You are on page 1of 22

INSPECTION & TEST PLAN

INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 3 0f 6
Item Name : Blow Down Tank
Item No. : N.A
Verified Acceptance Inspection
No. Work Flow Quality Activities Reference Document
Document Criteria BRT DKME PKG Disnaker
1 FABRICATION DOCUMENT
Inspection and Test Plan Prepare and review ITP Related drawing N.a ASME, Customer Spec. P R R R
WPS and PQR Prepare and review WPS / PQR ASME Section II & IX N.a ASME Section IX P R R R

2 INCOMING MATERIAL ( Plates, pipe, flange, bolts, consumable, etc. )


Receiving Material Receiving material inspection Mill certificate Report ASME Section II H W/R W/R W/R

3 HEAD
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -
Dishing Observation with template Related drawing N.a ASME Section VIII Div. 1 H - - -
Flanging Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting & Bevelling Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Observation with template Related drawing Report ASME Section VIII Div. 1 H R R R

4 SHELL
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -
Pre - Bending Dimensional inspection Related drawing N.a ASME Section VIII Div. 1 H - - -
Rolling Dimensional inspection Related drawing N.a ASME Section VIII Div. 1 H - - -
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
Re - Rolling Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
NDE RT spot RT procedure Report ASME Section VIII Div. 1 H R R R

5 JOINT HEAD TO SHELL


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE RT spot RT procedure Report ASME Section VIII Div. 1 H R R R
INSPECTION & TEST PLAN
INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 2 of 6

Explanation
Penjelasan

W Witness / Witness the operation or examination purchaser's inspection must be present during the specified activity
H Hold Saksi pengujian operasi atau pengujian dimana inspeksi pembeli harus ada selama aktivitas khusus

(w) Witness Random Witness random specified test/examination where the inspector must be notified in advance and may be
present during specified activity.
Saksi untuk tes khusus /pengujian dimana inspektor harus mencatat kemajuannya dan bisa ada/tidak ada selama
aktivitas khusus.

R Review The authority will review any documents, comparing the recorder data with the specified acceptance criteria
Document Petugas yang berwenang akan mengkaji ulang setiap dokumen, membandingkan data yang direcord (dicatat)
dengan kriteria penerimaan yang dispesifikasikan.

M Manufacturer's Vendor and / or subvendor's inspection implementation

W/R When Required When Required


Bila diperlukan

P Document Preparation Fabrication / Engineering / QA / QC Document shall be prepared, reviewed or approved.

NOTE : "Witness" point is the same as a "Hold" point

INSPECTION: BRT PT. BARATA INDONESIA (PERSERO)


DKME DAEKYUNG MACHINERY & ENGINNERING CO.LTD
PKG PT. PETROKIMIA - GRESIK
Disnaker DINAS TENAGA KERJA - GRESIK
INSPECTION & TEST PLAN
INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 4 0f 6
Item Name : Blow Down Tank
Item No. : N.A
Verified Acceptance Inspection
No. Work Flow Quality Activities Reference Document
Document Criteria BRT DKME PKG Disnaker
6 CLOSING HEAD TO SHELL
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE RT spot RT procedure Report ASME Section VIII Div. 1 H R R R

7 JOINT NECK TO FLANGE ( M1, N1, N2, N3, N4, N5a, N5b, N6 & N7)
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
8 JOINT NECK TO SHELL ( M1, N1, N2, N3, N4, N5a & N5b )
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

9 JOINT NECK TO HEAD ( N6 & N7 )


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

10 LIFTING LUGS
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -

11 EARTH LUGS
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -
INSPECTION & TEST PLAN
INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 5 0f 6
Item Name : Blow Down Tank
Item No. : N.A
Verified Acceptance Inspection
No. Work Flow Quality Activities Reference Document
Document Criteria BRT DKME PKG Disnaker
12 LEGS
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -

13 BASE PLATE
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -

14 INSULATION RING
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -
Pre - Bending Dimensional inspection Related drawing N.a ASME Section VIII Div. 1 H - - -
Rolling Dimensional inspection Related drawing N.a ASME Section VIII Div. 1 H - - -

15 JOINT INSULATION RING TO SHELL


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

16 JOINT LIFTING LUGS TO HEAD


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

17 JOINT BASE PLATE & EARTH LUGS TO LEGS


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R
INSPECTION & TEST PLAN
INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 6 0f 6
Item Name : Blow Down Tank
Item No. : N.A
Verified Acceptance Inspection
No. Work Flow Quality Activities Reference Document
Document Criteria BRT DKME PKG Disnaker
18 JOINT LEGS TO SHELL
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

19 FINAL INSPECTION
Final Inspection Final dimensional inspection Related drawing Report ASME Section VIII Div. 1 H W W W
Visual test Visual procedure Report ASME Section VIII Div. 1 H (w) (w) (w)

20 HYDROSTATIC TEST
Leak Test Leak test inspection Leak test procedure Report ASME Section VIII Div. 1 H R R R
Hydrostatic Test Hydrostatic test inspection Hydrostatic procedure Report ASME Section VIII Div. 1 H W W W

21 PAINTING
Sandblast Surface check after sandblast Painting spec. N.a Technical Spec. H - - -
Painting Painting inspection Painting spec. Report Dry Film Thickness H (w) (w) (w)

22 MDR
MDR Manufacturer's data report Customer requirement Report Technical Spec. H R R R
Disnaker
Disnaker
Disnaker
Disnaker
PT. BARATA INDONESIA
JL. Veteran 241 Gresik - 61123 - Indonesia
Phone : (031) 3990555 Ext. 506 ; Fax : (031) 3990666

QA - QC DOCUMENT

Pemesan
: PT. PETROKIMIA GRESIK
Customer No. Dokumen
: 02.1-5
Proyek Document No.
: FUNNED TUBE & BEND
Project Lembar
: Cover
No. Order Sheet
:
Order No.

Judul
Title

LIST WELDERS QUALIFICATION


AND
WELDERS SERTIFICATE
Signature

Signature

Signature
Tangan

Tangan

Tangan
Tanda

Tanda

Tanda

0 24/4/2013
Nama : Nama : Nama :
Name : Name : Name :
Revision

Maryudi Djohan Nyoman W.K.


Revisi

Tanggal Uraian
Date Description
Disiapkan Dikaji ulang Disetujui
Prepared Reviewed Approved
INSPECTION & TEST PLAN
INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 3 0f 6
Item Name : Flash Tank
Item No. : N.A
Verified Acceptance Inspection
No. Work Flow Quality Activities Reference Document
Document Criteria BRT DKME PKG Disnaker
1 FABRICATION DOCUMENT
Inspection and Test Plan Prepare and review ITP Related drawing N.a ASME, Customer Spec. P R R R
WPS and PQR Prepare and review WPS / PQR ASME Section II & IX N.a ASME Section IX P R R R

2 INCOMING MATERIAL ( Plates, flange, consumable, etc. )


Receiving Material Receiving material inspection Mill certificate Report ASME Section II H W/R W/R W/R

3 HEAD
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -
Dishing Observation with template Related drawing N.a ASME Section VIII Div. 1 H - - -
Flanging Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting & Bevelling Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Observation with template Related drawing Report ASME Section VIII Div. 1 H R R R

4 SHELL
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -
Pre - Bending Dimensional inspection Related drawing N.a ASME Section VIII Div. 1 H - - -
Rolling Dimensional inspection Related drawing N.a ASME Section VIII Div. 1 H - - -
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
Re - Rolling Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
NDE RT spot RT procedure Report ASME Section VIII Div. 1 H R R R

5 JOINT HEAD TO SHELL


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE RT spot RT procedure Report ASME Section VIII Div. 1 H R R R
INSPECTION & TEST PLAN
INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 2 of 6

Explanation
Penjelasan

W Witness / Witness the operation or examination purchaser's inspection must be present during the specified activity
H Hold Saksi pengujian operasi atau pengujian dimana inspeksi pembeli harus ada selama aktivitas khusus

(w) Witness Random Witness random specified test/examination where the inspector must be notified in advance and may be
present during specified activity.
Saksi untuk tes khusus /pengujian dimana inspektor harus mencatat kemajuannya dan bisa ada/tidak ada selama
aktivitas khusus.

R Review The authority will review any documents, comparing the recorder data with the specified acceptance criteria
Document Petugas yang berwenang akan mengkaji ulang setiap dokumen, membandingkan data yang direcord (dicatat)
dengan kriteria penerimaan yang dispesifikasikan.

M Manufacturer's Vendor and / or subvendor's inspection implementation

W/R When Required When Required


Bila diperlukan

P Document Preparation Fabrication / Engineering / QA / QC Document shall be prepared, reviewed or approved.

NOTE : "Witness" point is the same as a "Hold" point

INSPECTION: BRT PT. BARATA INDONESIA (PERSERO)


DKME DAEKYUNG MACHINERY & ENGINNERING CO.LTD
PKG PT. PETROKIMIA - GRESIK
Disnaker DINAS TENAGA KERJA - GRESIK
INSPECTION & TEST PLAN
INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 4 0f 6
Item Name : Flash Tank
Item No. : N.A
Verified Acceptance Inspection
No. Work Flow Quality Activities Reference Document
Document Criteria BRT DKME PKG Disnaker
6 CLOSING HEAD TO SHELL
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE RT spot RT procedure Report ASME Section VIII Div. 1 H R R R

7 JOINT NECK TO FLANGE ( M1, N1, N2, N3, N4, N5a, N5b, N6a, N6b, N7 & N8 )
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
8 JOINT NECK TO SHELL ( M1, N1, N5a, N5b, N6a, N6b & N7 )
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

9 JOINT NECK TO HEAD ( N2, N3, N4 & N8 )


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

10 LIFTING LUGS
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -

11 EARTH LUGS
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -
INSPECTION & TEST PLAN
INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 5 0f 6
Item Name : Flash Tank
Item No. : N.A
Verified Acceptance Inspection
No. Work Flow Quality Activities Reference Document
Document Criteria BRT DKME PKG Disnaker
12 LEGS
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -

13 BASE PLATE
Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Cutting Dimensional inspection Related cutting plan N.a ASME Section VIII Div. 1 H - - -

14 JOINT LIFTING LUGS TO HEAD


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

15 JOINT BASE PLATE & EARTH LUGS TO LEGS


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

16 JOINT LEGS TO SHELL


Marking Marking & identification inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Fit up Dimensional inspection Related drawing Report ASME Section VIII Div. 1 H R R R
Welding Dimensional inspection Related drawing Report ASME Section IX H R R R
Visual inspection Visual procedure Report ASME Section VIII Div. 1 H R R R
NDE PT PT procedure Report ASME Section VIII Div. 1 H R R R

17 FINAL INSPECTION
Final Inspection Final dimensional inspection Related drawing Report ASME Section VIII Div. 1 H W W W
Visual test Visual procedure Report ASME Section VIII Div. 1 H (w) (w) (w)
INSPECTION & TEST PLAN
INDONESIA
PT. Barata Indonesia (Persero)
Doc. No. : 01 / ITP / QC - PIB / 7.06.003 Revisi No. : 0 Sheet : 6 0f 6
Item Name : Flash Tank
Item No. : N.A
Verified Acceptance Inspection
No. Work Flow Quality Activities Reference Document
Document Criteria BRT DKME PKG Disnaker
18 HYDROSTATIC TEST
Leak Test Leak test inspection Leak test procedure Report ASME Section VIII Div. 1 H R R R
Hydrostatic Test Hydrostatic test inspection Hydrostatic procedure Report ASME Section VIII Div. 1 H W W W

19 PAINTING
Sandblast Surface check after sandblast Painting spec. N.a Technical Spec. H - - -
Painting Painting inspection Painting spec. Report Dry Film Thickness H (w) (w) (w)

20 MDR
MDR Manufacturer's data report Customer requirement Report Technical Spec. H R R R
Disnaker
Disnaker
Disnaker
Disnaker
Procedure No : 02.1 - 6
Revision No :0
Date : 24 April 2013
PT. Barata Indonesia (Persero) Page :5
Heavy Construction Division

WPS AND PQR

IV. LIST OF WPS


Thk. Welding
No. WPS No. Material Qualified AWS No. SFA No. PWHT Impact Hardness Remarks
(mm) Process
1 XA. 1. 1N - 163 Rev. 1 All P no. 1 4.76 - 50 P1 to P1 SMAW E. 7018 A5.1 N.A N.A N.A

2 XC. 1. 1N - 19 Rev.1 All P no. 1 1.56 - 7.80 P1 to P1 GTAW ER70S-6 A5.18 N.A N.A N.A
GTAW & ER70S-6 A5.18
3 XCA. 1.1H-31 Rev.1 All P no. 1 4.76 - 50 P1 to P1 Yes N.A N.A
SMAW E7018 A5.1
E7018
SMAW & A5.1
4 XAB. 1. 1N - 37 Rev.1 All P no. 1 4.76 - 32 P1 to P1 F7A5EM N.A N.A N.A
SAW A5.1
12K
GTAW & ER70S-6 A5.18
5 XCA. 1. !N - 30 Rev.1 All P no. 1 4.76 - 50 P1 to P1 N.A N.A N.A
SMAW E7018 A5.1

QA/QC PROCEDURE - PT. BARATA INDONESIA - W3


QA/QC PROCEDURE - PT. BARATA INDONESIA - W3
LIST OF WELDERS QUALIFICATION
FOR BLOW DOWN TANK - STEAM BOILER PACKAGE B - 1102 PROJECT

Welder Result of Test


No. Welder Name Process Position / Class Certification By Remark
Stamp X - Ray
SMAW Kelas 1 ACC Disnaker
1 Suyono B.42
GTAW Kelas 1 ACC Disnaker
SMAW Kelas 1 ACC Disnaker
2 Paeman B.53
GTAW Kelas 1 ACC Disnaker
3 Choirul Anam B.150 GTAW Kelas 1 ACC Disnaker
4 Kastunggal B.151 GTAW Kelas 1 ACC Disnaker
5 Nanang. S B.155 GTAW Kelas 1 ACC Disnaker