PROJECT INFORMATION
RESPONSIBILITY
CONTROL DOCUMENTS /
ITEM ACTIVITY DESCRIPTION ACCEPTANCE CRITERIA VERIFYING DOCUMENT
DERMAGA
VENDOR
PROCEDURES
HHA /
SUB
1.0 PRELIMINARY
ASME B31.3
ASME B16.5
INSPECTION TEST PLAN
ASME B36.10M
ASME B31.3
ASME B16.5
2.3 Welding Documentation Approval WPS ASME B31.3 Approved WPS X - R,A
WPQ
2.4 NDE Procedures Approval RT procedure ASME B31.3 Approved NDE Procedures X - R,A
2.5 Hydrostatic Test Procedure Approval HT Test Procedure HT Test Procedure Approved Hydrostatic X - R,A
INSPECTION TEST PLAN
ASME B31.3
2.6 Painting Procedure Approval Surface Preparation & Painting PTS 15.20.03 Approved Surface X - R,A
Procedure Preparation & Painting
Procedures
2.7 Positive Material Identification Procedure PMI Procedure ASME B31.3 Approved PMI Procedure X - R,A
3.1 Material Receiving Inspection Bill of Material (BOM) Applicable Material Standard Mill certificate X - R
3.2 Positive Material Identification Test PMI Procedure ASME B31.3 PMI Report R X R
3.3 Machining of Cone Element Approved GA Drawing ISO 5167-5 Material Certificate X - -
BS EN 10204 3.1
INSPECTION TEST PLAN
3.4 Dimensional Inspection of Cone Element Detail AFC Drawings Detail AFC Drawings Dimensional Report X - R
ISO 5167-5
3.6 Welding of Cone Element to Meter Body WPS WPS Fit up Report R X R
3.7 Welding of Pressure Tap to Meter Body WPS WPS Fit up Report R X R
3.8 Dye Penetrant Test of Welded Joints Dye Penetrant Test Procedure ASME B31.3 DPT Report R X R
3.9 Magnetic Particle Test Magnetic Particle Test Procedure ASME B31.3 MPT Report R X R
3.10 Radiographic Testing 100% Butt Weld Joint Radiographic Testing Procedure ASME B31.3 RT Report R X R
3.11 Ferrite Test On Duplex SS Material Ferrite Test Procedure ASME B31.3 FT Report R X R
3.11 Assembly Dimensional Control (As Built) GA Drawing GA Drawing Dimensional Report X R
3.12 Hydrostatic Test Hydrostatic Test Procedure ASME B31.3 Hydrostatic Test Report W,R X W,R
4.1 Surface Preparation & Painting – Cone Surface Preparation and Painting PTS 15.20.03 Painting Report R X R
Meter Procedure
5.1 Water Calibration – Discharge Coefficient Calibration Procedure ISO 5167 – 5 Calibration Report W,R X W,R
Determination
6.0 LOGISTICS
6.1 Final Visual and Dimensional Inspection Purchase Order Purchased Order Inspection Release X - H
Certificate (IRC)
Document Review GA Drawing GA Drawing
Datasheet Datasheet
6.2 Preservation and Packaging Packing Procedure Purchased Order Packing List R X R
INSPECTION TEST PLAN
INTERVENTION POINTS
X (RESPONSIBLE)
100% responsibility to ensure the activity or task been performed accordingly as per approved ITP.
R (REVIEW)
A (APPROVED)
W (WITNESS)
The related parties are required notification of the inspection timing. However, the inspection shall be performed as scheduled and if they are not present, the activity can be performed.
Permission to performed in written is required.
H (HOLD POINT)
The contractor shall not proceed to the next activity without clearance of a hold point by related parties in written.