A. Plumbness: Not more than 1.00 mm W H H H
per
one meter of gradual change, maximum
3.00 mm
Level: Not more than 1.00 mm per one
meter of gradual change, maximum 3.00
mm
Compressive Strength Reference Standard For CMU Blocks 4.14 MPa For Mortar 5 +- 1 W H H H
N/ mm2 Proportion grout in accordance
with ASTM C 476, Table 1 or paragraph
4.2.2 for specified 28-day compressive
strength indicated, but not less than 14 MPa
4 Pre-Commissioning
4.1 Not Applicable
ITP Approval Signature
Sub-Contractor (If Applicable) Main Contractor SC RSG
Name: Name: Name: Name:
2|Page
Signature Signature Signature Signature
Surveillance: QA/QC team to monitor work in progress without notice from the construction organization/Random check selection.
Project:
R03C02C02-Turtle Bay Village (TBV)
Building Name
Survey
Civil
Mechanical
Electrical
3|Page
Note:
1. Signature means agreed with the above mentions.
4|Page