POSORJA MULTIPURPOSE TERMINAL

TERMINAL WORKS

CONTRACTOR ENGINEER

CHINA HARBOUR CULLEN GRUMMITT & ROE

INSPECTION & TEST PLAN


PILING WORKS

Doc No.
PMPT-ITP-005-04

REVISIONS RECORD
Rev. No. Date Issued by Approved by Description

01 15/12/2017 Yafeng Wang Shi Tianhua Inspection Test Report

02 07/02/2018 Yafeng Wang Shi Tianhua Inspection Test Report

03 28/03/2018 Yafeng Wang Shi Tianhua Inspection Test Report

04 02/05/2018 Yafeng Wang Shi Tianhua Inspection Test Report


Doc. No.: PMPT-ITP-005-04
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 4

Date: 02/05/2018
INSPECTION TEST REPORT
Page: 2 of 3
PILING WORKS

PILES CONSTRUCTION

PERFORMANCE & INSPECTION TYPE OF INSPECTION/


SL NO ACTIVITY DESCRIPTION REFERENCE DOCUMENT ACCEPTANCE FRECUENCY FUNCTION SURVEILLANCE RECORD
FUNCTION
CRITERIA PERFORMER CHECKER CHEC CGR
CHEC CHEC
In accordance with Before start Planing Construction Method
1 Method Statement Employer´s Requirements Employer´s works engineering Manager H H/R Statement
A.10.11 Requirements
In accordance with Before start Environmental Construction Environmental
2 Enviromental Permit Employer´s Requirements Employer´s works Engineer Manager H R Permit Certificate
A.11.2.1 Requirements
In accordance with Before start Environmental Construction Access Permit
3 Access Permit Employer´s Requirements Employer´s works Engineer Manager H R Certificate
A.10.5.1 Requirements
In accordance with Before start Safety Incharge Construction Job Safety
4 Job Safety Analysis Employer´s Requirements Employer´s works Manager H H/R Analysis
A.10.11.1 Requirements
5 Steel casing MAS

5.1 Large diameter steel tubular


Employer´s Requirements ASTM A 252 Each pile Lab Assistant QA/QC H H Test report
piles
A.1.6.2.1 Engineer /PMPT-MAS
6 Piles concrete MAS

6.1 Workability ASTM C143/ Slump 200mm +- For every Lab Assistant QA/QC H H Test report
Employer´sRequirements 20mm batch at Engineer /PMPT-MAS
C.1.2.5.3 batching plant
and at the
work face

6.2 Compressive strenght test Employer´sRequirements ASTM C172 and Min 4 test Lab Assistant QA/QC H H Test report
C.1.3.4 ASTM C39. specimens / Engineer /PMPT-MAS
40 Mpa 50 cum

6.3 Flexural Strength Employer´s Requirements ASTM C1609 3 flexural Lab Assistant QA/QC H H Test report
C.1.3.4.1.7 beams per Engineer /PMPT-MAS
elementn as
minimun
ASTM C1202,
6.4 Rapid Chloride Permeability Employer´s Requirements AASHTO T277 Every 2,000 Lab Assistant QA/QC H H Test report
Test C.1.2.5.3 (acceptable limit below m3 Engineer /PMPT-MAS
1500 coulomb)
7 Reinforcement steel bar MAS
1 impact test
7.1 Bend Test Employer´s Requirements ASTM A706 per heat Lab Assistant QA/QC H H Test report
C.1.2.5.5 Engineer /PMPT-MAS
1 tensile tests
7.2 Tensile Test Employer´s Requirements ASTM A706 per heat Lab Assistant QA/QC H H Test report
C.1.2.5.5 Engineer /PMPT-MAS
1 product
7.3 Chemical Analysis Employer´s Requirements ASTM A706 chemical Lab Assistant QA/QC H H Test report
C.1.2.5.5 composition Engineer /PMPT-MAS
test per heat
8 Piles construction
The piles shall be Steel cage
8.1 Installation of steel casing Employer´s Requirements installed within a Each pile Site Engineer QA/QC H H inspection
C1.5.6.1 and C 1.5.6.2 tolerance of 75 mm in Engineer ITP-CL05-2
any direction at the
head. Piles shall be
installed vertically
within a tolerance of
1°. .

8.2 Drilling hole According to the design the socket must be 5 Each pile Site Engineer QA/QC H H Drilling
drawings D-132.003-304-12 meters and must be Engineer inspection
below the design ITP-CL05-3
RT-132.003-304-00-008-R01-B depth.
For axis 1-14
according to the tables
“Socket length for
Piles “
according to the Inspection steel
8.3 Placement of Steel design drawing Each pile Site Engineer QA/QC H H bars work
Reinforcement According to the design overlap length of 2m Engineer ITP-CL05-4
drawings D-132.003-304-12 and he thickness of
the concrete cover is
7.5cm.
Approved mix concrete
8.4 Pouring of Concrete Employer´s Requirements ACI 318 Each pile Site Engineer QA/QC H H receiving
C.1.4.2.1 Engineer inspection
record,ITP-
Temperature not
CL05-1
exceed 32 ℃

Slump 200 to 240 mm

Strenght f’c 40 Mpa at


28 days
Standard Test Method for High
8.6 Strain Dynamic Employer´s Requirements ASTM D 4945 10% of piles Site Engineer QA/QC H H Test report
Testing of Piles. C.1.5.7.4 as minimun Engineer
Dynamic Load Tests: Low
8.7 Strain Employer´s Requirements ASTM D5882 Each pile Site Engineer QA/QC H H Test report
C.1.5.7.6 Engineer

Note :
1) Strictly adhere with HSE plan for safe work enviroment.
2) Materials wich are not icluided in this ITP and need arises to use at site and same shall be added in ITP in later stage.
3) All items in wich cement is used shall be cured for minimun seven days.
LEGEND H = Hold Point W = Witness Inspection R = Review of Document S = Surveillance