You are on page 1of 63

MAHAWELI WATER SECURITY INVESTMENT PROGRAM (MWSIP)

CONSTRUCTION OF NORTH WESTERN PROVINcE GANAL PROJEcT (NWPCP)


CONSTRUCTION OF MAIN CANAL FROM NEBADAGAHAWATTA TO MAHAKITHULA RESERVOIR
INLET TUNNEL (FROM 5+250 KM TO 22+300 KM) - NWPCP - ICB-2
APPROVAL SHEET FOR DOCUMENTS PREPARED BY THE CONTRACTOR

Contract No.: MMD E/MWS I P/AD B/NWPC P/r C B-2l3267-3268-SRl/l C B/20 1 7/003

Name of Contractor: China State Construction Engineering Corporation Ltd.


Approval Sheet for the " Submittal of No.15 Method Statement for Ranwediyawa
Title of the Document:
Tunnel Construction"
Submittal of No.1 5 Method Statement
Drawing / Document No.: Revision: Rev. A
for Ranwediyawa Tunnel Construction

Received by Letter Ref.: C SC EC- I C 82-P M DSC-3 1 O -20 1 9 Dated: 21st June 2019

Previous Aoproval Status: Appr. Sheet No.


NWPCP-ICB2-AS-
Present Approval Status: AN Appr. Sheet No.
oth 0005
A= Approved
AN= Approved except as Noted
RR= Return for Correction and Resubmission

On your submission our comments are as follows.

1. A detailed review of ventilation calculations can be carried out between our respective Site Engineers
at site.
2. Working site lay outs are required. They may be submitted separately
3. Site proformas and lnspection and Test Plan will be reviewed on site between relevant PMDSC site
staff and China State Engineers when work proceeds. Adjustments to be agreed and made on site
4. lnformation in annexes 1,2 &3 to be included
5. Confirm that shotcrete/ concrete batching mixing will not be done at the portal site or if it is proposed
to produce at site portal area advise all relevant information on storage of materials operation of plant
and facilities for maintaining dusU noise free environment
6. Please confirm how equipment will be maintained at site and who will carry it out in absence of fitter/
mechanic on tunnel team?
7. H&S and Environmental sections of Method Statement may be subject to comment from PMDSC
relevant staff.
8. For requirements of working site set up area etc. please see comments on appropriate submission
(which has been rejected)
9. For portal layouts including access and surrounding surface features please see comments on
appropriate submission (which has currently been rejected for lack of detail).

The approval of drawings and documents shall not relieve the Contractor of any of his duties, obligations or
responsibilities under the Contract.
Checked by PMDSC

ilIal !P211
Resident Engineer Date
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Construction of Main Canal from Nebadagahawatta


To Mahakithula Reservoir Inlet Tunnel
(From 5+250km to 22+300).

METHOD STATEMENT FOR RANWEDIYAWA TUNNEL CONSTRUCTION

MS-015
Rev.A

Contractor: China State Construction Engineering Corp.

No Date Prepared Checked Approved Remark


REV.A 21/06/2019 H.M.Dissanayake Chen zhijun Li jianshuang

Ref.Letter No :
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Contents
1.0 Introduction ................................................................................................................................... 4
2.0 Purpose of the method statement ................................................................................................... 4
3.0 Work Force Allocation ................................................................................................................... 5
4.0 Documents to be referenced with this method statement .............................................................. 8
5.0 Detailed method of carrying out method statement activity.......................................................... 9
6.0 Temporary Access to Tunnel ......................................................................................................... 9
7.0 Equipment and Material .............................................................................................................. 10
7.1 Equipment ................................................................................................................................ 10
7.2 Material .................................................................................................................................... 11
8.0 Construction Method ................................................................................................................... 12
8.1 Blasting Design for Ranwediyawa Tunnel .............................................................................. 12
8.2 Drilling ..................................................................................................................................... 12
8.3 Blast holes arrangement for the drilling pattern ...................................................................... 13
8.4 Conceptual drilling geometry and firing sequences................................................................. 13
8.5 Top heading part of the tunnel ................................................................................................. 13
8.6 Lower part or the bench ........................................................................................................... 13
8.7 Charging ................................................................................................................................... 14
8.8 Charging method for Perimeter holes ...................................................................................... 15
8.9 Charging method for Production holes .................................................................................... 15
8.10 Approximate Blasting Parameters ........................................................................................... 16
8.11 Sample specific charge calculation .......................................................................................... 16
8.12 Mechanical Excavation – Using excavator/Backhoe Loader or Hammer ............................... 17
8.13 Forepoling ................................................................................................................................ 18
9.0 Mucking and Disposal of Excavated Materials ........................................................................... 21
10.0 Tunnel Support ............................................................................................................................ 22
10.1 Shotcrete and Wire Mesh ......................................................................................................... 25
10.2 Installation of Rock Bolt .......................................................................................................... 26
10.3 Lattice Girders and Steel Ribs ................................................................................................. 28
10.4 Tunnel Lining ........................................................................................................................... 33
11.0 Temporary Facilities for Tunnel Excavation ............................................................................... 34
11.1 Compressed Air Supply for Construction ................................................................................ 34
11.2 Water Supply for Construction ................................................................................................ 35
11.3 Electricity for Construction...................................................................................................... 35
11.4 Lighting .................................................................................................................................... 35
11.5 Ventilation ................................................................................................................................ 36
11.6 Drain ........................................................................................................................................ 39
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
11.7 Communication ........................................................................................................................ 40
12.0 Quality Control ............................................................................................................................ 41
12.1 Survey Works ........................................................................................................................... 41
12.2 Laboratory and Testing ............................................................................................................ 41
13.0 Working Programme .................................................................................................................... 42
14.0 QA/QC Measures ........................................................................................................................ 42
15.0 Inspection and Test Plan for Tunnel Construction ....................................................................... 43
16.0 Environmental Management Plan for Tunnel construction ......................................................... 43
16.1 Environmental Monitoring Plan .............................................................................................. 54
17.0 Safety Requirements for Tunnel Construction ............................................................................ 56
17.1 Safety Orientation Course and Employee Registration ........................................................... 56
17.2 Duty Oriented Safety Courses ................................................................................................. 56
17.3 General Safety Requirements .................................................................................................. 56
17.4 Safety Procedure ...................................................................................................................... 57

Annexure 1: Inspection and Test Plan


Annexure 2: System Formwork Panel Arrangement
Annexure 3: Details and Photos of Machineries
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
1.0 Introduction

In this project there are two tunnels namely Ranwediyawa tunnel and Nilagama tunnel.
Renwediyawa tunnel starts at Ch. 9+060km and ends at ch.9+680km. Nilagama tunnel starts at
ch.13+420km and ends at ch.14+240km.

This method statement is applicable to the Ranwediyawa tunnel construction works.

Figure 1: Site Layout

2.0 Purpose of the method statement

The main purpose of this method Statement is:

- To outline the works involved in this particular job.

- To provide a document that project staff must read and understand before starting the job.

- To meet specification requirements, that is, identification and control.

- To program work, materials, time, staff, and to anticipate possible problems;

- To use as a tool in quality assurance

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

3.0 Work Force Allocation

Figure2: Organization Chart for Tunnel Construction Activity

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
Fallowing manpower will be deployed for the tunnel construction work.

No. Position Quantity Duties and Responsibilities of Key positions


1 Tunnel Engineer 1 •Planning and controlling project schedule.
•Checking, analyzing and reporting the differences between
schedule and actual progress.
•Coordination to each section with respect to relevant
technical matters.
•Supervising the operation of document control system.
•Controlling the project's design documents and the change
of the design documents at site.
•Controlling for expediting the delivery of purchased
material and handling materials at site.
•Preparing of work procedures related to temporary
facilities such as lighting, water, ventilation..etc, blasting
and transport.
•Determination of tunnel advance rates and tunnel program
/ schedule including maintenance strategies
•Determination of required resources for tunnelling works,
including labour and equipment
•Support of Mechanical /Plant Manager with determining
choice of equipment and plant required for tunneling works
•Supervision of construction progress and cost controlling
•Preparation of target – actual comparison sheets
•Setup and preparation of all necessary documents related
to the construction process such as quantity recording,
construction diary etc.
•Preparation of monthly statements and maintaining of
work execution estimate
•Assignment and coordination of personnel, subcontractors
and consultants
•Planning of material and equipment
•Participation in construction discussions and meetings
2 Engineering Geologist 1 •Preparation of documentation
•Responsible for identifying the geological factors that
could affect tunnel construction
•All geological/geotechnical data recording (Geological
tunnel mapping)
•Analyze ground materials to assess their risk factors and
advise on the best procedures for developments and the
suitability of construction,
•Coordination with the Engineers on all
geological/geotechnical matters.
•Keep in touch with the engineering and design personnel’s
•Participation in construction discussions and meetings
•Preparation of all documents/report on
3 Mining Engineer 1 •Responsible for charging of explosives and arranging the
delay paten.
•Perform the blasting in a safe manner
•o-ordinate with the Engineer’s mining engineer
6

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
•co-ordinate with GSMB and any other third party
monitoring team
•Participation in tunnel construction meeting and
discussions
4 Material Engineer 1 •Conduct or supervise laboratory tests in order to ensure
material quality
•Analyses laboratory test results in order to determine
causes of problems and develop solutions.
•Design and direct the testing and/or control of processing
procedures.
•Monitor material performance and evaluate material
deterioration.
•Coordination with the Engineers on all QA/QC matters.
•Participation in construction discussions and meetings
5 QA/QC Engineer 1 •Initializing and establishing the quality management
system through project QA/QC plan
•Having responsibility to assure that all project activities
affecting quality are in compliance with the plan.
•Establishing objectives of continual improvement.
•Ensuring surveillance, evaluation and inspection of
materials.
•Administering non conformity with respect to material and
work execution.
•Determining, collecting and analyzing appropriate data to
demonstrate the suitability and effectiveness of the quality
management system.
•Coordination with the Engineers on all QA/QC matters.
•Production of material and laboratory testing record
6 Site Engineer 2 •Preparation of work procedures
•Document and drawing control.
•Coordination with QA/QC department regarding
inspection and testing
•Check and review of progress schedule.
•Control of manpower and equipment
•Coordination with design and planning department
•Assisting the Construction manager in any aspect
regarding engineering matter.
7 Surveyor 2 •Create the miniature of the construction plans that would
serve as the source of the site plans
•Keep in touch with the engineering and design personnel’s.
•Responsible/in charge for all construction layout and
survey documentation,
•Provides and maintains horizontal and vertical survey
control by use of a level, total station, etc. Including
organized documentation of survey notes.
•Assists in the preparation of final records for the project,
including as-built.
•Works with site engineer/foreman to ensure structures are
built in conformance with the design alignment and
contractual requirements.
• Responsible for tunnel deformation monitoring and
ground settlement monitoring.
7

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

8 Safety Officer 1 •Avoid all personal injuries during the execution of the
Project by targeting to Zero LTI.
•Ensure that all personnel employed on the Project are
competent to carry out their designated tasks
Safely by supporting continuous HSE training, adequate
HSE measures, instruction and supervision.
•Create positive health, safety and environment attitudes
and perceptions at all levels of the Site organization, and to
raise health, safety and environmental awareness in general.
•Implement a training program that supports the
achievement of personnel competency in relation to Health
and Safety.
•Continually monitor and improve HSE performance
9 Environment Officer 1 •Complete the site work without any significant damage to
environment such as flora, fauna, natural water resources
and etc.,
•Complete the site work without incurring any significant
property damage to permanent or temporary facilities.
•Implement a training program that supports the
achievement of personnel competency in relation to the
Environment
•Carry out all operations related to construction and
commissioning with the health and safety of personnel and
the impact on the environment as the prime consideration.
•Continually monitor and improve Environment
performance
10 Forman 3
11 Blasting workers 6
12 Electrician 1
13 Drivers 6
14 Machine Operators 6
15 General Labor 12

4.0 Documents to be referenced with this method statement

List of relevant referenced documents are below

a. Technical Specification
b. Construction drawings
c. Site Safety & Environmental Plan
d. Method Statement for Construction of Tunnel Portal( MS-004)
e. Method Statement for Blasting

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

5.0 Detailed method of carrying out method statement activity

Tunneling work would be inspected regularly to ensure the tunnel and supporting systems remain
stable, intact and work can be carried out safely. The inspection would compare the actual
conditions with those assumed in the original or amended designs, excavation method or safety
management plan and the adequacy of control measures.

Figure3: Construction Sequence


6.0 Temporary Access to Tunnel

Tunnel excavation will be preceded after completion of temporary access and completion of tunnel
portal construction. Ranwediyawa Tunnel construction will be carried out from two direction inlet
and outlet portals. Temporary Access Road will be constructed at both side of the portal and it
would be a ramp and generally having a driveway width about 6m, where practicable to do so and
not less 4m. Longitudinal slope of the Access Road is not more than 15%. The typical cross section
is shown on the Figure.4.
9

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Figure 4: Typical section of the Portal

7.0 Equipment and Material

7.1 Equipment
No. Description Total Specification Note
units
Excavating/Blasting:
1 Drilling machine 10 YT28 For blasting hole
2 Geological drilling rig 1 M13 For fore hole
3 Excavator + Breaker 2 Pc-200
4 Loader 2 2C-30L
5 Explosive Transportation Truck 2 2.5t
Hauling:
6 Wheel Loader 2 ZW140
7 Dump Trucks 8 1 cub

10

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Supporting Works:
8 Welding Machine 3 400A
9 Steel Bar Bender 1 Q32
10 Steel Bar Cutter 1 GQ40
11 Shotcrete Machine 1 TK-961
12 Grout Mixer 2 HFV-50
13 Grout Pump 2 8.0A
Concrete Lining

14 Concrete Mixing Plant 1 S600


15 Concrete Vibrator 4 ø30&ø50
16 Concrete Truck Mixer 3 6m3
17 Concrete pump, including. all pipes 1 -
and fittings
Other Equipment:
18 Air Compressor 2 110kW
19 Submersible Pump 10 7.5kW
20 Generator Set 2 200kW
21 Blower/ Ventilator 4 11kW
22 Water Pump 4 5kW
23 Vibration Monitoring Machine 1 FRZ50

7.2 Material

No. Description Specification


1 Rock Bolts(25mm Grouted rock bolt, yield load 250kN,
Dia) L=2m
2 Steel Mesh 6mm dia , high yield steel ,
fyk500N/mm2
3 Steel Rib Support Lattice girder pantex 70/20/30 or
equivalent , high yield steel,fyk
500N/mm2
4 Cement Comply to specification Section
3.2.2.2

11

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

8.0 Construction Method

According to the given geological profile along the tunnel alignment the same excavation method
cannot be used. The reason is that the rock condition and rock class varies along the alignment
having a range from good rock to very poor rock based on RMR classification. This section
consists of good rock, fair rock, poor rock and very poor rock. As the geology changes specific
excavation methods and supporting techniques are required for each section. Depending on the
ground condition, drill and blast will be used along with mechanical and manual excavation
techniques. Excavation can be done using an excavation machine (Excavator) and in case of hard
rock encounter which cannot be scraped using the excavation machine it can be done according to
conventional drill and blast method
8.1 Blasting Design for Ranwediyawa Tunnel
As per available geological information of Ranwediyawa tunnel rock class is mainly class IV and
V which is known as soft rock. The existing rock condition and thus the parameters for the tunnel
construction are planned based on the guidelines for excavation and supports of 10m span rock
tunnels in accordance with RMR system (after Bieniawski 1989, seen Table:4)
Blasting will be done only in rock which are hard enough to be blasted .The sections having a
RMR more than 20 (except Class V) will be excavated using the conventional drilling and blasting
method as follows
Common steps in drill and blast excavation method are
1. Drilling
2. Charging
3. Blasting and Ventilation
4. Scaling
5. Loading and carrying excavated material
6. Surveying and Geological mapping
7. Tunnel rock supporting
8.2 Drilling
Drilling will be done by using hand held rock drilling machine with an air leg to position to
required orientation. Excavation progress is mainly dependent on drilling pattern and quality of
drilling. A “V – cut” drilling method is proposed. Drilling diameter will be 40mm and the drilling
depth will vary according to the ground/rock condition and it is summarized in the table No.3.
Lookout angle will be approximately 3 degrees outwards the contour.
12

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
8.3 Blast holes arrangement for the drilling pattern
A conceptual drilling geometry and firing sequence is given herewith. The exact drilling pattern
and firing sequence will be changed slightly form the given design based on the initial test blasting
works and exact ground condition when exposed
8.4 Conceptual drilling geometry and firing sequences
The blasting in Ranwediyawa tunnel will be done in two stages as top heading part and benching
part. There is a “V cut” at the middle of the top heading section. The prepared pattern is marked
carefully in the site face by the surveyor and then using jack legs, holes will be drilled with
required angles and length
8.5 Top heading part of the tunnel
Delay sequence is shown using numbers from 0 to 5 and the distances are in meters (Figure No.5)
“V-cut” has proposed in order to obtain a higher progression rate and alternatively a parallel cut
also can be used. Cut hole angles are shown in Degrees and can be changed to suit the advance and
drilling depth.

Figure 5: Drilling and firing sequence of top part

8.6 Lower part or the bench


13

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
Can be done using benching or horizontal drilling – but horizontal drilling is proposed to maintain
the smooth shape of the outer edge of the tunnel (Figure No.6)

Figure 6: Drilling and firing sequence for the lower part


8.7 Charging
Proposed explosives are Emulsion or water gel and ANFO along with Non electric delay
detonators and Detonating cords.
Before charging, approval will be taken from the Engineer by requesting the amount of explosive
material with drawings of relevant blasting pattern. Charging will be done manually. Prior to
charging, hole depth and deviation will be checked.
Perimeter holes will be charged with emulsion/Watergel and Detonating codes and the production
holes will be charged using Emulsion/Water-gel and ANFO. (Charging method is illustrated
below)Explosive cartridges connected with detonators will be inserted into the drill holes by using
a charging stick. This operation will be done in the following sequence:
A. Connecting the detonator cap to the primer and pushing into hole
B. Inserting required charge within the holes behind the primer
C. Pushing charge firmly into blast hole with a charging stick thinner than drilled hole
D. Stemming
For the stemming bagged coarse sand or quarry dust will be used

14

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
For the tunnel works non-electric detonators will be used. Non-electric detonators (Nonel) are
safer as they are not affected by stray electric current. The very common detonator of this type is
Nonel blasting detonator. In Nonel blasting detonator system tubes transferring waves replace
electrical wires. The tube in Nonel system is not sensitive to electrical current, magnetic field, high
temperature, humidity and thunder. In the portal area and close to the inlet Electric delay
detonators will be used in case of unavailability of NONEL.

8.8 Charging method for Perimeter holes

Figure 7: Tunnel blasting charging method of perimeter holes

8.9 Charging method for Production holes

Figure 8: Tunnel blasting charging of production holes

15

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
8.10 Approximate Blasting Parameters

Table 1: Explosive quantity for one round in top part

Table 2: Explosive quantity for one round in lower part


8.11 Sample specific charge calculation
Drilling depth - 1.5m
Face area - 16m2
Rock volume - 24m3
Total explosive amount - 83kg
Specific charge - 3.4kg/m3
(This value is subjected to changes after initial blast according to the site condition and in situ
trials Also the round length will be changed based on the performance of the rock and is
summarized in the Table No.3 )
16

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
As the rock class belongs to class IV and V, New Austrian Tunneling Method will be adapted and
based on the soil/rock mass performance following steps will be followed (if required)
 Applying thin layer of shotcrete immediately after phase advance (temporary support due
to high early strength and rigidity of shotcrete )
 Rock mass deformation will be continuously monitored after each blast
 If gravel clay and sand encounter, a pipe arch canopy will be used which is made of steel
pipes drilled in to the ground and grouted
8.12 Mechanical Excavation – Using excavator/Backhoe Loader or Hammer
An excavator or backhoe loader with suitable dimensions will be adopted for excavation of
completely weathered rock (CW) and this will incorporate manual rectification and trimming
works.
In most of the cases for competent rock which cannot be excavated by excavator, then hammering
can be done, specially for loose jointed and fractured rock. Hammer/Breaker is successful for
tunneling compared to drilling and blasting when the fractured rock structure makes controlled
blasting hard to achieve.

Figure 9: Example for Tunnel Excavation using a Hammer/Breaker

17

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Figure 10: Example for Tunnel Excavation using an Excavator

8.13 Forepoling
Forepoling will be done based on the client’s design. In segments where completely (CW) and
highly weathered (HW) rock encounter and for sections identified as class IV support, grouted
rebar will be installed prior to start excavation to prepare a pipe arch canopy in the crown section.
After installing the rebar and grouting, excavation will be done in multiple drifts of as top heading
to suit the ground condition. Refer the picture below (Figure No.11). Excavation will not be done
until 24 hours after grouting.

18

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Figure 11: Example for Installation of Forepoling


Excavation will be done by mechanical means and manual means.

Chainage and description Excavation method


9+060 – 9+090 Drilling and Blasting, in case of encounter of highly jointed or
RMR -40 fractured rock hammering will be done, maximum advance will
Class IV be 1.7m, forepolling will be done prior to start the excavation
Support Class 4 works as given support class is 4.
Medium Risk Excavation sequence will be top heading and benching
CW – HW
9+060 – 9+130 Mechanical excavation using Breaker and Backhoe loader – In
RMR – 26 case of hard boulder encounter occasional blasting will be done.
Class IV forepolling will be done prior to start the excavation works.
Support Class 4 Maximum advance will be 1.7m. Excavation sequence will be
High Risk top heading or multiple drifts
CW – HW
9+130 – 9+270 Drilling and Blasting, in case of encounter of highly jointed or
RMR 15-40 fractured rock hammering will be done, maximum advance will

19

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Class IV and V be 1.7m, forepolling will be done prior to start the excavation
Support Class 4 works as given support class is 4.
High Risk Excavation sequence will be top heading and benching
HW – MW
9+270 – 9+510 Drilling and Blasting. maximum advance will be 3m.
RMR 41 -80 Excavation sequence will be top heading and benching.
Class II and III – Possibility of full face excavation will be considered if the site
According to RMR condition allows.
Support Class 3
High Risk
SW
9+510 – 9+540 Mechanical excavation using Breaker and Backhoe loader – In
RMR 15 -25 case of hard boulder encounter occasional blasting will be done.
Class V – According to forepolling will be done prior to start the excavation works.
RMR Maximum advance will be 1.7m. Excavation sequence will be
Support Class 4 top heading or multiple drifts
High Risk
HW
9+540 – 9+680 Mechanical excavation using Breaker and Backhoe loader – In
RMR 0-25 case of hard boulder encounter occasional blasting will be done.
Rock Class V – According forepolling will be done prior to start the excavation works.
to RMR Maximum advance will be 1.7m. Excavation sequence will be
Support class 4 top heading or multiple drifts
High Risk
CW – HW
Table 3: Method of excavation for each segment of rock type According to the given
geological profile along the tunnel.

Combination of all above methods will be utilized to suit the site condition where necessary.

20

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Table 4: Guidelines for Excavation support of 10m Span Rock Tunnel in accordance with
RMR system (after Bieniawski 1989)

9.0 Mucking and Disposal of Excavated Materials

Loose material and hard rock fragment can be expected as a result of blasting while constructing of
Ranwediyawa tunnel. Therefore, loose material and hard rock will be separated and transported to
respective disposal/stock file. The mucking (excavated material) out will be done with loaders and
dump trucks. The mucking will be loaded to dump trucks to transport to the designated location or
the disposal yard for storage.
The selection of locations, the design and the management practices relating to the muck disposal
sites are all based on technical, environmental and safety criteria.
The measures adopted during the setup, operation and abandonment phases of the muck disposal
sites will be implemented and also an environmental monitoring plan will be implemented for site
management and use, which will include field inspections, and regular control of entries to the
sites, among other actions.
21

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

10.0 Tunnel Support

The excavation and the installation of support elements will be executed according to the approved
working cycles for respective ground conditions. Applying the tunnel ground support in the form
of rock bolts and shotcrete as determined by the deforming ground as the excavation is carried out
is known as the New Austrian Tunneling Method (NATM).The type and amount of tunnel support
will be installed immediately after excavation is directly related to the Rock Class established by
BIENIAWSKY and the subsequent Support Class as established.
The standard primary support associated with the established rock support classification system is
shown on the Drawings. However, variations from the anticipated rock conditions may imply that
the standard support systems as shown on the Drawings for each rock support class may require
modifications and adjustment during construction will be proposed and as directed and approved
by the Engineer. The support elements will be installed or applied in such a manner and sequence
as to prevent deterioration, disintegration and loosening of the rock mass surrounding the
excavated tunnel. Temporary support within weak rock zones will depend on the geological
conditions encountered and will be installed as foreseen in the respective rock support classes
shown on the relevant rock support Drawings or as directed by the Engineer. Support Classes have
been designed for tunnel sections provided with both shotcrete lining and the watertight concrete
lining to cope with all anticipated rock conditions. Each Support Class defines the permissible
round length and the support measures required in order to achieve equilibrium of the respective
rock mass. The Support Classes are indicated on the construction Drawings.

RMR Support Rock Bolt (25mm Shotcrete Steel sets


diameter, fully grouted)
Class (C20/25)
81~100 1w Grouted rock bolts 250kN 50mm where Generally, no support required except spot bolting
l=2m where required required
61~80 2w 4/3 grouted rock bolts 50mm Non
250kN, l=2m, Distance
3-4m
41~60 3w 5/4 grouted rock bolts 100mm Wire mesh 6/6/150/150,
250kN, l=2m, Distance
2.2-3m
21~40 4w 7/6 grouted rock bolts 150mm -Wire mesh 6/6/150/150,
250kN, l=3m, Distance -Lattice girder pantex 70/20/30 or equivalent where
2.2-2.0 m required
-Forepoling Dia.25mm, l=2.5~3m, c/c=0.2-0.3m, where
required

Table 4: Guidelines for Excavation and Support in Accordance with RMR

22

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

23

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

24

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

10.1 Shotcrete and Wire Mesh


Wet mix shotcrete method will be applied for tunnel protection work. A shotcreting trial will be
conducted as per specification and under engineer’s supervision at site and engineer’s approval
will be obtained prior to permanent shotcrete works. Shotcrete work will be carried out as per
bellow

Figure12: Sequence of Shotcrete Work

25

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
The steel mesh will be placed on the excavated surface where required and it will be fastened back
against expose rock surface to ensure no possibility of retaining air pockets behind shotcrete. The
steel mesh will be 6mm dia, high yield steel fyk 500N/mm2 and arranged in 150mm x 150mm
square grid. Shotcrete will be sprayed by appropriate shotcrete spray machine with skilled people.
The shotcrete grade will be C20/25 grade. Curing measure will be adopted for keep moist for 3
days after shotcreting. Each completed layer of shotcrete will be checked, to the satisfaction of the
Engineer. Repair work will be carryout all hollow, sandy, cracked or any other areas where, in the
opinion of the Engineer. Shotcreting strength will be tested by crushing 100mm diameter of cores
from casted shotcrete panels as per specification. Five cores with a diameter of 100mm and length
not less than 100mm will be drilled from each panel.
10.2 Installation of Rock Bolt
The Engineer’s approval will obtain for the rock bolt and for all the necessary auxiliary material
prior to fully grouted rock bolt construction. And also, the approval will be obtained for the
grouting slurry mix proportion from the Engineer in advance.The scaffoldings and access facilities,
such as ladders, will be arranged and the holes for rock bolt will be marked in accordance with the
approved construction drawings. The deviation of marked location from design will be controlled
within 50mm tolerance. The engineers’ inspection will be called upon after completing the setting
out of holes locations and drilling work will be started after his confirmation.

Preparation

Drilling Hole

Cleaning out the hole by air Compressor


-Approved
material,
Grouting the hole with Cement -Engineer
Grout inspection
the hole
before
grouting and
placing Bolt
Placing the Rock Bolt in the hole

Fixing MS plate and tightening nut


Figure13: Sequence of Installation of Rock Bolts

26

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
Pneumatic drill or Down – the – hole, (DTH) drilling machine will be used to drill the rock bolt
holes in compliance with design length plus additional 100mm and inclination. Diameter of the
bolt hole is between φ+15mm and φ+35mm. The dross in the rock bolt hole will be cleaned with
compressed air as soon as bolt hole drilling completed. Then the hole will be kept clean until
grouting and bolt installation completed.
Grout will be mixed from ordinary Portland cement and clean water. The water-to-cement ratio is
the most important factor in grout which will not be exceeded 0.45 as per engineer’s requirement.
The appropriate grout mix design will be proposed to the Engineer and mix design will be carried
out under engineer’s supervision and confirm the specified strength and a proper workability in
association with the grouting device used.
The influence of additives to the strength development which may use for improving workability
will be tested by grout mortar cub compressive strength testing. Five cubes (50mm) will be
prepared for each compressive strength test and the resultant strength will be the average evaluated
from the 3 remaining values after eliminating of the highest and lowest results.
The grout will be free from segregation and grout will be mixed on site and will be pumped under
appropriate pressure in to the holes and the bolts will be inserted to the center of the drilling holes.
It is important to ensure that the grout mortar is perfectly compacted in the hole to prevent in
accurate results.
Ten cubes (50mm Cubs) of grout mortar will be taken weekly during construction for testing
purpose.
Any remaining void at the exterior end of the drilled hole of a rock bolt assembly will be filled
with grout and the rock bolt secured at the surface with shotcrete.

27

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Figure14: Fully grouted rock bolt. The bolt consists of three parts; rod, face plate and a
bonding.

Rock bolts will be carried out according to the Support Class and will be installed with the lengths
and in the patterns shown on the Drawings for each relevant standard support system which is
decided by engineering geologist after tunnel mapping, unless otherwise directed by the Engineer.
Comprehensive records about details of the installation of rock bolts, such as grout consistency,
drilling depth, length and type of rock bolts, type and time of grouting, time of tightening, special
observations, etc. will be kept for each round and countersigned by the representative of the
Engineer during all rock bolt installation activities.

10.3 Lattice Girders and Steel Ribs


Generally lattice girders are installed at portals and other sections of the tunnel where fore poling
is required and also in sections where the rock mass is fractured to such a degree that drilling of
holes for independent fixation of wire mesh is not possible.

28

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Figure15: Example for Lattice Girders and Steel Ribs on Tunnels

Figure 16: Typical details of lattice girder


29

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
(a.) Steel Girder Processing and Production

Processing Sequence

(b).Operation method
 Rebar and steel section processing:
- The required rebar shall be cut out as per required dimensions according to
bending schedule.
- Adjust the shape of reinforcement bar according to the tunnel curvature as
shown in lattice girder drawing.
 Welding forming:
- all parts of the welded girder shall be assembled according to the
requirements of the drawings.
- The end steel section shall be tightened with connection bolts and steel plate
holes to ensure the accuracy of connection holes of all parts of the girder.
 After the parts of the girder are preliminarily welded and fixed in the mold, the
parts of the girder are uniformly and symmetrically removed from the mold to
avoid the distortion of the girder. According to the welding specification and
design requirements, the steel girder parts shall be welded into shape, and the
welding shall be evenly and symmetrically to reduce the stress and deformation
 acceptance:
- after welding all components of the reinforcement grid, a trial assembly shall
be carried out to check the geometric size of the reinforcement grid, bolt
joints of each component and welding quality, etc.
- After the first truss is qualified and accept, then carry on the batch
production, and carries on the batch acceptance according to the stipulation
sampling.

30

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
(c).Installation of steel girder

Processing Sequence

( d.)Operation method

 Grid erection:

(1) on-site sampling and trial assembly: the steel girder shall be sampled and assembled
in batches. The ground shall be flat and spacious, and only after qualified assembly can
the girder be installed.
(2) After qualified on-site test, the girder shall be placed in the design position and
pre-fixed. The elevation and position of the girder shall be controlled and positioned by
laser instrument.
(3) after the girder is installed and positioned, the outer bolt of the vault shall be
tightened first, and then the inner two bolts shall be tightened. If necessary, the
reinforcement of the same type as the main reinforcement can be used for welding.
 Installation of the outer mesh:

After the girder is installed, the outer mesh shall be installed according to the design
requirements. The processing width of the steel mesh shall be the same as the
construction step distance of the girder. The longitudinal and circumferential lap length of
the steel mesh shall be no less than two grid widths. Between the mesh, mesh and steel
girders, longitudinal connection of steel should be welding binding firm.
 Welding of longitudinal connecting rebar

(1) after the girder is installed and positioned, longitudinal connecting rebar shall be
set as required in the drawings.
(2) Longitudinal connecting bars are distributed along the main ring of the girder,

31

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
which are divided into two inner and outer rows. The spacing between connecting bars
and rings in each row meets the design requirements, and is firmly welded.
(3) Installation of the inner mesh: the inner mesh shall be laid along the main arcing
bars and longitudinal connecting bars on the inner side of the girder and shall be firmly
tied.

Figure 17: Example for Fabricating of Lattice Girder at a Work Shop

32

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
10.4 Tunnel Lining
Steel system formwork shall be used for lining concrete works in Ranwediyawa tunnel. The
formwork model arrangement for tunnel lining is as shown below.

Figure 18: System formwork arrangement in tunnel

Concrete lining shall start after finished the soil excavation and rock blasting works. Because
as per above sketch, there is a limited space after placing the formwork system. It is unable to
travel any dumping truck or machinery within this limited space.
The length of formwork system is 12m. This total length is divided into two segment with 9m
and 3m lengths. The 3m long segment will be used to curve lining works. As well as separate
windows are available in formwork panels to pour the concrete and to other works. Mainly
three numbers of panels are available in sectional view as shown below.
(Refer Attachment 2- System Formwork Panel Arrangement)

33

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Figure 19: Major parts of system formwork arrangement


The concrete pouring windows are located in crest formwork panels and diameter of window
is 125mm. Concrete shall be pumped through those windows by using concrete stationary
pump. Shutter vibrators shall be used to compact the concrete. The inspection and working
windows are located in left and right side of formwork panels. The size of working window is
450mm x 450mm. The formwork system will be moved on rails.
The inspection and working windows shall be closed when the concrete reached the window
bottom level. Water curing shall be used to cure the concrete. Concrete shall be cured for a
period of not less than 14 consecutive days or until the concrete is covered by later
construction, whichever is the shorter period.

11.0 Temporary Facilities for Tunnel Excavation

11.1 Compressed Air Supply for Construction


The compressor air is mainly used for drilling of excavation and rock bolt installation. The mobile
air compressor will be used for air supply. According to the construction process, the mobile air
compressor is arranged in a suitable location. The specific allocation of compressor
air is shown in the follow.

34

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Description Mobile Air Compressor


Location Tunnel Outlet Portal and inlet Portal
3
Capacity m /min 20
Allocation Units 2sets (425HH)

11.2 Water Supply for Construction


A 80 m3 of water tank (water tank 4) shall be built at the ridge of the tunnel portal, a well with a
depth of about 4 m and a diameter of 1 m is excavated near the tunnel portal as the water resource
for construction

Description Water Tank


Location Tunnel Outlet Portal and inlet Portal
Capacity 80m3
Water Pipe Diameter 60mm

11.3 Electricity for Construction


The construction electricity is mainly used for lighting and water drainage. A diesel generator
station is arranged near the tunnel outlet, which is used as power supply for open excavation
construction at the early stage and for construction of tunnel in the later stage. The specific detail is
shown in the following table 5:
Description Capacity Location Electricity Wire Remarks
Diesel 200kW Tunnel outlet Model Length(m)
Generator portal and BV-2x25 1000 Illuminating
inlet Portal line
VV3x120+2x70 500 Power line

11.4 Lighting
Proper Tunnel Lighting Systems will be developed for the Tunneling. The lighting system
complies with the Requirements of BS 6164. This system will be designed with the construction
and tunneling environment in mind.

Apply 400W miner’s lamps near cutting face, as illustrated in longitudinal profile.

35

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Figure20: Cross Sectional View of Lighting and Ventilation Facilities

11.5 Ventilation
A proper ventilation system will be installed for the tunnel which would sufficient capacity to
maintain an adequate supply of uncontaminated air in underground excavations throughout the
tunnel construction period.
And also, tunnel atmosphere will be monitored by a standard atmosphere monitoring system.

36

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Figure21: Example for the Ventilation System

Ventilation calculation
1. Calculate the wind volume according to the maximum number of people working at the same
time in the tunnel
The maximum number of working personnel on the working surface is 6, and the air volume
required by the construction personnel is calculated according to the following formula:
Q1 = Q * M * K = 3 * 10 * 1.15 = 34.5 m3 / min
Where;
Q -- Fresh air requirement per person inside the cave;(3 m3/min per person)
M -- The maximum number of people working in the hole at the same time( 10 person)
K -- Air volume reserve coefficient, take 1.0~1.15, (consider 1.15 here.)
2. Calculate the air volume according to the minimum allowable wind speed in the tunnel
Q2 = 60 * S * v
Where;
S -- Tunnel cross section area, m2,( 13.85m2 for this project);

37

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
V -- Minimum allowable wind speed, (0.15m/min for full section excavation);
Q2=60 * 13.85 * 0.15 = 124.6 m3 / min
3. Calculate the maximum explosive amount used for blasting within the same time in the cave
Q3=5 m * B/T
Where;
Q3 -- quantity required for smoke extraction by blasting, m3/min
M -- Consumption of explosive for a single blasting, kg, take 91.4kg here;
B -- Carbon monoxide volume (L) produced by blasting of 1kg explosive, generally 40;
T -- Ventilation time, take 40min here;
Q3 = 5 * 91.4 * 40/40 = 457 m3 / min
4. Selection of ventilation equipment
4.1 fan volume calculation
Qj= (1+PL/100) Qi= (1+2%*310/100) *457= 485.3m3 /min
Qj- fan calculates air volume
Qi- the operating surface needs air volume
P- Duct wind resistance coefficient
L- Ventilation distance
4.2 fan pressure calculation
The fan pressure is the sum of the frictional resistance and local resistance of the duct
Hf=H friction +HD+H other =RfQjQi/3600+HD+H other
Rf=6.5 alpha L/D5, when D=0.6m, Rf=38.87;When D=0.8m, Rf=9.23.
Hf 457/3600 = 38.87 * 485.3 * + 50 + 60
= 2505.6
5. Fan power calculation
W = QHK / 60 eta
60 * = 485.3 * 2505.6 * 1.05 / (0.8) = 26599.3 w = 26.6 kw
Q- Working air volume of fan
H- Fan operating pressure
K- Power reserve factor
Eta -work efficiency
Ventilation equipment selection of 2x11kw axial fan, ventilation pipe used with 80cm flame
retardant hose.
38

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
11.6 Drain
The seepage ground water from the tunnel will be controlled in systematically to make proper
working area. Proposed ground water controlling is based on to the procedures and specifications
detailed in the section 5 Clause (5.3.7) of the Technical Specification.
After tunnel excavation, if there is a concentrated seepage point on the surface of the surrounding
rock, a half drainage pipe can be arranged along the circumferential direction of the surface of the
surrounding rock, and the water on the top of the tunnel can be directed to the drainage ditch along
the half drainage pipe, rather than dropping randomly. Drainage and half pipe using phi 50 of the
PVC tube is split in two and fix with Ω plastic positioning device. (Refer Figure 17) The invert of
the tunnel is provided with a transverse slope of 2% to discharge water into the temporary drainage
ditch. The section size of the drainage ditch is 20cm*20cm, and the longitudinal slope at the
bottom of the trench is equal to the slope ratio of the tunnel body. Drain longitudinal every 30
meters set up a water pit, 40cm*40cm of the cross section, in order to use water pump drainage.
A sump pit shall be arranged at a suitable location to collect all the drain water. The collected
water will be pumped out with a 7.5kW water pump. The construction wastewater will be
discharged to the sedimentation tank which would be located in a suitable location. Once the water
is clear from the sediment it will be discharged to the ground surface or natural stream channel
after checking the water quality.
During the tunnel excavation through water-bearing area, seepage from the discontinuities is taken
place. A large amount of water which inflows into the tunnel can be affected for lowering of
groundwater table around the project area. Hence, water inflow of tunnel will be recorded as
inflow rate (ℓ/min) during tunnel construction. Reduction of seepage after applying for rock
support also will be noticed.
According to technical specification Section 5.3.4.4 Rock Probe Drilling Ahead of D&B
Excavation, in order to detect cavities, pockets filled with soft and broken material, shear zones,
gauge filled faults and groundwater, probe drilling will be carried out whenever it is required and
subject to the Engineer instruction.
Probe hole will be drilled by means of percussion drilling at the 3 or 9 o’clock position or as
indicated by the Engineer. Probe drilling in advance would always keep a distance of at least 5
meters from the excavation face. The standard probe drilling length is 20 m and hole diameter is
between 48mm and 56mm. Probe drilling would be done only in the presence of contractor’s
geologist who would be recorded all findings.

39

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
Inflowing of groundwater may cause of the weakening of rock joints contact, thus, it may also
weaken the stability of rock mass of the tunnel. Therefore, if an unexpectedly severe influx of
water is encountered from faults or fracture zones, it will be reduced the inflow of water by
grouting as directed by the Engineer.
Sufficient water samples will be collected from water flowing out of fissures or faults and
chemically analyzed in order to determine the aggressivity of the water towards concrete in
accordance with the requirement of Section 3 [Concrete Works] of the Specification. The pH and
temperature of the water will be measured directly in the tunnel where the sample is taken.

Figure22: Cross Sectional View of Tunnel Draining System


11.7 Communication
A proper wireless communication system would be arranged to allow person to use it efficiently
and effectively for;
 distribute information and instructions „
 control operations like lifting, transporting people, materials and plant „
 Monitor plant and systems like ventilation and help co-ordinate maintenance, and

40

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 manage an emergency including contacting emergency services.


The communication system may also be used to pass information on safety-related matters like
plant-condition, instrumentation and atmospheric monitoring and fire alarms.
The communication system would be linked with;
 major workplaces
 Engineer’s and contractor’s site office
 tunnel portal and faces
 Site offices and safety critical locations like first aid and emergency control rooms.

12.0 Quality Control

12.1 Survey Works


Prior to commencement of excavation, temporary bench mark and reference point to be set up at
each portal area of tunnel. The points shall be places where no damage or movement are expected
and well protect. During tunnel excavation line and level marked by painted nail on the shotcrete
surface, will be setting up as near from the cutting face, which could be based of works.
During underground excavation would be checked to existence of displacement geology condition.
Method of data sampling for displacement is executed once a week.
12.2 Laboratory and Testing
No Activity Type of Test Remarks
1 Rock Bolt Pull Out -10 No of first 100 bolts and from
remaining bolts 5% of the installed bolts.
- The designed axial load will be use as
initial load.
(comply specification Section 5.7.4.2)
2 Shotcrete Material Water shall comply to specification Section
3.11.
Aggregate shall comply to specification
Section 3.11.2.1
Trial Test
Field trails, Horizontal and vertical, comply
to specification Section 3.11.4.2

Compressive strength test, Comply to


specification Section 3.11.4.3
Sampling Test Sample test, Comply to specification
Section 3.11.4.3

3 Concrete Material Comply to specification Section 3.2.2.2

Concrete Test Comply to specification Section 3.5.6


41

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

13.0 Working Programme

Ranwediyawa Tunnel construction will be carried out from two direction inlet and outlet portals.
Basically single workman shift will be implemented at the beginning and double workman shift
will be operated whenever required during tunnel construction as day and night shift which is
subjected to the Engineer’s approval.
Day Shift will be from 7:00 Am to 7:00 Pm
Night Shift will be from 7:00 Pm to 7:00Am

According to above arrangement the working programme will be as follows.

Start Finish
m

Excavation & Support Work at RanwediyawaTunnel 1-Jul-19 16-Jul-20 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20
Ite

1 Inlet Portal Construction and Temporaray Facilities 1-Jul-19 31-Aug-19 1/ 7/ 19-31/ 8/ 19

2 Tunnel Excavation and Support(~310m from Intlet portal) 1-Sep-19 15-Jan-20 1/9/2019 - 15/1/2020
3 Tunnel Lining(~310m from Intlet portal) 16-Jan-20 16-May-20 16/1/2020 - 16/5/2020
4 Outlet Portal Construction and Temporaray Facilities 1-Sep-19 30-Oct-19 1/ 9 / 19 - 3 0 / 10 / 19

5 Tunnel Excavation and Support(~310m from Outlet portal) 1-Nov-19 15-Mar-20 1/11/2019 - 15/3/2010
6 Tunnel Lining(~310m from Outlet portal) 16-Mar-20 16-Jul-20 16/3/2020 - 16/7/2020

14.0 QA/QC Measures

 Site layout strictly according to the design drawing.


 Material shall be strictly in compliance mentioned herein the method statement and design
drawings.
 Raw materials of shotcrete are from approved sources and compliance with requirements.
 Lattice girder fabrication is strictly in accordance with design drawing.
 Lattice girder only from approved suppliers, brands, and in acceptable conditions, free from
dirt, corrosion, grease and oil.
 Rock bolt only from approved suppliers, brands, and in acceptable conditions, free from
dirt, corrosion, grease and oil.
 The shotcrete mix design requirements such as proportions of raw materials including
water cement ratio are strictly followed in concrete batching plant and site.
 Shotcrete spray works are not commenced until the engineer’s final inspection and
confirmation.

42

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
15.0 Inspection and Test Plan for Tunnel Construction

To improve the quality of the work, the proposed inspection and test plan is included as an
attachment (Refer Annexure- 1)

16.0 Environmental Management Plan for Tunnel construction

The Tunneling area consists of paddy land, Home garden, Forest reservation, abandoned land rock
area, irrigation and natural stream as well as surrounded by human settlements. Therefore, it has
been subjected to various human pressures on biological environment for many decades. There are
natural habitats within to the forest area. Also, the proposed project important as a biologically
significant.
The proposed site which is consist of different land fatten with forest area too, Therefore, the
environmental and biological importance is also significant. However, the Constructer proposed all
construction activity to mitigation measures to reduce the environmental issues.

Anticipated Source of Mitigation measures for the identified Alternatives/other


Environmen impact impact remarks
tal Impact
The threat of a. Loss of  Close monitoring of transportation, storage Avoiding the cutting or
spreading of vegetation of borrowing material for the spread of any removing of trees as
alien invasive cover invasive species will be done. Vehicles will much as possible
species b. be covered during transportation.
Spreading
on  The Contractor will follow the Mitigation
invasive measures mentioned in “Material Sourcing”
species (Item 2) under Preconstruction stage
impacts

 Washing the vehicles periodically to prevent


carrying any invasive species will be carried
out.

 All the gravel transporting vehicles will be


covered during transportation. Frequent
checks for invasive species will be
undertaken by the Environmental Specialist
(having a sound ecological background).

 The tree enumeration survey shall be


carried out by PMDSC and the list shall
be submitted to the relevant authorities
through PMU/PIU for required
43

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

approval.

 Only the listed and identified trees as


per the approval granted, that would
disturb the construction activities shall
be removed by the contractor.

 Trees will be removed from the


construction sites before commencement
of construction with prior permission
from the concerned department.

 Compensatory plantation by way of


Re-plantation of at least twice the
number of trees cut will be carried out in
the project area.

 Close monitoring of transportation, storage


of borrowing material for the spread of any
invasive species will be done. Vehicles will
be covered during transportation.
 The Contractor will follow the Mitigation
measures.
 Washing the vehicles periodically to prevent
carrying any invasive species will be done.
 All the gravel transporting vehicles will be
covered during transportation. Frequent
checks for invasive species will be
undertaken by the Environmental Specialist
(having a sound ecological background).

Impacts due Sedimentat


to diverting ion, water  Use of oil/ water separators to extract
existing logging floating oils will be done.
surface  Proper storage of contaminated liquids and
waterways disposal after treatment to bring such liquids
streams within prescribed permissible limits will be
carried out.
 Construction activities near water courses as
far practicable during the dry season will be
restricted.
 On site fuelling area of vehicles and
equipment will be selected away from water
bodies and will be protected by a berm to
prevent runoff from leaving the area.
 A construction material handling protocol
will be prepared and applied.
 Collection of roadway water in a dedicated

44

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
drainage system will be done to separate it
out from the clean water drainage system.
As the tunnel will be open for vehicular
traffic carrying dangerous goods, the
drainage system will consist of a slotted
gutter. This will be connected to the
principal longitudinal drains by gully pits
containing a siphon system
 Water collection basins will be put at each
end of the portals where drainage water will
be collected.
 Implement Proper drainage management
plan with engineering designs.
 To avoid siltation in the waterways
crossing the project site, temporary
drainage paths from construction sites
will not be directly sent to the Streams
without passing through a silt trap
 Implementation of suitable disposal
methods of sediment construction
debris in tune with the local condition
to avoid water logging at construction
site
 Proper drainage and sanitation facilities
will be provided at the construction site

Generation of 1.Vehicle  Identification of infrastructural supports All machinery and


Noise & and needed for the construction programme equipment should be
Vibration machinery well maintained and
due to vehicle operations and ensuring their timely availability
fitted with noise
and machinery
 All construction materials such as sand, reduction
operations 2.
metal, lime, bricks etc. will be transported
Transporta under cover to the site and stored under Less Sound
tion cover at the site. Plastic sheeting (of about machineries use
(Vehicles, 6 mm minimum thickness) will be used
Machineri and held in place with weights, such as old
es) tires or cinder blocks, with the edges of the
sheeting buried, or by the use of other
anchoring systems. This will minimize the
levels of airborne dust.
 Mud patches caused by material
transporting vehicles on the access road
will be immediately cleaned

 Strictly adhere the CEA regulations


Continual water sprinkling will be carried
out in the work and fill areas and the
access road if dust stir is observed. Water
sprinkling will be done more frequently on
the days that are dry and windy (at least
45

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
four time’s day) as the levels of dust can be
elevated during dry periods.

 To reduce noise level in the tunnel and


constructions adjacent to the tunnel it is
necessary to use the soundproofing and
sound-absorbing barriers.
 To provide installation of noise
suppressors at inducing and exhaust in
ventilation systems.
 to travel on predetermined routes and
approaches to strictly comply with the
permissible speed when crossing
settlements, limiting working hours in
time zones designated by local
authorities, in the case of acoustic
emission in a specific direction - to use
acoustic barriers to break the line of
impact from noise source to noise
receiver.
 Construction materials would be stored
in covered stores or enclosed spaces

 Adequate dust suppression measures


such as regular sprinkling of water
around vulnerable areas of the
construction site by suitable means to
control fugitive dust during
construction material handling/over
hauling activities particularly near
habitation

Impact due to  Unstable banks will be protected / Frequent Monitoring


erosion/Slope stabilized by mechanical means such as programs
failures retaining walls.
 The debris material will be disposed in Only the required area
such a manner that waterways, drainage to be cleared
paths would not get blocked. And keeping the
 Drainage paths in LB / RB of the canal will vegetation cover as
be improved / erected to drain rain water much as possible
properly.
 Earth / scupper drains on the road along
the LB canal, will be developed (erected,
deepen & reshaped) to drain rain water
properly.
 Silt traps will be constructed to avoid
siltation into waterways and paddy fields
46

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
where necessary
 To avoid siltation, drainage paths will not
be directed to paddy fields / marshy lands
and they will be kept separated from the
paddy fields / marshy lands when road
lying along paddy fields / marshy lands
 Disposed materials will not be allowed to
wash away during floods
 To avoid erosion of unloaded soil, the
disposal will be leveled once a week in dry
period or regularly during rainy season.
 Water spraying will be done regularly
Air Quality Due to the  Storage areas should be located Identify construction
and dust constructi downwind of the habitation area. activity to small
emissions machineries/ vehicles
on activity
(Vehicles,  Mask and other PPE shall be provided to
the all construction workers.
Machineri
es)  Road transportation vehicles should not
be loaded with bulk materials beyond
the safe-clearance and the materials
should be covered during transportation;

 Disposal of waste, not subject of


frequent loading-unloading activity, to
be protected from the wind by covers;
practice speed restrictions.

 Burning of wastes generated at the


construction sites, work camps and other
project-related activities shall be strictly
prohibited.

 Keep stockpiles moist and cover


vehicles with tarpaulin sheets or other
suitable materials to minimize dust
emission and prevent spillage of
materials (e.g., soil, cement, stone, sand,
aggregates, etc.).

 Artificial ventilation of underground


excavations should be applied at all
stages of tunnel and installation and
construction works

 All operating diesel, petrol construction


machines should be equipped with the
systems of neutralization of exhaust
47

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

gases of engines.

 The amount of air necessary for airing of


the constructed underground
excavations, should be chosen basing on
the condition of non-exceeding the
content of harmful and poisonous gases,
as well a dust of maximum permissible
concentration.

 Air quality monitoring should be carried


out during construction phase. If
monitored parameters are above the
prescribed limit, suitable control
measures shall be taken.

. Leakage of Constructi  Grouting poor quality fractured rock in the Frequent Monitoring
ground on tunnel face will be done. programs
water into the activities  Shot creating and anchor bolting of the
tunnel tunnel face will be done.
. Ground Rock  The contractor carries out crack surveys Frequent Monitoring
vibration, blasting programs
cracks, activities  The complains through GRC will be
foundation attended.
failures
during
tunnel
construction,
rock blasting
Effects on  All archaeological property found during Frequent Monitoring
archaeological works will be treated in accordance with programs
sites national legislation. In the event of the
unexpected discovery of archaeological
objects the Contractor will immediately
cease the activity at the site until further
order from the Supervision Engineer, and
immediately inform the Supervision
Engineer, the Employer, and the local and
archaeological authorities and follow their
directions of Archaeological department
through Engineer/PD of PIU

a. Activity Blasting  In case of finding of mineralized zones Frequent Monitoring


from tunnels activities along the tunnel alignment during programs
may have excavation, The contractor will bring it to
some impact
the notice of the Geological Survey and
on the fossil
finds in the Mines Bureau (GSMB), Sri Lanka

48

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
sedimentary Appropriate blasting design will be adopted
considering safety, blast geometry, free
b. The blasting faces, burden, spacing, initiation pattern and
operations angled holes followed by test blasting and
will
obtaining required approvals
lead to rock
movement,
minor
fragmentations
and vibrations.
Thus directly
impacting the
geology.
Nuisance to  Temporary access will be provided when
the public due permanent access is blocked for
to hindrance construction. When construction work is in
to access,
progress on one side, the other side will be
dust, noise and
traffic issues opened for traffic & properly trained
etc. flagmen will be made available with proper
sign boards for control vehicles. At the end
of each day, the debris that blocked access
path will be cleared away under the
supervision of a supervisor.

 Accesses will be checked regularly (several


times daily) by Contractor HSE personnel
and any problems immediately rectified.

The Contractor with the Site Engineer will


ensure to comply with the mitigatory
measures

Nuisance to Vehicles,  Temporary access will be provided when Identify construction


the public due Machineri permanent access is blocked for activity to small
to hindrance construction. When construction work is in machineries/ vehicles
to access, es
progress on one side, the other side will be
dust, noise
and traffic opened for traffic & properly trained
issues etc. flagmen will be made available with proper
sign boards for control vehicles. At the end
of each day, the debris that blocked access
path will be cleared away under the
supervision of a supervisor.

 Accesses will be checked regularly (several


times daily) by Contractor HSE personnel
and any problems immediately rectified.

49

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
The Contractor with the Site Engineer will
ensure to comply with the mitigatory
measures.

 The Contractor will take all precautions to


Health prevent odour and offensive smell
problem may emanating from chemicals and processes
occur due to applied in construction works or from labor
poor sanitation camps. In a situation when/ where odour or
offensive smell does occur, the Contractor
facilities and
will take immediate action to rectify the
breeding of
situation.
mosquitoes.
Poor solid The Contractor takes responsibility for
waste any compensation involved with any health
management issue arisen out of bad odour and offensive
shall be a smells. To prevent the breeding of vectors,
major concern the labor camps will be kept clean and
hygienic. If there is any outbreak of
disease, then the MOH or PHI of the area
will be informed immediately. PHI and his
staff will be requested for fumigation
anti-mosquito chemicals at regular period
to avoid spreading of Dengue, Malaria etc.

Blockage of  Prior notification to road users during a


movement closure in appropriate local language
across roads (Sinhala /Tamil) will be done.

 Alternate routes with proper signage will


be provided

 Road closure through proper planning will


be minimized.

 Alternate and safe bridges if a longer


period of closure is required will be
provided.

Surface soil
erosion,
siltation into  The debris material will be disposed in
water bodies, such a manner that waterways, drainage
paddy fields & paths would not get blocked.
marshy lands,  Drainage paths in LB / RB of the canal will
blockage of be improved / erected to drain rain water
water ways & properly.
50

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
drainage paths,  Earth / scupper drains on the road along
wash away the LB canal, will be developed (erected,
of disposing deepen & reshaped) to drain rain water
soil materials properly.
during floods  Silt traps will be constructed to avoid
are created siltation into waterways and paddy fields
while handling where necessary
dispose soil &  To avoid siltation, drainage paths will not
other be directed to paddy fields / marshy lands
construction and they will be kept separated from the
waste material paddy fields / marshy lands when road
lying along paddy fields / marshy lands
 Disposed materials will not be allowed to
wash away during floods
 To avoid erosion of unloaded soil, the
disposal will be leveled once a week in dry
period or regularly during rainy season.
 Water spraying will be done regularly
The Contractor with the Site Engineer will
ensure to comply with the mitigatory
measures.

Safety issues  Optimal level of safety in tunnels will be


arrived.
 People will be made to involve in accidents
to rescue themselves
 Appropriate and timely response by
emergency services will be ensured.
 The contractor will prepare site specific
Plan

 Ensure that sufficient fresh air is


supplied at confined work spaces such
as the tunnel and excavation sites.
Re-circulation of contaminated air is not
acceptable. Air inlet filters shall be kept
clean and free of dust and
microorganisms.
 Confined spaces (e.g., tunnel) shall be
provided with safety measures for
venting, monitoring, and rescue
operations, to the extent possible.
 Design of works connected with the use
of explosive materials should be carried
out according to the requirements of
uniform safety rules during the blasting
works.
 Plan of accident elimination should be
developed and approved

51

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 Content of toxic substances in


ventilation emissions should not exceed
the maximum permissible values for
each ingredient according to the norms
established by Sanitary and
Epidemiological Bodies.
 content of harmful substances in the air
of underground excavations and
drainage waters should not exceed
maximum permissible concentration,
 Tunneling, construction, load-lifting,
transport vehicles, mechanisms and
equipment should conform to the state
requirements, the rules for installation
and safe operation, as well as to the
manuals of manufacturers.
 protection of people in the tunnel from
influence of products of burning
(smoke) it should be ensured by timely
evacuation outside through portals or
safe zone (in the next tunnel) through
evacuation passes (linkage), thus
operation of the smoke protection
system if available should be
considered.

Muck disposal  Muck disposal will be done only in the Waste designated at the
and Impact designated areas. site
due to  Soft soil from excavations may be used
construction in road embankments if necessary, after Making the workers
waste aware on the waste
proper treatment.
 Recrement obtained from tunnel management
excavation can be used in production of
aggregates for road making.
 Hard rock can be used in construction
of retaining walls as well as gabion
walls. Reuse of excavated material after
testing their suitability will minimize
requirement surface areas for dumping.
 The debris and spoil shall be disposed
in such a manner that;
(i) waterways and drainage paths
are not blocked
(ii) the disposed material should not
be washed away by runoff an
(iii) should not be a nuisance to the

52

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Health  The construction site will be


protection barricaded at all time in a day with
and labour adequate marking, safety tape,
safety flags, reflectors etc. for safety of
individuals using the site daily
basis. (Items such as parking cones,
lights, tubular markers, orange and
white strips and barricades of a
luminous nature for night visibility
will be procured where deemed
necessary)
 At all times, the Contractor will be
provided safe and convenient
passage for vehicles, pedestrians
and livestock. Work that affects the
use of existing accesses will not be
undertaken without providing
adequate provisions to the prior
satisfaction of the Engineer.
a) Alternative accesses will be
arranged;
b) Nearby pedestrian access will be
arranged (across canals in the case
of bridge reconstruction);
c) Adequate signage for detours
will provided.
 The construction site will be clearly
demarcated by the above means and
restriction of access to public to the
site will help the safety of public.
 Safety signboards will be displayed
at all necessary locations.
 The Contractor will be obtained the
third party insurance to compensate
any damages, injuries caused to the
public or laborers during the
construction period.
 All construction vehicles will be
operated by experienced and
trained operators under supervision.
 Basic on-site safety training will be
conducted for all labourers during
the EMP training prior to the start
of the construction activities.
 All digging and installation work
will be completed in one go, if this
task is not accomplished in the area.
53

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

It will be isolated using luminous


safety tape and barricading
structures surrounding the whole
area.
 Trenches will be progressively
rehabilitated once work is
completed.
 Material loading and unloading
should be done in an area, well
away from traffic and barricaded
 Construction wastes will be
removed within 24 hours from the
site to ensure public safety.
 The procedural and infrastructural
arrangements will be in place to
ensure
Traffic Issues  Use of mouth guard, helmets, Boots
 Erect precautionary sign boards
 All reasonable precautions will be
taken to prevent danger of the
workers and the public from
accidents such as cutting trees,
clearing of site etc.

16.1 Environmental Monitoring Plan

All the rock drilling and blasting works shall be done under the supervision of a qualified Mining
Engineer as per the Contract agreement.
Monitoring on following factors will be done by third party monitoring group accepted by Central
Environmental Authority (CEA) and Geological Survey and Mines Bureau (GSMB);
 Soil erosion
 Disposal waste
 Loss of vegetation cover and Spreading on invasive species
 Surface water
 Ground water
 Noise and vibration
 Fauna and Flora
 Blasting Parameters
 Ground vibration level
54

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 Air blast over pressure levels


 Fly rock distances and Air blast over pressure levels
Monitoring Plan
Impacts Parameters to Frequency of Location of Sampling Monitoring
Monitored Monitoring points responsibility
agency/agencies
Soil erosion Siltation As required by Tunnel and dumping CEA/
Consultant sites area Supervision
Consultant (SC),
PMU, LA
Dumping As required by Tunneling area
Muck disposal Procedure Consultant CEA/
Responses from Supervision
local residents Consultant (SC),
PMU, LA
Loss of Water quantity in As required by Tunneling area
vegetation cover steams, Ponds Consultant CEA/
and Spreading on during dry periods Supervision
invasive species No and frequency Consultant (SC),
of flora observed PMU, LA

Effluent quality As required by Tunneling area


Surface water Water quantity in Consultant CEA/
steams with special Supervision
reference to Consultant (SC),
suspended solids, PMU, LA
PH, BOD, DO
pesticide residual
levels
Ground Water Water Level As required by Tunneling area
Consultant
Noise and Noise levels As required by GSMB Tunneling area CEA/
vibration As instructed by Supervision
GSMB Consultant (SC),
PMU, LA
Ground vibration Vibration level As instructed by GSMB Tunneling area CEA/
level Supervision
Consultant (SC),
PMU,
LA,GSMB
Fly rock Fly rock distance As instructed by GSMB Tunneling area CEA/
distances Supervision
Air blast over Consultant (SC),
pressure levels PMU,
LA,GSMB
Dust Dust emission As required by Tunneling area CEA/
Consultant Supervision
Consultant (SC),
PMU, LA
55

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
17.0 Safety Requirements for Tunnel Construction

17.1 Safety Orientation Course and Employee Registration


a. All employees shall attend the Safety Orientation Course before assigning to any
work
b. They shall be required to attend a basic medical test.
c. They shall be registered with the safety department on the successful completion
of SOC and medical test.
d. They shall be issued with the Site ID No., which would be printed on the Green
Cross Sticker to be pasted on the Helmet.
17.2 Duty Oriented Safety Courses
e. Hazard Forecast
All Supervises and above shall follow a special safety course on Hazard Forecasting and
conducting of Toolbox Meetings.
f. Rock Blasting
All employees involved with the Blasting must follow a special safety course on Blasting
Regulations and practice.
g. Transportation
All employees involved with Transportation must undergo an awareness programme on Transport
Regulations and practice.
 All subcontractors must submit the details of all their staff to the CSCEC safety
department to arrange SOC in Advance. Not a single worker shall be allowed to work on
site without attending the SOC.
 All employees shall be provided with the Personal Protective Equipment
required to perform any particular task and provide overalls.
17.3 General Safety Requirements
 All workers shall be provided with basic Personal Protective Equipment’s.
(Hard Hats (helmets), Safety Shoes or boots, Ear Guards, Goggles, Gloves `Dust Masks and
Overalls)
 Workers work on the height over 2m shall be provided with Safety Belts,
 Well-equipped First Aid Box shall be kept at a convenient location.
 A Lunch Room, Toilets and a Changing Room shall be provided with in the premises...
 Adequate lighting facilities shall be provided and electrical equipment must be in sound
working condition and without electric current leakage.
56

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 Adequate air shall be provided


 All workers who work in the tunnel shall be provided with Emergency hand touches.
 Blasting operation shall be carried out under the supervision of a qualified blaster-blasting
blasting officer).
 Public living around the tunnel shall be informed about the operation and potential hazards.
They shall be made aware of siren alarm procedure.
 Siren alarm shall be whistled as per the following sequence
1. 1st siren alarm when the loading is done, checked and ready for the blast
2. 2nd siren alarm 3 minutes after the first siren alarm
3. Blasting 1 minute after the 2nd siren
4. 3rd siren alarm “all clear” after checking for misfires and road cleaning
 Two flagmen shall be deployed at the road with high visibility safety jackets and radios to
control the traffic.
 Advanced warning signboards shall be erected on the both sides of the road.
(Men at work, Drive slowly. Blasting zone ahead, Heavy equipment’s work ahead
etc.,)
17.4 Safety Procedure
 The face shall be carefully cleared of loose rock, secured and cleaned before starting blast.
 Never drill into boreholes, which contains or may have contains explosive.
 Simultaneous drilling and loading is prohibited.
 The distance between hole being drilled and a hole partly or completely loaded shall under
no circumstance be less than two meter.
 Nobody shall be in front of the drilling rig during the operation.
 The face shall be carefully checked for left-over of any explosives before next drilling
starts. Such inspection shall be done by washing down by water.
 With undetonated or risk of undetonated explosives must be cleared marked.
 Drilling should not take place above holes being loaded. Loose rock may fall down on to
the detonators and explosive.
 Drilling rods which are clogged shall not be used and they must be carefully marked and
not kept with together with rest of the other rods.
 Immediate after the blast, carefully check that the round fired normally before proceeding
further. Undetonated explosive shall be taken care immediately by placing and detonating a

57

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).
new charge in close contact with the undetonated one. If the shooting of undetonated
explosive is unsuccessfully, try to remove it with water under pressure.
 After undetonated explosive have been taken care of, the area shall be carefully checked
again.
 During the loading with electric detonators, the following points must be observed:
 Do not let the leads to the detonators, at any time during the loading; come in contact with
metallic objects
 Do not keep electrical lamps and. electrical pumps too close to the work place during
loading.
 Increased safety during loading is achieved by use of insulator sleeves at the free end of the
leads.
 Under thunder weather and risk of lightning, the procedure is to discontinue all loading
with electric detonators.
 Exhaust emission from vehicle can also cause static electricity buildup and should not be
allowed too close to places. Where detonators are being hooked up.
Note: Effective lightning devices are available. They register flashes of lightning and electricity
in atmosphere.

58

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Annexure 1: Inspection and Test Plan

59

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Annexure 2: System Formwork Panel Arrangement

60

1.0
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Annexure 3: Details and Photos of Machineries

61

1.0

You might also like