KONSTRUKSI
Revision Status
Rev Issue Date Prepared Checked Approved Issue Purpose Owner Signature
INSPECTION TEST PLAN
PENSTOCK PIPE FABRICATION AND INSTALATION
Doc. No. : 01/ITP/ACST-ITK/22
2 MATERIAL
2.2 Material Inspection & Verification Material Specification; Material Receiving Report
3 FABRICATION
3.1 Marking and cutting AFC Drawing Cutting Report
5 NDT
6 Pressure Testing
7 PAINTING
8 HANDOVER
8.3 Final Inspection prior delivery/ shipment Handover System & Certification IRN
Manual
INSPECTION TEST PLAN PENSTOCK PIPE INSTALAT
Doc. No. : 02/ITP/ACST-ITK/22
1 DOCUMENT REVIEW
2 INSTALLATION PROCESS
3.1 Joint Inspection AFC Drawing Joint Integrity Certificate (JI1) AFC Drawing
Installation Procedure
4 PAINTING
5 HANDOVER
6.1 NCR (Non Conformance Report) Non Conformance Procedure NCR NCR Close
6.2 Handover Process Repair Record Document Repair Dosier Approved Repa
Procedure
o : 01/ITP/ACT-ITK/22
PENSTOCK
Signature
Owner Signature
Legend :
ST PLAN M : Monitor P : Perform
ON AND INSTALATION A : Approve R : Review
ST-ITK/22 W : Witness H : Hold Point
Acceptance Criteria
ITK QA/QC ACSET
Legend :
ST PLAN M : Monitor P : Perform
ON AND INSTALATION A : Approve R : Review
ST-ITK/22 W : Witness H : Hold Point
Acceptance Criteria
ITK QA/QC ACSET
Data Sheet; P R
Drawing;
ASTM Material.
ASME B31.3 Par-323.1 P W
AFC Drawing, P M
AFC Drawing, P M
ASME B31.3 Par.332.1
Approved WPS; P M
ASME B31.3,Par.328.4
Approved WPS; P M
ASME Sec IX, Artikel-3
Legend :
ST PLAN M : Monitor P : Perform
ON AND INSTALATION A : Approve R : Review
ST-ITK/22 W : Witness H : Hold Point
Acceptance Criteria
ITK QA/QC ACSET
Level Inspection
Approved Procedure P R R R
Approved Procedure P R R R
ASME B 31.3
AFC Drawing P R R R
Erection Drawing P W - -
Installation Procedures
AFC Drawing P W R -
ASME Sec. VIII
AFC Drawing P W W W
Drawing/Installation Procedures P W W W
Legend :
TOCK PIPE INSTALATION M : Monitor P : Perform
ST-ITK/22 A : Approve R : Review
W : Witness H : Hold Point
Level Inspection
NCR Close P A R R