You are on page 1of 22

INSPECTION AND TEST PLAN - PIPING WORK

CUSTOMER : OPTIMAL CONTROLLED COPY NO


PROJECT : 10" TAILGAS LINE
BY : DIALOG HOLDINGS SDN BHD

ITEM PROCESS QC SPEC /


NO DESCRIPTION ACTIVITY ACCEPTANCE CRITERIA

1 Material Control
1.1 Receipt Inspection - Check material against purchasing docs Project Proc. DH/KCTF/QC/MC.02
- Check Material Certificates DIN 50049.3.1.B
- Visual Inspection of material to ensure Relevant ASTM spec. for pipe and fittings.
conformity to relevant specification
1.2 Storage of Material - Ensure all material adequately protected N/A

1.3 Handling of materials - Ensure all material carefully handled N/A

1.4 Rectification of Nonconforming Items - Determine disposition of nonconforming Control Procedure DHSB/CP/4.14
material and follow-up corrective action

2 Welding Procedures
2.1 Qualification of WPS - Submit WPS for Approval ASME 9

3 Welder Qualification
3.1 Qualification of Welders - Perform Welder Qualification Test ASME 9
- Visual Inspection ASME 9
- Non-destructive Testing ASME 9
- Issue ID Tag N/A

1 of 22
INSPECTION AND TEST PLAN - PIPING WORK
CUSTOMER : OPTIMAL CONTROLLED COPY NO
PROJECT : 10" TAILGAS LINE
BY : DIALOG HOLDINGS SDN BHD

ITEM PROCESS QC SPEC /


NO DESCRIPTION ACTIVITY ACCEPTANCE CRITERIA

4 Piping Fabrication
4.1 Marking / cutting / edge prep. - Visual Inspection AFC Isometric drawing /
ASME B31.3 Fig. 328.4.4
4.2 Fit-up - Fit-up Inspection WPS / ASME B31.3 Fig. 328.4.5
- Check location of branch connections AFC Isometric drawing
- Check weldolet / elbolet penetrations Cut holes must be at 90º and dressed

4.3 Tacking - Visual Inspection WPS


- Check correct consumeable WPS

4.4 Hi-Low transitions - Check with welding gauge ASME B31.3 Fig 324.8 / WPS

5 Production welding
5.1 Welding Execution - Amps, weave width WPS

- Check correct consumeable WPS

6 Control of Welding Consumables

2 of 22
INSPECTION AND TEST PLAN - PIPING WORK
CUSTOMER : OPTIMAL CONTROLLED COPY NO
PROJECT : 10" TAILGAS LINE
BY : DIALOG HOLDINGS SDN BHD

ITEM PROCESS QC SPEC /


NO DESCRIPTION ACTIVITY ACCEPTANCE CRITERIA

6.1 Receipt - Check manufacturer's certificate Project Proc. DH/KCTF/QC/MC.01

6.2 Storage - Ensure stored dry and sealed Project Proc. DH/KCTF/QC/MC.01

6.3 Baking - Bake and hold electrodes in Project Proc. DH/KCTF/QC/MC.01


accordance with manufacturer's rec.

6.4 Issuing - Record weight and type of electrodes Project Proc. DH/KCTF/QC/MC.01
issued

7 Inspection of Completed Welding


7.1 Visual - Visual Inspection ASME B31.3 - 1996

7.2 Dimensional - Dimensional Inspection AFC Isometric drawing

8 Non destructive testing


8.1 Radiography - Request RT % marked on AFC Isometric drawing
- Interpret radiographs ASME B31.3 Table 341.3.2.a and 354.3.2b

3 of 22
INSPECTION AND TEST PLAN - PIPING WORK
CUSTOMER : OPTIMAL CONTROLLED COPY NO
PROJECT : 10" TAILGAS LINE
BY : DIALOG HOLDINGS SDN BHD

ITEM PROCESS QC SPEC /


NO DESCRIPTION ACTIVITY ACCEPTANCE CRITERIA

8.2 Magnetic Particle Examination - Evaluate Weld Quality ASME B31.3 Table 341.3.2.a and 354.3.2b

9 Welding Repairs
- Review NDT report ASME B31.3 para 328.6
- Perform repair WPS

10 Hydrostatic testing
10.1 Prior to Hydrotest - Prepare Hydrotest Packages Project Procedure DH/KCTF/QC/MW.13 (a, b)
- Review NDT and Inspection Docs N/A
- Perform Line Walk and check against ISO N/A

10.2 Hydrotest Equipment - Check rating of temporary blinds Same pressure rating as permanet material
- Check calibration of gauges and recorder Project Procedure DH/KCTF/QC/MW.13 (a, b)

10.3 During Testing - Check test pressure Apply pressure as required by P&ID Dwg
- Hold for 1 hour Project Procedure DH/KCTF/QC/MW.13 (a, b)
- Visual Inspection for leaks Project Procedure DH/KCTF/QC/MW.13 (a, b)

10.4 Reinstatement - Check that gaskets are replaced Isometric Dwg and P&ID
- Check condition of bolting Bolting is to be in new condition
- Check in-line instument etc are replaced Isometric Dwg and P&ID

4 of 22
INSPECTION AND TEST PLAN - PIPING WORK
CUSTOMER : OPTIMAL CONTROLLED COPY NO
PROJECT : 10" TAILGAS LINE
BY : DIALOG HOLDINGS SDN BHD

ITEM PROCESS QC SPEC /


NO DESCRIPTION ACTIVITY ACCEPTANCE CRITERIA

11 Flushing / drying - Visual Inspection Piping is to be air dried and free from water
( on specific lines only )

12 Documentation - Review all Quality Records and compile N/A


QC Catalogue.

Prepared By : Tim Swift

Approved By : Chan Fok Kyong

5 of 22
WORK DOC. NO. : DH/TAILGAS/QC/MW.02 REV : 0
OLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
VERIFYING RESPONSIBILITY INSP. STATUS REMARK
RECORD
DHSB OPTIMAL DHSB OPTIMAL

Delivery Note N/A QC Inspector W M Acceptance of material to be stamped


Material Receiving Inspection Report QC Inspector W M on Delivery Note.
Material Receiving Inspection Report QC Inspector W M

N/A Supervisor Mat. Controller W M

N/A Supervisor Mat. Controller W M

Supplier Corrective Action Request QA/QC Mngr - M Identify Nonconforming Material by


segregation or colour coding.

Welding Procedure Specification QC Mngr. QC Mngr. W AP


Procedure Qualification Record (PQR)

Welder Qualification Test Record QC Inspector QC Inspector W AP


Welder Qualification Test Record QC Inspector QC Inspector W AP
RT Report QC Inspector QC Inspector W AP
ID Tag QC Inspector QC Inspector W AP

6 of 22
WORK DOC. NO. : DH/TAILGAS/QC/MW.02 REV : 0
OLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
VERIFYING RESPONSIBILITY INSP. STATUS REMARK
RECORD
DHSB OPTIMAL DHSB OPTIMAL

N/A Supervisor QC Inspector w M

N/A QC Inspector QC Inspector W M


As Built Dwg QC Inspector QC Inspector W M
N/A QC Inspector QC Inspector W M

N/A QC Inspector QC Inspector M M


N/A QC Inspector QC Inspector M M

N/A QC Inspector QC Inspector M M Fitter to check all transitions.

N/A Welder / QC Inspector M M


QC Inspector
N/A Welder / QC Inspector M M
QC Inspector

7 of 22
WORK DOC. NO. : DH/TAILGAS/QC/MW.02 REV : 0
OLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
VERIFYING RESPONSIBILITY INSP. STATUS REMARK
RECORD
DHSB OPTIMAL DHSB OPTIMAL
Retain all manufacturer's certificates Storeman QC Inspector W M

N/A Storeman QC Inspector W M

Baking Log Storeman QC Inspector W M

Consumable Issue Register Storeman QC Inspector W M

Visual Inspection Report QC Inspector / QC Inspector W M


Supervisor
As Built Drawing Supervisor / QC Inspector W M
QC Inspector

NDT Request QC Inspector QC Inspector W M


RT Report - QC Inspector - M Interpretation by NDT Company

8 of 22
WORK DOC. NO. : DH/TAILGAS/QC/MW.02 REV : 0
OLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
VERIFYING RESPONSIBILITY INSP. STATUS REMARK
RECORD
DHSB OPTIMAL DHSB OPTIMAL
MT Report QC Inspector QC Inspector W M

RT Report QC Inspector QC Inspector W M Re-number weld as repair (eg R1, R2)


Visual Inspection Report QC Inspector QC Inspector W RD Repeat Inspection as above.

Test Packages QC Inspector QC Inspector W AP


Test Packages QC Inspector QC Inspector W H
Punchlists QC Inspector QC Inspector W AP

Hydrotest Checklist Supervisor QC Inspector W M


Calibration Certificates QC Inspector QC Inspector W R

Hydrotest Report QC Inspector QC Inspector W W


Hydrotest Report QC Inspector QC Inspector W W
Hydrotest Report QC Inspector QC Inspector W W

Reinstatement Report QC Inspector QC Inspector W M


Reinstatement Report QC Inspector QC Inspector W M
Reinstatement Report QC Inspector QC Inspector W M

9 of 22
WORK DOC. NO. : DH/TAILGAS/QC/MW.02 REV : 0
OLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
VERIFYING RESPONSIBILITY INSP. STATUS REMARK
RECORD
DHSB OPTIMAL DHSB OPTIMAL

Flushing / Drying Report Supervisor QC Inspector W W Only required where indicated on dwg.

QC Catalogue QC Inspector QC Inspector W H

10 of 22
INSPECTION AND TEST PLAN - PIPING WORK (SHOP)
CLIENT : PC METHANOL SDN. BHD PLANT 1 CONTROLLED COPY
PROJECT : TO SUPPLY & CONSTRUCT FIREWATER SYSTEM
BY : WELFIELD SERVICES SDN BHD

ITEM
PROCESS DESCRIPTION QC ACTIVITY SPECIFICATION / ACCEPTANCE CRITERIA
NO

1 Drawing Control
1.1 Marking of weld nos on Isometric dwgs - Prepare AFC N/A
1.2 Workshop Receipt of Dwgs from PCMSB - Review against Drawing Masterlist N/A

2 Material Control
2.1 Receipt Inspection - Check material against purchasing docs
- Check Material Certificates DIN 50049.3.1.B
- Visual Inspection of material to ensure Relevant ASTM spec. for pipe and fittings.
conformity to relevant specification
2.2 Storage of Material - Ensure all material adequately protected N/A
2.3 Handling of materials - Ensure all material carefully handled N/A
2.4 Rectification of Nonconforming items - Determine disposition of nonconforming
material and follow-up corrective action

3 Welding Procedures
3.1 Qualification of WPS - Submit WPS for Approval ASME -IX

4 Welder Qualification
4.1 Qualification of Welders - Perform Welder Qualification Test ASME -IX

11 of 22
INSPECTION AND TEST PLAN - PIPING WORK (SHOP)
CLIENT : PC METHANOL SDN. BHD PLANT 1 CONTROLLED COPY
PROJECT : TO SUPPLY & CONSTRUCT FIREWATER SYSTEM
BY : WELFIELD SERVICES SDN BHD

ITEM
PROCESS DESCRIPTION QC ACTIVITY SPECIFICATION / ACCEPTANCE CRITERIA
NO

- Visual Inspection ASME -IX


- Non-destructive Testing ASME -IX
- Issue welder certificates ASME -IX

5 Piping Fabrication
5.1 Marking / cutting / edge prep. - Visual Inspection AFC Isometric drawing /
ASME B31.3 Fig. 328.4.4
5.2 Fit-up - Fit-up Inspection WPS / ASME B31.3 Fig. 328.4.5
- Check location of branch connections AFC Isometric drawing
- Check weldolet / elbolet penetrations Cut holes must be at 90º and dressed

5.3 Tacking - Visual Inspection WPS


- Check correct consumeable WPS

5.4 Hi-Low transitions - Check with welding gauge ASME B31.3 Fig 324.8 / WPS

6 Production welding
6.1 Welding Execution - Amps, weave width WPS

- Check correct consumeable WPS

12 of 22
INSPECTION AND TEST PLAN - PIPING WORK (SHOP)
CLIENT : PC METHANOL SDN. BHD PLANT 1 CONTROLLED COPY
PROJECT : TO SUPPLY & CONSTRUCT FIREWATER SYSTEM
BY : WELFIELD SERVICES SDN BHD

ITEM
PROCESS DESCRIPTION QC ACTIVITY SPECIFICATION / ACCEPTANCE CRITERIA
NO

13 of 22
INSPECTION AND TEST PLAN - PIPING WORK (SHOP)
CLIENT : PC METHANOL SDN. BHD PLANT 1 CONTROLLED COPY
PROJECT : TO SUPPLY & CONSTRUCT FIREWATER SYSTEM
BY : WELFIELD SERVICES SDN BHD

ITEM
PROCESS DESCRIPTION QC ACTIVITY SPECIFICATION / ACCEPTANCE CRITERIA
NO

7 Control of Welding Consumables


7.1 Receipt - Check manufacturer's certificate

7.2 Storage - Ensure stored dry and sealed

7.3 Baking/Holding - Bake and hold electrodes in


accordance with manufacturer's rec.

7.4 Issuing - Record weight and type of electrodes


issued

8 Inspection of Completed Welding


8.1 Visual - Visual Inspection ASME B31.3
8.2 Dimensional - Dimensional Inspection AFC Isometric drawing

9 Non destructive testing


9.1 Radiography N/A N/A
9.2 Dye-Penetration Testing - Evaluate Weld Quality ASME B31.3
9.3 Magnetic Particle Examination N/A ASME B31.3

14 of 22
INSPECTION AND TEST PLAN - PIPING WORK (SHOP)
CLIENT : PC METHANOL SDN. BHD PLANT 1 CONTROLLED COPY
PROJECT : TO SUPPLY & CONSTRUCT FIREWATER SYSTEM
BY : WELFIELD SERVICES SDN BHD

ITEM
PROCESS DESCRIPTION QC ACTIVITY SPECIFICATION / ACCEPTANCE CRITERIA
NO

10 Welding Repairs
- Review NDT report ASME B31.3
- Perform repair WPS

11 Hydrostatic testing
11.1 Prior to Hydrotest - Prepare Hydrotest Packages
- Review NDT and Inspection Report N/A
- Perform Line Walk and check against ISO N/A

11.2 Hydrotest Equipment - Check rating of temporary blinds Same pressure rating as permanet material
- Check calibration of pressure gauges
and recorder
11.3 During Testing - Check test pressure Apply pressure as required by P&ID Dwg
- Hold for 1 hour
- Visual Inspection of leaks

11.4 Reinstatement - Check that gaskets are replaced Isometric Dwg and P&ID
- Check condition of bolting Bolting is to be in new condition
- Check in-line instument etc are replaced Isometric Dwg and P&ID

15 of 22
INSPECTION AND TEST PLAN - PIPING WORK (SHOP)
CLIENT : PC METHANOL SDN. BHD PLANT 1 CONTROLLED COPY
PROJECT : TO SUPPLY & CONSTRUCT FIREWATER SYSTEM
BY : WELFIELD SERVICES SDN BHD

ITEM
PROCESS DESCRIPTION QC ACTIVITY SPECIFICATION / ACCEPTANCE CRITERIA
NO

12 Flushing / drying - Visual Inspection Piping is to be air dried and free from water
( on specific lines only )

13 Documentation - Review all Quality Records and compile N/A


QC Catalogue.

Prepared By : Approved By:

Name : Name :

Date : Date :

Signature : Signature :

16 of 22
DOC. NO. : WSSB/PML/ITP/01/2012 REV : 0
ROLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
RESPONSIBILITY INSP. STATUS REMARK
VERIFYING RECORD
WSSB PCMSB WSSB PCMSB

Approved Isometrics Dwgs QC Inspector QC Inspector R/AP R/AP


Transmittals Supervisor QC Dept. R R

Delivery Note Mat. Controller QC Inspector W M Acceptance of material to be stamped


Material Receiving Inspection Report Mat. Controller QC Inspector W M on Delivery Note.
Material Receiving Inspection Report Mat. Controller QC Inspector W M

N/A Supervisor Mat. Controller W M


N/A Supervisor Mat. Controller W M
Supplier Corrective Action Request QA/QC Mngr./ - W M Identify Nonconforming Material by
QC Inspector segregation or colour coding.

Welding Procedure Specification QC Mngr. QC Mngr. W AP


Procedure Qualification Record (PQR)

Welder Qualification Test Record QC Inspector QC Inspector W W

17 of 22
DOC. NO. : WSSB/PML/ITP/01/2012 REV : 0
ROLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
RESPONSIBILITY INSP. STATUS REMARK
VERIFYING RECORD
WSSB PCMSB WSSB PCMSB

Welder Qualification Test Record QC Inspector QC Inspector W AP


RT Report QC Inspector QC Inspector W AP
Welder Certificates QC Inspector QC Inspector W AP

N/A Supervisor QC Inspector W M

N/A QC Inspector QC Inspector W M


As Built Dwg QC Inspector QC Inspector W M
N/A QC Inspector QC Inspector W M

N/A QC Inspector QC Inspector M M


N/A QC Inspector QC Inspector M M

N/A QC Inspector QC Inspector M M Fitter to check all transitions.

N/A Welder / QC Inspector M M


QC Inspector
N/A Welder / QC Inspector M M

18 of 22
DOC. NO. : WSSB/PML/ITP/01/2012 REV : 0
ROLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
RESPONSIBILITY INSP. STATUS REMARK
VERIFYING RECORD
WSSB PCMSB WSSB PCMSB

QC Inspector

19 of 22
DOC. NO. : WSSB/PML/ITP/01/2012 REV : 0
ROLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
RESPONSIBILITY INSP. STATUS REMARK
VERIFYING RECORD
WSSB PCMSB WSSB PCMSB

Retain all manufacturer's certificates Storeman QC Inspector W M

N/A Storeman QC Inspector W M

Baking Log Storeman QC Inspector W M

Consumable Issue Register Storeman QC Inspector W M

Visual Inspection Report QC Inspector QC Inspector W RD


As Built Drawing QC Inspector QC Inspector W RD

N/A
DPT Report QC Inspector QC Inspector W W Interpretation by NDT Company
MT Report QC Inspector QC Inspector W W

20 of 22
DOC. NO. : WSSB/PML/ITP/01/2012 REV : 0
ROLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
RESPONSIBILITY INSP. STATUS REMARK
VERIFYING RECORD
WSSB PCMSB WSSB PCMSB

NDT Report QC Inspector QC Inspector W M Re-number weld as repair (eg R1, R2)
Visual Inspection Report QC Inspector QC Inspector W RD Repeat Inspection as above.

Test Packages QC Inspector QC Inspector R/AP R


N/A QC Inspector QC Inspector R/AP R
Punchlists QC Inspector QC Inspector W W

Hydrotest Checklist Supervisor QC Inspector W M


Calibration Certificates QC Inspector QC Inspector R R

Hydrotest Report QC Inspector QC Inspector W W


Hydrotest Report QC Inspector QC Inspector W W
Hydrotest Report QC Inspector QC Inspector W W

Reinstatement Report QC Inspector QC Inspector W M


Reinstatement Report QC Inspector QC Inspector W M
Reinstatement Report QC Inspector QC Inspector W M

21 of 22
DOC. NO. : WSSB/PML/ITP/01/2012 REV : 0
ROLLED COPY NO. : ABBREVIATIONS
M = MONITOR W = WITNESS
R = REVIEW AP = APPROVAL
RD = RANDOM H = HOLD
RESPONSIBILITY INSP. STATUS REMARK
VERIFYING RECORD
WSSB PCMSB WSSB PCMSB

Flushing / Drying Report Supervisor QC Inspector W W Only required where indicated on dwg.

QC Document QC Inspector QC Inspector R/AP H

Appraised By (PCMSB):

Name :

Date :

Signature :

22 of 22

You might also like