STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


As of November 06, 2019

CONTRACT ID # :19KB0026
PROJECT NAME :Road Widening on Specific Location Along Maramag-Maradugao Road - K1562+054 -
K1563+000
LOCATION :Base Camp, Maramag, Bukidnon
CONTRACTOR :RRN Construction

1. Period Covered : June 28, 2019 to November 06, 2019


2. Original Contract Time : 245 CD
3. Date of Effectivity of Contract : June 28, 2019
4. Original Contract Amount : Php 29,392,527.59
5. Revised Contract Amount due to Approved Change : Php 30,936,640.00
Order/Extra Work Order
6. Original Expiry Date : February 27, 2020
7. Revised Expiry Date : none
8. Approved Time Extension : none
9. Shutdown Days due to Suspension of Work : none
10. Approved Time Extension due to VO : none
11. Total Calendar After Time Extension/Suspension : none
12. Contract Time Elapsed To Date : 132 CD
13. Contract Time Elapsed (After Ext. & Suspension) : none
14. Percentage of Time Elapsed : 53.88%
15. Percentage of Planning Work Accomplished : 52.40%
16. Percentage of Actual Work Accomplished : 90.91%
17. Slippage : (+) 38.51%

REMARKS: Project is on-going