Inspection of I Steel Casing Welding Construction Site: Posorja Multipurpose Terminal-Terminal works-Part/Lot No.: Section of Specs.: Drawing No.

The document describes an inspection of steel casing welding for a construction site. It includes acceptance criteria for identifying non-conformities during inspection of steel pipe piles, including identification number, diameter, thickness, circumference, and damage. Any non-conformities found are described and their remedy is noted.

Uploaded by

hz135874
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views1 page

Inspection of I Steel Casing Welding Construction Site: Posorja Multipurpose Terminal-Terminal works-Part/Lot No.: Section of Specs.: Drawing No.

The document describes an inspection of steel casing welding for a construction site. It includes acceptance criteria for identifying non-conformities during inspection of steel pipe piles, including identification number, diameter, thickness, circumference, and damage. Any non-conformities found are described and their remedy is noted.

Uploaded by

hz135874
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Inspection of ITP- I INR-

Steel Casing Welding CL05-2


CL-
Construction Site: Posorja multipurpose terminal-terminal works-
Part/Lot No.:
Section of Specs. : Drawing No.:
** Use the diagram to identify any Non-conform and locate the fail.

Total Length ____________

L1_______________ L2_______________ L3_______________ L4_______________

Inspections *
Date Does not
Work performed by:  CHEC  Sub-contr. : Conforms
conform

1 Identification number? Numb. ID


2 Steel Pipe Pile Diameter ___________
Acceptance Criteria

3 Thickness Inspection OK?


4 Measurement and thickness according with the specifications?
5 Circumference and Alignment of the Steel Pipe (Visual Check)
6 Free of bumps and damage?
7 Pile driving increments marked on
8
9
* Tick box as appropriate
The non-conformances found during the inspections have been remedied.
* Further checks to be stipulated by inspector.
Non-
conformances
Non-conformances

Description Date remedied?

yes no
1
2
3
4

Date: Date Date: Date: