CONTRACTOR ENGINEER
Doc. No.
PMPT-ITP-053-01
REVISIONS RECORD
Rev. No. Date Issued by Approved by Description
01 16-05-2019 Roberto Pazmiño Tianhua Shi Pump House Construction Inspection Test Plan
Doc. No.: PMPT-ITP-053-01
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 1
Date: 16-05-2019
INSPECTION & TEST PLAN
Page: 2 of 9
Pump House Construction
Employer´s Requirements In accordance with Employer´s Before start works Safety In charge Construction Job Safety
4 Job Safety Analysis A.10.11.1 Requirements Manager H R Analysis
Employer’s Requirements In accordance with Employer´s Before start works Planning Construction Test report
C.1.3.4, C.1.4.2, C.1.4.5 Requirements engineering Manager H R /PMPT-MAS
5 Concrete MAS
PMPT-MAS-108
ACI 211.1
For every batch at
5.1 Workability ASTM C143/ Employer’s Slump 200mm +-20mm batching plant and Lab Assistant QA/QC H W Test report
Requirements at the work face Engineer /PMPT-MAS
C.1.2.5.3, C1.4.1.2
5.2 Temperature Employer’s Requirements < 32 Celsius degrees For every batch at
C.1.3.5.5 batching plant and Lab Assistant QA/QC H W Test report
at the work face Engineer /PMPT-MAS
Employer’s
5.3 Compressive strength Employer’s Requirements ASTM C172 and ASTM C39. Requirements Lab Assistant QA/QC H H Test report
test C.1.3.4 40 Mpa Min 4 test Engineer /PMPT-MAS
D-132.003-300-19/20-37 specimens / 50 m3
and 38
3 flexural beams
5.4 Flexural Strength Employer´s Requirements ASTM C1609 per element as Lab Assistant QA/QC H H Test report
C.1.3.4.1.7 minimum Engineer /PMPT-MAS
ASTM C1202, AASHTO T277
5.5 Rapid Chloride Employer´s Requirements (acceptable limit below 1500 Every 2,000 m3 Lab Assistant QA/QC H H Test report
Permeability Test C.1.2.5.3 coulomb) Engineer /PMPT-MAS
Doc. No.: PMPT-ITP-053-01
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 1
Date: 16-05-2019
INSPECTION & TEST PLAN
Page: 3 of 9
Pump House Construction
7 Material Requirements
7.1 Steel for structural steel Rolled sections, plates and Grade 50. In accordance with Before Start Works Manufacturer QA/QC R Test report
work. bars. ASTM A572 D-132.003-311-15-031-R02-E Engineer H /PMPT-MAS
7.2 Structural Steel Works Hot-Formed Welded and Grade 50. In accordance with Before Start Works Manufacturer QA/QC R Test report
Hollow Sections Seamless High-Strength, D-132.003-311-15-031-R02-E Engineer H /PMPT-MAS
Low-Alloy Structural Tubing.
ASTM A572
7.3 Nuts, bolts and washers ASTM A325, A449, ASTM Grade 8.8 Galvanized. Before Start Works Manufacturer QA/QC Test report
for structural A563 Employer´s Requirements Engineer H R /PMPT-MAS
connections. Table.1.10.
7.4 Tolerances and rolling ASTM A6 Plates and bars In accordance with the Before Start Works Manufacturer QA/QC R Test report
for structural steel ASTM A6 Universal Employer’s Requirements. Engineer H /PMPT-MAS
Beams, columns, rolled Section C.1.6.2.3
Joists, Channels and tees
ASTM A6 Angles
ASTM A500, ASTM
A501Structural Hollow
Sections
7.5 Quality surface of ISO 8501-1 The surface conditions of steel Before Start Works Manufacturer QA/QC Test report
material. ASTM A529 for fabrication shall be in Engineer H R /PMPT-MAS
ASTM A618 accordance with the
ASTM A 568 Employer’s Requirements
ASTM A924 C.1.6.2.4, C.1.6.2.5, C.1.6.2.6
Doc. No.: PMPT-ITP-053-01
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 1
Date: 16-05-2019
INSPECTION & TEST PLAN
Page: 4 of 9
Pump House Construction
ASTM A1085
ASTM A 1003
ASTM A
7.6 Welding requirement Employer’s Requirement All Welding shall be carried out Before Start Works Manufacturer QA/QC Test report
C.1.6.3 in accordance with the Engineer H R /PMPT-MAS
requirements of AWS D1.1,
unless otherwise stated.
7.7 Testing laboratory. Employer´s Requirements The Contractor shall submit Before Start Works Manufacturer QA/QC R Test report
C.1.6.4.1 test certificates from Engineer H /PMPT-MAS
independent testing
laboratories approved by the
Engineer.
7.8 Testing Frequency Employer´s Requirements The minimum frequency of Before Start Works Manufacturer QA/QC Test report
C.1.6.4.2 these tests shall be in Engineer H R /PMPT-MAS
accordance with the following:
7.9 Tests Required Employer´s Requirements Charpy Impact Test Before Start Works Manufacturer QA/QC R Test report
C.1.6.4.5 Tensile Test Before Start Works Engineer H /PMPT-MAS
Cross Weld Test
Chemical Analysis
Geometrical properties
Bend tests
Flattening tests
Eco-tip testing
7.10 Samples dimensions Employer´s Requirements Sample Characteristics: Before Start Works Manufacturer QA/QC Test report
C.1.6.4.6 Samples 300mm x 300mm and Engineer H R /PMPT-MAS
350mm x 350mm.
Shall be taken perpendicular to
the direction of the spiral weld
and the weld shall pass exactly
through the middle of the
sample.
7.11 Steel protective Employer´s Requirements Protection for severe marine Before Start Works Manufacturer QA/QC Test report
treatment C.1.6.5.1 environmental exposure Engineer H R /PMPT-MAS
Employer´s Requirements Protective treatments to all
C.1.6.5.2 metallic items
Employer´s Requirements Grit-Blasted to Sa 21⁄2 in
C.1.6.5.3 accordance with ISO 12944-4
Employer´s Requirements Galvanizing and its testing
C.1.6.5.4 ASTM-A123
Employer´s Requirements Any coating damage shall be
C.1.6.5.5 repaired according to ASTM
Employer´s Requirements A123
Doc. No.: PMPT-ITP-053-01
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 1
Date: 16-05-2019
INSPECTION & TEST PLAN
Page: 5 of 9
Pump House Construction
8 Pump House
Construction
8.1 Pre-Assembly of steel PMPT-MST-077-01 The steel frame is pre- All the frame Site Engineer QA/QC Test report
frame Pre-assembled Fire assembled to reduce the Engineer H R /PMPT-MAS
Pump Building Drawings underwater operation.
All the bolts are fixed in the pre-
assembly process, except the
bolts which are used for
attached the structure to the
pile.
The perpendicularity and
elevation are adjust using a
level.
All the welding surface needs
to be tested and repaired
following the supplier
instructions.
8.2 Lifting and fasten the PMPT-MST-077-01 Four 6t chain block is adopted All the structure Site Engineer QA/QC Test report
clamp bolts Pre-assembled Fire between the lifting rope and the Engineer H R /PMPT-MAS
Pump Building Drawings steel frame.
The clamps on both sides of
the steel sleeve frame are
firstly set on two piles
Then, the steel frame is slowly
lowered along the two piles
until the steel sleeve is reached
the right elevation
The steel sleeve elevation and
position are adjusted by chain
block, divers tighten bolts in the
blue rectangle shown in the
following picture.
8.3 Precast Sleeve PMPT-MST-077-01 The sleeve will be placed Every Precast Site Engineer QA/QC H H PMPT-INR
installation Pre-assembled Fire with PC001 type, 100cm Di. sleeve Engineer
Pump Building Drawings Top level Sleeve +4.40m
Doc. No.: PMPT-ITP-053-01
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 1
Date: 16-05-2019
INSPECTION & TEST PLAN
Page: 6 of 9
Pump House Construction
D-132.003-308-12-003-
R00-B
8.4 Fasten the upper hoop PMPT-MST-077-01 The lifting frame and chain Each Piece Site Engineer QA/QC Test report
bolts. Pre-assembled Fire block shall be removed and Engineer H R /PMPT-MAS
Pump Building Drawings handed over to the civil
engineering for pile cap
construction.
After the construction of pile
cap is completed, the hanging
basket can be used to fasten
the bolts.
the clamp can be removed
temporarily and can be
reinstalled and fastened after
the construction of pile cap is
completed.
8.5 Pump House PMPT-MST-077-01 Provisional platform-I beams Visual inspection Site Engineer QA/QC W W
Provisional Structure D-132.003-308-12-003- 25 and 50 cm depth once that the Engineer
R00-B Support piles 00B and 00C provisional
structure starts to
work
8.6 Pump house formwork PMPT-MST-077-01 Once that the temporary Once that the Site Engineer QA/QC H H PMPT-INR
and steel works super D-132.003-308-14-001- structure is ready, the steel bar works for Engineer
structure R01-B formwork for the first stage of each stage are
D-132.003-308-15-001- 25 cm of height of the fire pump complete an
R01-B house will be assemble, then inspection will be
D-132.003-308-15-002- the steel bar works start carried out of the
R01-B according the design drawings. formwork and the
D-132.003-308-15-003- contrast the quay steel bar.
R01-B superstructure for the fire pump
D-132.003-308-15-004- house the contractor has
R01-B decided not to use
D-132.003-310-00-015-R02 prefabricated elements and to
place concrete in the entire
structure on site, that is why the
casting will be carried out in
three phases. The first stage of
25 cm, second stage 30 cm
and third stage of 66 cm as
shown in drawings.
Doc. No.: PMPT-ITP-053-01
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 1
Date: 16-05-2019
INSPECTION & TEST PLAN
Page: 7 of 9
Pump House Construction
8.7 Pump house concrete PMPT-MST-077-01 Once that the steel bar and Engineer will Site Engineer QA/QC H H PMPT-INR
super structure D-132.003-301-23-003 formwork work for each stage require the Engineer
Pre-assembled Fire are completed, the poured following nominal
Pump Building Drawings. concrete will be done. testing frequency:
Employer Requirements Concrete elements shall be Slump test each
Part C section C1.3.2 designed in accordance with truck load. All
the requirements of the latest slump testing
edition of ACI 318 shall be carried
All structural concrete shall out at work face.
meet the Table C.1.6 of the Slump test for
employer requirement as a consistency shall
minimum requirements. be taken in
accordance with
ASTM C143. Any
batches of
concrete failing to
meet the specified
slump criteria
shall not be
placed and shall
be replaced with
new concrete in
conformance with
the employer’s
requirements.
The minimum
frequency of
sampling of
concrete of each
grade shall be in
accordance with
table C.1.7 of the
Employer
requirements.
8.8 Location of pump house PMPT-MST-077-01 The location should require a Each Connection Site Engineer QA/QC Test report
D-132.003-301-23-003 minimum of elbows and fittings Engineer H R /PMPT-MAS
Pre-assembled Fire in the discharge line to
Pump Building Drawings. minimize friction losses.
8.9 Foundation PMPT-MST-077-01 Before pouring a foundation, All Foundation Site Engineer QA/QC Test report
D-132.003-301-23-003 locate anchor bolts per the Engineer H R /PMPT-MAS
Pre-assembled Fire outline drawing.
Pump Building Drawings. Allow for alignment ¾ to 1-
Doc. No.: PMPT-ITP-053-01
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 1
Date: 16-05-2019
INSPECTION & TEST PLAN
Page: 8 of 9
Pump House Construction
8.11 Grouting PMPT-MST-077-01 Build a strong form around the Site Engineer QA/QC Test report
D-132.003-301-23-003 baseplate to contain the grout. Engineer H R /PMPT-MAS
Pre-assembled Fire Pump Adjust the metal shims or
Building Drawings. wedges until the top flange of
the discharge head is level
Tighten the foundation bolts
snugly, but not too firmly, and
recheck the alignment before
grouting.
The pump must be level to
within 0.001 inch per food of
width.
14 Days after the grout has
been poured or when it is
thoroughly cured and dry,
apply an oil base paint to
exposed edges of the grout to
prevent air moisture from
meeting the grout.
Doc. No.: PMPT-ITP-053-01
POSORJA MULTIPURPOSE TERMINAL WORKS
REV. 1
Date: 16-05-2019
INSPECTION & TEST PLAN
Page: 9 of 9
Pump House Construction